LAMAR US 82 (0045-11-044)

Items: 62

County: LAMAR
Length: N/A
Highway: US 82
District: PARIS
Control Number: 0045-11-044
DBE Goal: N/A
Project: STP 2023(236)HES
Guaranty: N/A
Time: 79 WORKING DAYS
Engineer's Estimate: $2,228,124.60
Date: 12/02/2022 (3 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
DANIEL TAYLOR
ZACHARY SMITH
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$2,228,124.60
$1,751,101.00
Over/Under Est: -21.41% -$477,023.60
Over/Under Est: 3.44% $76,627.82
Amt Left: 31.62% $553,651.42
Over/Under Est: 7.61% $169,621.03
Amt Left: 36.93% $646,644.63
Delta: -4.03% -$92,993.21

Bid Items & Bid Tabulations

62 Total 0 of 62
LAMAR  |  US 82  |  PARIS  |  0045-11-044  |  12/02/2022  |  $2,228,124.60  |  STP 2023(236)HES  |  HAZARD ELIM & SAFETY  |  79 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
H. H. HOWARD & SONS, INC.
D. L. LENNON INCORPORATED - CONTRACTOR
EAST TEXAS BRIDGE, INC.
PREPARING ROW
STA 22.000 $2,875.000 $800.000 $1,567.000 $5,000.000
REMOVING STAB BASE & ASPH PAV (8"-10")
SY 4,818.000 $5.500 $6.250 $21.230 $10.000
EXCAVATION (ROADWAY)
CY 2,500.000 $25.000 $10.000 $16.000 $17.000
SUBGRADE WIDENING (ORD COMP)
STA 22.000 $400.000 $400.000 $1,409.000 $500.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 2,500.000 $30.000 $10.000 $16.000 $20.000
BACKFILL (TY B)
STA 22.000 $175.000 $400.000 $1,409.000 $400.000
ROAD GRADER WORK (ORD COMP)
STA 22.000 $165.000 $400.000 $1,409.000 $600.000
BLOCK SODDING
SY 14,454.000 $7.000 $6.000 $4.230 $6.000
BROADCAST SEED (TEMP) (WARM)
SY 7,227.000 $0.650 $0.300 $0.130 $0.150
BROADCAST SEED (TEMP) (COOL)
SY 7,227.000 $0.650 $0.300 $0.100 $0.150
VEGETATIVE WATERING
MG 87.000 $110.000 $100.000 $60.000 $25.000
PROOF ROLLING
HR 4.000 $150.000 $500.000 $75.000 $100.000
CEMENT
TON 211.000 $200.000 $250.000 $275.000 $275.000
CEMENT TREAT (SUBGRADE)(12")
SY 10,599.000 $4.000 $8.000 $18.000 $4.500
PLANE ASPH CONC PAV(0" TO 12")
SY 89.000 $10.000 $100.000 $67.000 $20.000
PLANE ASPH CONC PAV (0" TO 1 1/2")
SY 482.000 $3.000 $20.000 $28.000 $20.000
CUT & RESTORE ASPH PAVING
SY 39.000 $160.000 $150.000 $200.000 $100.000
CUT AND RESTORE PAV (FLEX BASE)
SY 240.000 $150.000 $50.000 $100.000 $50.000
CONC BOX CULV (6 FT X 5 FT)(EXTEND)
LF 17.000 $900.000 $1,500.000 $700.000 $1,500.000
RC PIPE (CL III)(18 IN)
LF 456.000 $80.000 $60.000 $57.000 $100.000
WINGWALL (PW - 2) (HW=6 FT)
EA 2.000 $15,607.000 $15,000.000 $18,500.000 $22,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 28.000 $880.000 $800.000 $875.000 $1,000.000
REMOV STR (HEADWALL)
EA 2.000 $1,350.000 $5,000.000 $450.000 $1,200.000
REMOV STR (PIPE)
EA 14.000 $400.000 $200.000 $250.000 $700.000
MOBILIZATION
LS 1.000 $177,615.000 $100,000.000 $205,500.000 $235,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $6,000.000 $3,000.000 $9,920.000 $10,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 60.000 $35.000 $60.000 $50.000 $35.000
ROCK FILTER DAMS (REMOVE)
LF 60.000 $10.000 $20.000 $10.000 $12.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 20.000 $60.000 $100.000 $50.000 $100.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 120.000 $5.000 $5.000 $4.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 120.000 $2.000 $5.000 $1.000 $1.000
TURNOUTS (ACP)
SY 62.000 $65.000 $110.000 $110.000 $100.000
RUMBLE STRIPS (SHOULDER)
LF 4,336.000 $2.000 $3.000 $7.000 $1.250
RUMBLE STRIPS (CENTERLINE)
LF 1,829.000 $2.000 $3.000 $7.000 $1.250
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 10.000 $255.000 $500.000 $500.000 $350.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 10.000 $800.000 $1,000.000 $1,500.000 $750.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 5.000 $1,000.000 $1,000.000 $1,900.000 $900.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 2.000 $1,700.000 $2,000.000 $2,500.000 $1,100.000
REMOVE SM RD SN SUP&AM
EA 16.000 $105.000 $500.000 $150.000 $135.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 2.000 $70.000 $500.000 $300.000 $100.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 16,128.000 $1.250 $0.300 $0.250 $0.280
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 16,128.000 $1.250 $0.300 $0.250 $0.280
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,613.000 $3.000 $5.000 $1.750 $2.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 3,500.000 $1.000 $1.250 $1.000 $1.150
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 10.000 $6.500 $15.000 $10.000 $12.000
REFL PAV MRK TY I (W)(ARROW)(090MIL)
EA 4.000 $150.000 $200.000 $150.000 $170.000
REFL PAV MRK TY I (W)(WORD)(090MIL)
EA 4.000 $200.000 $200.000 $160.000 $180.000
REF PAV MRK TY I(W)18"(YLD TRI)(090MIL)
EA 5.000 $80.000 $200.000 $100.000 $120.000
REFL PAV MRK TY I (Y)12"(SLD)(090MIL)
LF 14,094.000 $3.500 $3.250 $3.200 $3.600
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 10,752.000 $2.000 $0.550 $0.500 $0.600
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 10,752.000 $2.000 $0.550 $0.500 $0.600
REFL PAV MRKR TY II-A-A
EA 109.000 $7.500 $5.000 $4.000 $4.500
ELIM EXT PAV MRK & MRKS (4")
LF 16,128.000 $3.500 $0.350 $0.300 $0.350
TRACKLESS TACK COAT
GAL 482.000 $10.000 $6.500 $6.400 $20.000
REINFORMT GRID FOR ASPHALT PVMT OVERLAY
SY 2,409.000 $20.000 $11.000 $14.000 $12.000
D-GR HMA TY-B PG64-22
TON 5,722.000 $140.000 $114.900 $129.900 $155.000
D-GR HMA TY-C SAC-A PG64-22(EXEMPT)
TON 1,735.000 $150.000 $117.620 $132.620 $160.000
D-GR HMA TY-D SAC-A PG64-22(EXEMPT)
TON 121.000 $150.000 $160.000 $160.000 $250.000
BONDING COURSE
GAL 771.000 $5.000 $6.500 $6.400 $15.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $7,500.000 $10,000.000 $22,000.000 $25,000.000
TMA (STATIONARY)
DAY 79.000 $200.000 $300.000 $200.000 $300.000
TMA (MOBILE OPERATION)
HR 40.000 $50.000 $100.000 $85.000 $75.000
Totals: $2,228,124.600 $1,751,101.000 $2,304,752.420 $2,397,745.630