LAMAR BU 271B (0901-00-067)
Items: 19
County: LAMAR
Length: 0.6120 MILES
Highway: BU 271B
District: PARIS
Control Number: 0901-00-067
DBE Goal: 0.0%
Project: F 2026(319)
Guaranty: $18,000.00
Time: 96 WORKING DAYS
Engineer's Estimate: $898,065.30
Date: 02/04/2026 (4 months ago)
Contract Number: 2263031
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Project ID: A00198028
Contract Type: Federal
Project Description: ADA REMEDIATION ON NORTH MAIN ST IN PARIS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DANIEL TAYLOR
ZACHARY SMITH
LAMAR BU 271B (0901-00-067)
Project Name: N/A
Project: F 2026(319)
Length: 0.6120 MILES
Project Type: CONSTRUCTION
Limits From: E PRICE ST
Limits To: MLK DR
Project Description: ADA REMEDIATION ON NORTH MAIN ST IN PARIS
Bidders (13)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$898,065.30 | |||
| $727,152.75 |
-19.03%
-$170,912.55
|
|||
| $753,593.75 |
-16.09%
-$144,471.55
|
3.64%
$26,441.00
|
||
| $772,855.00 |
-13.94%
-$125,210.30
|
6.29%
$45,702.25
|
-2.56%
-$19,261.25
|
|
| $792,260.51 |
-11.78%
-$105,804.79
|
8.95%
$65,107.76
|
-2.51%
-$19,405.51
|
|
| $818,260.00 |
-8.89%
-$79,805.30
|
12.53%
$91,107.25
|
-3.28%
-$25,999.49
|
|
| $829,318.50 |
-7.65%
-$68,746.80
|
14.05%
$102,165.75
|
-1.35%
-$11,058.50
|
|
| $835,784.50 |
-6.93%
-$62,280.80
|
14.94%
$108,631.75
|
-0.78%
-$6,466.00
|
|
| $836,617.50 |
-6.84%
-$61,447.80
|
15.05%
$109,464.75
|
-0.10%
-$833.00
|
|
| $864,899.97 |
-3.69%
-$33,165.33
|
18.94%
$137,747.22
|
-3.38%
-$28,282.47
|
|
| $902,619.00 |
0.51%
$4,553.70
|
24.13%
$175,466.25
|
-4.36%
-$37,719.03
|
|
| $1,031,405.00 |
14.85%
$133,339.70
|
41.84%
$304,252.25
|
-14.27%
-$128,786.00
|
|
| $1,074,530.00 |
19.65%
$176,464.70
|
47.77%
$347,377.25
|
-4.18%
-$43,125.00
|
|
|
13
|
$1,113,655.00 |
24.01%
$215,589.70
|
53.15%
$386,502.25
|
-3.64%
-$39,125.00
|
E
Engineer's Estimate
$898,065.30
1
Awarded
$727,152.75
Over/Under Est:
-19.03%
-$170,912.55
$753,593.75
Over/Under Est:
-16.09%
-$144,471.55
Amt Left:
3.64%
$26,441.00
$772,855.00
Over/Under Est:
-13.94%
-$125,210.30
Amt Left:
6.29%
$45,702.25
Delta:
-2.56%
-$19,261.25
$792,260.51
Over/Under Est:
-11.78%
-$105,804.79
Amt Left:
8.95%
$65,107.76
Delta:
-2.51%
-$19,405.51
$818,260.00
Over/Under Est:
-8.89%
-$79,805.30
Amt Left:
12.53%
$91,107.25
Delta:
-3.28%
-$25,999.49
$829,318.50
Over/Under Est:
-7.65%
-$68,746.80
Amt Left:
14.05%
$102,165.75
Delta:
-1.35%
-$11,058.50
$835,784.50
Over/Under Est:
-6.93%
-$62,280.80
Amt Left:
14.94%
$108,631.75
Delta:
-0.78%
-$6,466.00
$836,617.50
Over/Under Est:
-6.84%
-$61,447.80
Amt Left:
15.05%
$109,464.75
Delta:
-0.10%
-$833.00
$864,899.97
Over/Under Est:
-3.69%
-$33,165.33
Amt Left:
18.94%
$137,747.22
Delta:
-3.38%
-$28,282.47
$902,619.00
Over/Under Est:
0.51%
$4,553.70
Amt Left:
24.13%
$175,466.25
Delta:
-4.36%
-$37,719.03
$1,031,405.00
Over/Under Est:
14.85%
$133,339.70
Amt Left:
41.84%
$304,252.25
Delta:
-14.27%
-$128,786.00
$1,074,530.00
Over/Under Est:
19.65%
$176,464.70
Amt Left:
47.77%
$347,377.25
Delta:
-4.18%
-$43,125.00
13
$1,113,655.00
Over/Under Est:
24.01%
$215,589.70
Amt Left:
53.15%
$386,502.25
Delta:
-3.64%
-$39,125.00
| Subcontractor | Percentage | Amount |
|---|---|---|
| CATOCON, INC. | 1.37% | $9,961.99 |
| STRIPE-A-ZONE, LLC | 1.35% | $9,816.56 |
| DIAMOND ELITE BARRICADES, LLC | 1.25% | $9,089.41 |
| Total: | 3.97% | $28,867.96 |
Bid Items & Bid Tabulations
19
Total
0 of 19
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $8,164.23 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $16,328.46 |
| Total: | $24,492.69 |