LAMAR CR (0901-29-091)

Items: 31

County: LAMAR
Length: N/A
Highway: CR
District: PARIS
Control Number: 0901-29-091
DBE Goal: N/A
Project: BR 2021(303)
Guaranty: N/A
Time: 129 WORKING DAYS
Engineer's Estimate: $583,060.07
Date: 03/04/2022 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (3)
E
Engineer's Estimate
$583,060.07
Over/Under Est: -0.61% -$3,539.32
Over/Under Est: 10.07% $58,716.99
Amt Left: 10.74% $62,256.31
Over/Under Est: 31.95% $186,260.33
Amt Left: 32.75% $189,799.65
Delta: -19.87% -$127,543.34

Bid Items & Bid Tabulations

31 Total 0 of 31
LAMAR  |  CR  |  PARIS  |  0901-29-091  |  03/04/2022  |  $583,060.07  |  BR 2021(303)  |  BRIDGE REPL  |  129 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HODGES AND SON CONSTRUCTION COMPANY, INC.
HIGHWAY 19 CONSTRUCTION LLC
ENCINO LANDSCAPE, INC.
PREPARING ROW
STA 8.000 $1,500.000 $3,000.000 $1,000.000 $3,000.000
EXCAVATION (ROADWAY)
CY 78.000 $8.000 $30.000 $15.000 $20.000
EXCAVATION (CHANNEL)
CY 298.000 $10.000 $20.000 $20.000 $20.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 623.000 $15.000 $20.000 $30.000 $40.000
BROADCAST SEED (TEMP) (WARM)
SY 938.000 $1.500 $1.200 $1.000 $0.150
BROADCAST SEED (TEMP) (COOL)
SY 938.000 $1.500 $1.200 $1.000 $0.150
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 1,876.000 $3.000 $2.000 $1.000 $0.150
VEGETATIVE WATERING
MG 13.000 $20.000 $1.000 $10.000 $1.000
SOIL RETENTION BLANKETS (CL 1) (TY C)
SY 263.000 $1.500 $2.000 $5.000 $4.000
FL BS (CMP IN PLC)(TY A GR 4) (6")
SY 1,543.000 $27.000 $26.000 $24.310 $20.000
CEM STABIL BKFL
CY 80.000 $190.000 $250.000 $180.000 $200.000
DRILL SHAFT (24 IN)
LF 261.000 $250.000 $160.000 $186.000 $250.000
CL C CONC (ABUT)
CY 44.600 $1,000.000 $1,200.000 $1,100.000 $1,100.000
REINF CONC SLAB (SLAB BEAM)
SF 2,600.000 $20.000 $20.000 $16.510 $50.000
PRESTR CONC SLAB BEAM (5SB15)
LF 494.210 $230.000 $255.000 $413.000 $260.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 360.000 $150.000 $150.000 $150.000 $200.000
RAIL (TY T631LS)
LF 248.000 $75.000 $75.000 $54.000 $100.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $13,000.000 $8,000.000 $10,000.000 $25,000.000
MOBILIZATION
LS 1.000 $50,713.000 $52,000.000 $60,000.000 $50,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $2,500.000 $2,000.000 $1,150.000 $2,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 72.000 $33.000 $1.000 $40.000 $50.000
ROCK FILTER DAMS (REMOVE)
LF 72.000 $6.000 $1.000 $10.000 $10.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 266.000 $21.130 $1.000 $25.000 $30.000
CONSTRUCTION EXITS (REMOVE)
SY 266.000 $7.630 $1.000 $5.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 788.000 $2.500 $1.000 $3.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 788.000 $0.620 $1.000 $1.000 $1.000
MTL W-BEAM GD FEN (STEEL POST)
LF 200.000 $25.000 $30.000 $27.000 $30.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $3,000.000 $3,100.000 $2,995.000 $2,600.000
WIRE FENCE (TY C)
LF 255.000 $15.200 $15.000 $17.000 $120.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 1.000 $449.550 $600.000 $350.000 $500.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 24.000 $45.000 $30.000 $35.000 $50.000
Totals: $583,060.070 $579,520.750 $641,777.060 $769,320.400