LAMAR VA (0901-29-090)
Items: 18
County: LAMAR
Length: N/A
Highway: VA
District: PARIS
Control Number: 0901-29-090
DBE Goal: N/A
Project: STP 2019(787)TAPS
Guaranty: N/A
Time: 256 WORKING DAYS
Engineer's Estimate: $1,290,231.65
Date: 10/02/2019 (6 years ago)
Contract Number: N/A
Type: 10-FOOT WIDE SHARED USE PATH ON RAILBANKED CORRIDO
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,290,231.65 | |||
| $1,331,649.70 |
3.21%
$41,418.05
|
|||
| $1,333,949.90 |
3.39%
$43,718.25
|
0.17%
$2,300.20
|
||
| $1,779,177.99 |
37.9%
$488,946.34
|
33.61%
$447,528.29
|
-33.38%
-$445,228.09
|
|
| $1,790,758.25 |
38.79%
$500,526.60
|
34.48%
$459,108.55
|
-0.65%
-$11,580.26
|
|
| $2,324,021.50 |
80.12%
$1,033,789.85
|
74.52%
$992,371.80
|
-29.78%
-$533,263.25
|
E
Engineer's Estimate
$1,290,231.65
1
Awarded
$1,331,649.70
Over/Under Est:
3.21%
$41,418.05
$1,333,949.90
Over/Under Est:
3.39%
$43,718.25
Amt Left:
0.17%
$2,300.20
$1,779,177.99
Over/Under Est:
37.9%
$488,946.34
Amt Left:
33.61%
$447,528.29
Delta:
-33.38%
-$445,228.09
$1,790,758.25
Over/Under Est:
38.79%
$500,526.60
Amt Left:
34.48%
$459,108.55
Delta:
-0.65%
-$11,580.26
$2,324,021.50
Over/Under Est:
80.12%
$1,033,789.85
Amt Left:
74.52%
$992,371.80
Delta:
-29.78%
-$533,263.25