LAMAR FM 1497 (0688-03-031)

Items: 63

County: LAMAR
Length: 6.0910 MILES
Highway: FM 1497
District: PARIS
Control Number: 0688-03-031
DBE Goal: 0.0%
Project: STP 2026(784)HES
Guaranty: $16,000.00
Time: 96 WORKING DAYS
Engineer's Estimate: $806,243.00
Date: 06/02/2026 (8 days ago)
Contract Number: 6263032
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00206681
Contract Type: Federal
Project Description: SAFETY TREAT FIXED OBJECTS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DANIEL TAYLOR
ZACHARY SMITH
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$806,243.00
Over/Under Est: -19.58% -$157,877.81
$1,020,536.14
Over/Under Est: 26.58% $214,293.14
Amt Left: 57.4% $372,170.95
$1,140,139.15
Over/Under Est: 41.41% $333,896.15
Amt Left: 75.85% $491,773.96
Delta: -11.72% -$119,603.01
Over/Under Est: 42.38% $341,706.32
Amt Left: 77.05% $499,584.13
Delta: -0.69% -$7,810.17
$1,197,205.92
Over/Under Est: 48.49% $390,962.92
Amt Left: 84.65% $548,840.73
Delta: -4.29% -$49,256.60

Bid Items & Bid Tabulations

63 Total 0 of 63
LAMAR  |  FM 1497  |  PARIS  |  0688-03-031  |  06/02/2026  |  $806,243.00  |  STP 2026(784)HES  |  HAZARD ELIM & SAFETY  |  96 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
THK CONSTRUCTION LLC
RB CONTRACTING, LLC
CDM HOLDINGS
GHB EQUIPMENT COMPANY, L.L.C.
ICOS MANAGEMENT, LLC
PREPARING ROW
STA 86.000 $1,150.000 $700.000 $1,500.000 $1,655.000 $1,500.000 $770.000
REMOV CONC (RIPRAP)
SY 58.000 $15.000 $10.000 $50.000 $125.000 $20.000 $22.000
REMOV CONC (SAWCUT)
LF 30.000 $27.000 $10.000 $50.000 $290.000 $20.000 $28.000
REMOV CONC (MISC)
SY 11.000 $20.000 $10.000 $175.000 $115.000 $20.000 $28.000
EXCAV (CHANNEL)
CY 45.000 $50.000 $10.000 $40.000 $92.000 $50.000 $110.000
EMBANK (VEH)(OC)(TY B)
CY 4,865.000 $22.500 $10.000 $37.000 $41.750 $40.000 $22.000
SPEC EXCAV WORK (HYD EXCAVATOR)
HR 150.000 $200.000 $25.000 $150.000 $415.000 $135.000 $330.000
BROADCAST SEED (TEMP_WARM_COOL)
SY 39,353.000 $0.250 $0.130 $0.300 $0.160 $0.240 $0.160
HYDRO MULCH SEED (PERM_RURAL_CLAY)
SY 19,678.000 $0.450 $0.420 $0.580 $0.490 $0.700 $0.480
VEGETATIVE WATERING
TGL 122.000 $15.000 $1.000 $91.000 $10.000 $25.000 $33.000
CUT & RESTORE CONC PAVING
SY 24.000 $155.000 $150.000 $300.000 $250.000 $225.000 $385.000
CUT & RESTORE ASPH PAVING
SY 56.000 $130.000 $150.000 $150.000 $131.000 $175.000 $302.000
CUT AND RESTORE PAV (FLEX BASE)
SY 51.000 $40.000 $100.000 $100.000 $170.000 $150.000 $220.000
FLOWABLE BACKFILL
CY 32.000 $400.000 $350.000 $300.000 $525.000 $400.000 $302.000
TRENCH EXCAVATION PROTECTION
LF 15.000 $9.320 $5.000 $15.000 $28.000 $140.000 $220.000
TEMPORARY SPL SHORING
SF 540.000 $28.000 $25.000 $20.000 $14.000 $50.000 $22.000
CL C CONC (COLLAR)
EA 7.000 $1,500.000 $1,000.000 $1,000.000 $1,368.000 $1,100.000 $2,200.000
CONC STR REPAIR (EPOXY MORTAR)
SF 20.000 $75.000 $140.000 $200.000 $350.000 $250.000 $275.000
RIPRAP (CONC)(5 IN)
CY 5.000 $600.000 $700.000 $500.000 $1,120.000 $500.000 $990.000
RIPRAP (MOW STRIP)(4 IN)
CY 43.000 $572.000 $700.000 $750.000 $650.000 $500.000 $880.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 39.000 $145.000 $150.000 $150.000 $236.000 $175.000 $198.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 321.000 $160.000 $150.000 $175.000 $184.750 $200.000 $220.000
RC PIPE (CL III)(18 IN)
LF 378.000 $48.000 $50.000 $50.000 $74.750 $100.000 $99.000
RC PIPE (CL III)(24 IN)
LF 70.000 $90.000 $62.280 $80.000 $106.550 $150.000 $121.000
RC PIPE (CL III)(36 IN)
LF 224.000 $140.000 $105.750 $120.000 $151.500 $200.000 $275.000
RC PIPE (CL III)(42 IN)
LF 50.000 $185.000 $132.700 $200.000 $209.100 $350.000 $373.000
RC PIPE (CL III)(48 IN)
LF 24.000 $230.000 $224.800 $275.000 $315.750 $450.000 $484.000
HEADWALL (CH - PW - 0) (DIA= 48 IN)
EA 1.000 $14,500.000 $12,000.000 $10,500.000 $18,592.000 $5,000.000 $27,500.000
SET (TY I)(S= 3 FT)(HW= 3 FT)(6:1)(P)
EA 2.000 $6,468.000 $6,000.000 $14,000.000 $14,336.000 $2,100.000 $19,800.000
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 8.000 $1,500.000 $700.000 $850.000 $815.000 $1,800.000 $1,540.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 27.000 $1,000.000 $700.000 $850.000 $862.000 $1,800.000 $1,760.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 4.000 $2,200.000 $1,025.000 $1,500.000 $1,442.000 $3,500.000 $2,420.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 3.000 $4,800.000 $4,145.150 $7,000.000 $5,799.000 $5,000.000 $9,900.000
SET (TY II) (42 IN) (RCP) (6: 1) (P)
EA 4.000 $9,200.000 $5,416.200 $8,000.000 $6,879.000 $8,000.000 $15,400.000
SET (REMOV & REINSTALL)
EA 4.000 $1,000.000 $250.000 $500.000 $1,036.000 $1,000.000 $2,200.000
REMOV & RE - LAY PIPE (18 IN)
LF 52.000 $50.000 $20.000 $25.000 $39.850 $125.000 $66.000
REMOV & RE - LAY PIPE (36 IN)
LF 120.000 $80.000 $20.000 $25.000 $34.500 $150.000 $88.000
CLEAN EXIST CULVERTS
EA 3.000 $1,500.000 $250.000 $1,000.000 $2,072.000 $3,000.000 $6,600.000
REMOV STR (SET)
EA 23.000 $357.000 $100.000 $100.000 $540.000 $1,000.000 $1,100.000
REMOV STR (HEADWALL)
EA 1.000 $1,000.000 $500.000 $1,000.000 $8,288.000 $1,500.000 $2,750.000
REMOV STR (PIPE)
LF 490.000 $20.000 $5.000 $10.000 $33.900 $40.000 $11.000
MOBILIZATION
LS 1.000 $1.000 $50,000.000 $85,000.000 $75,000.000 $70,000.000 $55,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $5,000.000 $1,728.140 $1,500.000 $5,000.000 $5,000.000 $5,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $12,000.000 $5,000.000 $15,000.000 $7,280.000 $5,000.000 $8,800.000
TMA (STATIONARY)
DAY 40.000 $225.000 $250.000 $375.000 $235.000 $750.000 $275.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 60.000 $60.000 $59.450 $60.000 $61.250 $75.000 $66.000
ROCK FILTER DAMS (REMOVE)
LF 60.000 $12.810 $41.000 $25.000 $30.600 $30.000 $66.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 525.000 $6.000 $5.540 $5.000 $5.100 $10.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 525.000 $1.020 $1.030 $2.000 $1.000 $5.000 $1.000
DRIVEWAYS (BASE)
SY 55.000 $75.000 $25.000 $35.000 $163.000 $50.000 $385.000
TURNOUTS (ACP)
SY 704.000 $65.000 $115.000 $95.000 $80.800 $50.000 $99.000
MTL W-BEAM GD FEN (STEEL POST)
LF 325.000 $26.910 $29.220 $36.000 $29.600 $35.000 $40.000
REMOVE METAL BEAM GUARD FENCE
LF 625.000 $2.300 $2.570 $3.000 $2.050 $15.000 $5.000
REMOVE TERMINAL ANCHOR SECTION
EA 5.000 $140.000 $205.000 $245.000 $204.000 $600.000 $168.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,000.000 $3,254.380 $3,800.000 $3,162.000 $2,500.000 $3,730.000
GUARDRAIL END TREATMENT (REMOVE)
EA 1.000 $200.000 $205.000 $245.000 $204.000 $1,000.000 $550.000
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 2.000 $604.000 $716.480 $950.000 $790.500 $1,000.000 $1,100.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 52.000 $313.000 $371.050 $425.000 $351.900 $375.000 $550.000
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 8.000 $361.000 $418.200 $525.000 $433.500 $650.000 $660.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 1.000 $800.000 $169.130 $850.000 $713.000 $750.000 $1,100.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND
EA 68.000 $30.000 $46.130 $55.000 $44.000 $100.000 $110.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 12.000 $70.000 $20.000 $300.000 $175.000 $200.000 $220.000
CNC CRACK REPAIR (FLOOD)(GRAVITY)
SF 14.000 $50.000 $20.000 $110.000 $125.000 $100.000 $220.000
Totals: $806,243.000 $648,365.190 $1,020,536.140 $1,140,139.150 $1,147,949.320 $1,197,205.920
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $1.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1.00
Total: $2.00