LAMAR VA (0901-29-090)

Items: 18

County: LAMAR
Length: N/A
Highway: VA
District: PARIS
Control Number: 0901-29-090
DBE Goal: N/A
Project: STP 2019(787)TAPS
Guaranty: N/A
Time: 256 WORKING DAYS
Engineer's Estimate: $1,290,231.65
Date: 10/02/2019 (6 years ago)
Contract Number: N/A
Type: 10-FOOT WIDE SHARED USE PATH ON RAILBANKED CORRIDO
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$1,290,231.65
$1,331,649.70
Over/Under Est: 3.21% $41,418.05
$1,333,949.90
Over/Under Est: 3.39% $43,718.25
Amt Left: 0.17% $2,300.20
Over/Under Est: 37.9% $488,946.34
Amt Left: 33.61% $447,528.29
Delta: -33.38% -$445,228.09
Over/Under Est: 38.79% $500,526.60
Amt Left: 34.48% $459,108.55
Delta: -0.65% -$11,580.26
$2,324,021.50
Over/Under Est: 80.12% $1,033,789.85
Amt Left: 74.52% $992,371.80
Delta: -29.78% -$533,263.25

Bid Items & Bid Tabulations

18 Total 0 of 18
LAMAR  |  VA  |  PARIS  |  0901-29-090  |  10/02/2019  |  $1,290,231.65  |  STP 2019(787)TAPS  |  10-FOOT WIDE SHARED USE PATH ON RAIL...  |  256 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SAMMY GIST ENTERPRISES, INC.
WE BUILD, INC.
EAST TEXAS BRIDGE, INC.
HIGHWAY 19 CONSTRUCTION LLC
FNH CONSTRUCTION, LLC
EMBANKMENT (FINAL)(DENS CONT)(TY A)
CY 1,480.000 $25.000 $15.000 $30.990 $25.000 $30.000 $35.000
ROAD GRADER WORK (ORD COMP)
STA 636.000 $150.000 $100.000 $52.840 $450.000 $350.000 $450.000
BROADCAST SEED (TEMP) (WARM)
SY 14,216.000 $0.200 $0.150 $0.210 $0.170 $0.200 $1.000
BROADCAST SEED (TEMP) (COOL)
SY 14,216.000 $0.200 $0.150 $0.210 $0.170 $0.200 $1.000
STRAW/HAY MLCH SEED(PERM)(RURAL)(CLAY)
SY 28,427.000 $0.250 $0.350 $0.500 $0.400 $0.300 $1.000
VEGETATIVE WATERING
MG 711.000 $11.000 $1.000 $25.040 $15.000 $10.000 $50.000
PROOF ROLLING
HR 21.250 $300.000 $1.000 $83.790 $85.000 $100.000 $150.000
FL BS (CMP IN PLC)(TY E, GR4)(2")
SY 70,775.000 $4.000 $5.000 $3.890 $4.500 $4.850 $5.000
FL BS (CMP IN PLC)(TY D GR 4)(4")
SY 84,930.000 $8.000 $8.640 $9.210 $8.500 $10.000 $10.000
CEMENT
TON 59.000 $200.000 $301.000 $291.030 $250.000 $250.000 $200.000
CEMENT TREAT (EXIST MATL) (6")
SY 8,000.000 $4.000 $3.000 $3.690 $5.000 $5.000 $6.000
UNTREAT TIMBER
MBF 0.672 $7,500.000 $12,000.000 $13,691.550 $50,000.000 $20,000.000 $5,000.000
MOBILIZATION
LS 1.000 $80,000.000 $50,000.000 $40,345.830 $155,000.000 $100,000.000 $200,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 16.000 $1,000.000 $1,000.000 $1,420.910 $5,000.000 $3,500.000 $8,500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,515.000 $3.500 $3.000 $4.070 $3.000 $3.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,515.000 $1.000 $1.000 $0.840 $1.000 $1.000 $2.000
REMOVABLE BOLLARD
EA 39.000 $55.000 $150.000 $251.710 $500.000 $500.000 $3,000.000
TREATED TIMBER BOLLARD
EA 100.000 $55.000 $75.000 $111.430 $300.000 $500.000 $1,500.000
Totals: $1,290,231.650 $1,331,649.700 $1,333,949.909 $1,779,177.990 $1,790,758.250 $2,324,021.500