Show Job Controls
Bid Cobra

LAMAR VARIOUS (0901-00-069)

Items: 21

County: LAMAR
Length: 0.0000 MILES
Highway: VARIOUS
District: PARIS
Control Number: 0901-00-069
DBE Goal: 0.0%
Project: C 901-00-69
Guaranty: $16,000.00
Time: 99 WORKING DAYS
Engineer's Estimate: $823,730.00
Date: 04/08/2026 (2 months ago)
Contract Number: 4263226
Type: BRIDGE MAINTENANCE
Project ID: A00209284
Project Description: FUA EROSION REPAIR
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DARIUS HAGGARD
WILLIE BOLDEN
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (12)
E
Engineer's Estimate
$823,730.00
$734,734.00
Over/Under Est: -10.8% -$88,996.00
Over/Under Est: -5.53% -$45,557.00
Amt Left: 5.91% $43,439.00
$781,028.00
Over/Under Est: -5.18% -$42,702.00
Amt Left: 6.3% $46,294.00
Delta: -0.37% -$2,855.00
Over/Under Est: 7.43% $61,210.00
Amt Left: 20.44% $150,206.00
Delta: -13.30% -$103,912.00
Over/Under Est: 14.64% $120,595.00
Amt Left: 28.53% $209,591.00
Delta: -6.71% -$59,385.00
Over/Under Est: 16.62% $136,929.05
Amt Left: 30.75% $225,925.05
Delta: -1.73% -$16,334.05
Over/Under Est: 19.49% $160,515.00
Amt Left: 33.96% $249,511.00
Delta: -2.46% -$23,585.95
Over/Under Est: 26.44% $217,770.00
Amt Left: 41.75% $306,766.00
Delta: -5.82% -$57,255.00
$1,190,575.10
Over/Under Est: 44.53% $366,845.10
Amt Left: 62.04% $455,841.10
Delta: -14.31% -$149,075.10
Over/Under Est: 45.5% $374,820.00
Amt Left: 63.13% $463,816.00
Delta: -0.67% -$7,974.90
$1,310,540.30
Over/Under Est: 59.1% $486,810.30
Amt Left: 78.37% $575,806.30
Delta: -9.34% -$111,990.30
$1,576,067.00
Over/Under Est: 91.33% $752,337.00
Amt Left: 114.51% $841,333.00
Delta: -20.26% -$265,526.70

Bid Items & Bid Tabulations

21 Total 0 of 21
LAMAR  |  VARIOUS  |  PARIS  |  0901-00-069  |  04/08/2026  |  $823,730.00  |  C 901-00-69  |  BRIDGE MAINT  |  99 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
THE TRUESDELL CORPORATION
JACKSON EXCAVATION, LLC
ROAD DOCTORS LLC
GARRET SHIELDS INFRASTRUCTURE
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
THK CONSTRUCTION LLC
ICOS MANAGEMENT, LLC
PATHFIELD INVESTMENTS LLC
TUCAN CONTRACTING, LLC
SHALOM SERVICES CORPORATION
H. V. CAVER, INC.
PREMIER CONTRACTORS LLC
PREPARING ROW
STA 8.000 $500.000 $2,000.000 $1,000.000 $3,000.000 $500.000 $1,000.000 $1,200.000 $2,140.000 $2,000.000 $2,200.000 $2,250.000 $3,000.000 $15,000.000
EXCAV (CHANNEL)
CY 557.000 $20.000 $30.000 $20.000 $60.000 $40.000 $25.000 $18.000 $32.000 $90.000 $44.000 $25.000 $35.000 $75.000
EXCAV (SPECIAL)
CY 185.000 $30.000 $30.000 $12.000 $150.000 $40.000 $25.000 $18.000 $54.000 $110.000 $44.000 $40.000 $45.000 $150.000
EMBANK (VEH)(OC)(TY B)
CY 467.000 $40.000 $50.000 $20.000 $100.000 $30.000 $30.000 $18.000 $54.000 $90.000 $44.000 $20.000 $45.000 $145.000
EMBANK (VEH)(OC)(TY D)
CY 30.000 $45.000 $50.000 $25.000 $100.000 $30.000 $10.000 $18.000 $107.000 $100.000 $44.000 $35.000 $30.000 $150.000
BACKFILL (TY A OR B)(VEH)
CY 20.000 $50.000 $75.000 $6.000 $40.000 $30.000 $100.000 $18.000 $150.000 $430.000 $66.000 $75.000 $50.000 $100.000
BLOCK SODDING
SY 7.000 $10.000 $200.000 $7.000 $20.000 $10.000 $20.000 $20.000 $107.000 $100.000 $99.000 $300.000 $100.000 $100.000
FLOWABLE BACKFILL
CY 43.000 $300.000 $750.000 $300.000 $300.000 $300.000 $300.000 $400.000 $321.000 $560.000 $220.000 $350.000 $800.000 $600.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 145.000 $150.000 $135.000 $150.000 $110.000 $150.000 $150.000 $155.000 $161.000 $200.000 $220.000 $190.000 $210.000 $280.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 948.000 $150.000 $120.000 $140.000 $110.000 $140.000 $150.000 $155.000 $161.000 $150.000 $198.000 $190.000 $210.000 $280.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 3,649.000 $130.000 $110.000 $140.000 $100.000 $140.000 $150.000 $155.000 $161.000 $150.000 $192.500 $190.000 $210.000 $220.000
GABIONS (3' X 3')(GALV)
CY 115.000 $300.000 $300.000 $400.000 $100.000 $300.000 $250.000 $225.000 $235.000 $360.000 $418.000 $500.000 $395.220 $450.000
CLEAN EXIST CULVERTS
EA 2.000 $800.000 $5,000.000 $500.000 $2,500.000 $1,000.000 $7,500.000 $10,000.000 $5,350.000 $6,000.000 $1,650.000 $3,500.000 $2,500.000 $5,000.000
REMOV STR (PIPE)
LF 16.000 $25.000 $500.000 $7.000 $30.000 $10.000 $50.000 $5.000 $43.000 $60.000 $23.100 $35.000 $60.000 $100.000
MOBILIZATION
LS 1.000 $60,000.000 $26,166.000 $1,000.000 $70,000.000 $50,000.000 $52,000.000 $80,000.000 $50,000.000 $90,000.000 $55,000.000 $100,000.000 $83,000.000 $50,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $2,000.000 $1.000 $1,500.000 $3,000.000 $5,000.000 $7,000.000 $3,633.150 $1.000 $1.000 $3,300.000 $4,500.000 $5,000.000 $1.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $200.000 $3,500.000 $1.000 $1.000 $1,000.000 $3,500.000 $5,000.000 $5,350.000 $1.000 $8,800.000 $2,500.000 $5,000.000 $2,000.000
TMA (STATIONARY)
DAY 6.000 $200.000 $1.000 $10.000 $1.000 $300.000 $300.000 $200.000 $428.000 $1.000 $550.000 $300.000 $275.000 $1,000.000
TMA (MOBILE OPERATION)
HR 65.000 $100.000 $1.000 $10.000 $100.000 $50.000 $100.000 $10.000 $193.000 $1.000 $275.000 $75.000 $70.000 $50.000
DRIFTWOOD REMOVAL
CY 177.000 $60.000 $65.000 $50.000 $100.000 $120.000 $75.000 $30.000 $43.000 $60.000 $55.000 $110.000 $75.000 $200.000
TREE REMOVAL (4" - 12" DIA)
EA 15.000 $100.000 $300.000 $10.000 $1,000.000 $500.000 $200.000 $500.000 $535.000 $200.000 $440.000 $100.000 $400.000 $1,000.000
Totals: $823,730.000 $734,734.000 $778,173.000 $781,028.000 $884,940.000 $944,325.000 $960,659.050 $984,245.000 $1,041,500.000 $1,190,575.100 $1,198,550.000 $1,310,540.300 $1,576,067.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $5,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $9,000.00
Total: $14,000.00