Show Job Controls
Bid Cobra

LAMAR CR (0901-29-081)

Items: 36

County: LAMAR
Length: N/A
Highway: CR
District: PARIS
Control Number: 0901-29-081
DBE Goal: N/A
Project: BR 1402(210)
Guaranty: N/A
Time: 190 WORKING DAYS
Engineer's Estimate: $767,029.22
Date: 08/06/2019 (6 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$767,029.22
$777,276.90
Over/Under Est: 1.34% $10,247.68
Over/Under Est: 16.19% $124,176.98
Amt Left: 14.66% $113,929.30
Over/Under Est: 17.99% $138,000.43
Amt Left: 16.44% $127,752.75
Delta: -1.55% -$13,823.45
Over/Under Est: 18.81% $144,265.78
Amt Left: 17.24% $134,018.10
Delta: -0.69% -$6,265.35
$1,033,003.33
Over/Under Est: 34.68% $265,974.11
Amt Left: 32.9% $255,726.43
Delta: -13.36% -$121,708.33
$1,243,417.50
Over/Under Est: 62.11% $476,388.28
Amt Left: 59.97% $466,140.60
Delta: -20.37% -$210,414.17

Bid Items & Bid Tabulations

36 Total 0 of 36
LAMAR  |  CR  |  PARIS  |  0901-29-081  |  08/06/2019  |  $767,029.22  |  BR 1402(210)  |  BRIDGE REPL  |  190 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HIGHWAY 19 CONSTRUCTION LLC
STATELINE CONSTRUCTION, LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
EAST TEXAS BRIDGE, INC.
PIERCE R & B LLC
FNH CONSTRUCTION, LLC
PREPARING ROW
STA 10.200 $1,500.000 $2,500.000 $900.000 $3,000.000 $3,500.000 $5,500.000 $7,000.000
EXCAVATION (ROADWAY)
CY 469.000 $13.000 $15.000 $18.000 $20.000 $15.000 $22.000 $20.000
EXCAVATION (CHANNEL)
CY 679.000 $25.000 $20.000 $12.000 $20.000 $15.000 $22.000 $30.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 358.000 $25.000 $30.000 $17.000 $20.000 $20.000 $40.000 $50.000
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 2,332.000 $0.250 $1.950 $1.500 $2.000 $1.500 $1.100 $1.000
CELL FBR MLCH SEED(TEMP)(WARM)
SY 1,166.000 $0.100 $1.930 $1.500 $2.000 $1.500 $1.150 $1.000
CELL FBR MLCH SEED(TEMP)(COOL)
SY 1,166.000 $0.100 $2.000 $1.500 $2.000 $1.500 $1.150 $1.000
VEGETATIVE WATERING
MG 29.650 $10.000 $10.000 $100.000 $1.000 $20.000 $45.000 $50.000
SOIL RETENTION BLANKETS (CL 1) (TY C)
SY 1,754.000 $1.400 $2.130 $3.500 $2.000 $3.000 $2.750 $6.500
FL BS (CMP IN PLC)(TY A GR 4) (6")
SY 1,318.000 $12.000 $31.000 $47.500 $30.000 $15.000 $18.500 $25.000
FL BS (CMP IN PLC)(TY A GR 4)(4")
SY 700.000 $12.000 $25.000 $55.000 $25.000 $13.000 $18.500 $25.000
ASPHALT STAB BASE (GR 4)(AC-1.5)
TON 74.000 $60.000 $150.000 $150.000 $120.000 $200.000 $125.000 $200.000
CEM STABIL BKFL
CY 180.000 $200.000 $180.000 $156.590 $250.000 $200.000 $240.000 $350.000
DRILL SHAFT (24 IN)
LF 492.000 $140.000 $134.000 $145.000 $150.000 $190.000 $173.500 $185.000
CL C CONC (ABUT)
CY 73.600 $1,140.000 $850.000 $1,100.000 $1,100.000 $1,000.000 $1,200.000 $1,250.000
REINF CONC SLAB
SF 4,160.000 $18.000 $14.460 $17.000 $24.000 $22.000 $24.000 $17.000
PRESTR CONC SLAB BEAM (5SB15)
LF 470.000 $160.000 $228.000 $210.000 $200.000 $220.000 $295.000 $185.000
PRESTR CONC GIRDER (TX28)
LF 258.000 $160.000 $195.000 $225.000 $200.000 $220.000 $290.000 $185.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 723.000 $130.000 $100.000 $125.000 $120.000 $120.000 $140.000 $150.000
RAIL (TY T631)
LF 114.000 $72.000 $78.000 $85.000 $80.000 $90.000 $85.000 $185.000
RAIL (TY T631LS)
LF 286.000 $65.000 $54.000 $85.000 $80.000 $75.000 $60.000 $200.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $10,000.000 $10,000.000 $12,000.000 $20,000.000 $15,000.000 $8,500.000 $40,000.000
MOBILIZATION
LS 1.000 $66,689.920 $60,000.000 $85,000.000 $80,000.000 $90,000.000 $103,000.000 $120,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $2,500.000 $1,500.000 $1,650.000 $1,500.000 $2,000.000 $2,500.000 $8,500.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 172.000 $25.000 $25.000 $40.000 $5.000 $38.000 $37.000 $30.000
ROCK FILTER DAMS (REMOVE)
LF 172.000 $9.500 $10.000 $20.000 $1.000 $10.000 $10.000 $15.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 234.000 $22.000 $20.000 $9.000 $1.000 $27.000 $26.000 $40.000
CONSTRUCTION EXITS (REMOVE)
SY 234.000 $11.000 $5.000 $2.000 $1.000 $10.000 $9.000 $20.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 24.000 $200.000 $30.000 $65.000 $1.000 $100.000 $75.000 $150.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,580.000 $2.750 $3.000 $3.500 $1.000 $4.000 $3.290 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,580.000 $1.000 $1.000 $1.500 $1.000 $1.000 $1.130 $2.000
MTL W-BEAM GD FEN (STEEL POST)
LF 450.000 $23.000 $19.000 $20.000 $20.000 $21.000 $20.500 $35.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 6.000 $1,185.000 $100.000 $1,100.000 $1,000.000 $1,100.000 $1,005.990 $2,500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $2,300.000 $2,375.000 $2,750.000 $2,400.000 $2,650.000 $2,575.000 $3,000.000
WIRE FENCE (TY C)
LF 1,420.000 $9.000 $15.000 $10.000 $20.000 $12.000 $9.970 $10.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 36.000 $40.000 $29.000 $35.000 $30.000 $35.000 $31.990 $100.000
Totals: $767,029.220 $777,276.900 $891,206.200 $905,029.650 $911,295.000 $1,033,003.330 $1,243,417.500