Show Job Controls
Bid Cobra

LAMAR BU 82H (0045-09-114)

Items: 39

County: LAMAR
Length: 1.8300 MILES
Highway: BU 82H
District: PARIS
Control Number: 0045-09-114
DBE Goal: 600.0%
Project: STP 2B25(044)VRU
Guaranty: $33,000.00
Time: 157 WORKING DAYS
Engineer's Estimate: $1,759,908.94
Date: 09/05/2025 (9 months ago)
Contract Number: 9253222
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00193579
Contract Type: Federal
Project Description: INSTALL SIDEWALK
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DANIEL TAYLOR
ZACHARY SMITH
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (9)
E
Engineer's Estimate
$1,759,908.94
$1,345,111.44
Over/Under Est: -23.57% -$414,797.50
Over/Under Est: -15.51% -$272,902.57
Amt Left: 10.55% $141,894.93
Over/Under Est: -10.03% -$176,488.94
Amt Left: 17.72% $238,308.56
Delta: -6.48% -$96,413.63
$1,614,876.50
Over/Under Est: -8.24% -$145,032.44
Amt Left: 20.06% $269,765.06
Delta: -1.99% -$31,456.50
$1,649,861.75
Over/Under Est: -6.25% -$110,047.19
Amt Left: 22.66% $304,750.31
Delta: -2.17% -$34,985.25
Over/Under Est: -3.66% -$64,458.72
Amt Left: 26.05% $350,338.78
Delta: -2.76% -$45,588.47
$1,757,931.00
Over/Under Est: -0.11% -$1,977.94
Amt Left: 30.69% $412,819.56
Delta: -3.69% -$62,480.78
$1,887,110.10
Over/Under Est: 7.23% $127,201.16
Amt Left: 40.29% $541,998.66
Delta: -7.35% -$129,179.10
Over/Under Est: 17.75% $312,432.97
Amt Left: 54.06% $727,230.47
Delta: -9.82% -$185,231.81
Subcontractor Percentage Amount
CATOCON, INC. 5.68% $76,402.33
DIAMOND ELITE BARRICADES, LLC 0.84% $11,298.94
STRIPING TECHNOLOGY, L.P. 0.39% $5,245.93
Total: 6.91% $92,947.20

Bid Items & Bid Tabulations

39 Total 0 of 39
LAMAR  |  BU 82H  |  PARIS  |  0045-09-114  |  09/05/2025  |  $1,759,908.94  |  STP 2B25(044)VRU  |  HAZARD ELIM & SAFETY  |  157 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HIGHWAY 19 CONSTRUCTION LLC
SCOUT 5 CONSTRUCTION LLC
GARRET SHIELDS INFRASTRUCTURE
STX CIVIL
THK CONSTRUCTION LLC
GHB EQUIPMENT COMPANY, L.L.C.
RB CONTRACTING, LLC
TI-ZACK CONCRETE, LLC
O. TREVINO CONSTRUCTION, LLC
PREPARING ROW
STA 91.980 $2,100.000 $750.000 $2,800.000 $500.000 $1,000.000 $650.000 $420.000 $700.000 $687.500 $417.000
PREP ROW (TREE REMOVE) (12"-24" DIA)
EA 19.000 $2,000.000 $1,000.000 $1,275.000 $1,500.000 $500.000 $880.000 $960.000 $1,200.000 $1,045.000 $953.000
PREP ROW (TREE REMOVE) (24"-36" DIA)
EA 16.000 $2,500.000 $1,500.000 $2,200.000 $2,000.000 $1,000.000 $1,650.000 $1,800.000 $2,500.000 $3,630.000 $1,785.000
PREP ROW (TREE REMOVE) (36"-48" DIA)
EA 2.000 $3,500.000 $3,000.000 $4,225.000 $3,000.000 $1,500.000 $2,750.000 $3,000.000 $4,000.000 $10,450.000 $2,930.000
REMOV CONC (DRIVEWAYS)
SY 1,269.000 $25.000 $25.000 $21.310 $40.000 $25.000 $24.000 $32.000 $40.000 $28.750 $51.000
REMOV CONC (SIDEWALK, RAMP OR SUP)
SY 319.000 $22.000 $25.000 $17.760 $40.000 $25.000 $25.000 $32.000 $40.000 $28.590 $47.000
REMOV CONC (CURB RAMP)
SY 144.000 $25.000 $25.000 $16.360 $30.000 $25.000 $25.000 $37.500 $50.000 $31.670 $95.000
RMV (2"-6") TRT/UNTRT BASE & ASPH PAV
SY 72.000 $50.000 $15.000 $10.550 $20.000 $8.000 $10.000 $75.000 $20.000 $33.570 $61.000
EXCAV (SPECIAL)
CY 1,616.000 $30.000 $25.000 $35.000 $20.000 $45.000 $25.000 $75.000 $40.000 $42.330 $115.000
EMBANK (FNL)(OC)(TY B)
CY 471.000 $35.000 $30.000 $27.500 $40.000 $55.000 $25.000 $75.000 $30.000 $9.680 $205.000
BLOCK SODDING
SY 7,645.000 $8.000 $5.000 $14.580 $12.000 $2.500 $6.670 $7.160 $12.000 $7.700 $7.250
VEGETATIVE WATERING
TGL 43.000 $125.000 $100.000 $27.680 $50.000 $1.000 $10.000 $110.000 $100.000 $1.100 $251.000
BRIDGE SIDEWALK
SF 40.000 $150.000 $125.000 $43.600 $200.000 $100.000 $350.000 $125.000 $130.000 $91.030 $745.000
RIPRAP (CONC)(5 IN)
CY 2.000 $950.000 $1,000.000 $497.000 $800.000 $2,000.000 $1,000.000 $1,500.000 $1,500.000 $960.100 $1,100.000
RAIL (HANDRAIL)(TY E)
LF 24.000 $250.000 $300.000 $400.000 $350.000 $250.000 $300.000 $339.230 $300.000 $310.200 $331.000
MOBILIZATION
LS 1.000 $164,104.140 $170,000.000 $10,000.000 $140,000.000 $150,000.000 $150,000.000 $135,000.000 $180,000.000 $177,276.600 $200,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $6,000.000 $5,000.000 $0.010 $5,000.000 $3,800.000 $7,000.000 $6,000.000 $2,000.000 $2,750.000 $15,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $12,000.000 $10,000.000 $15,000.000 $1,000.000 $10,000.000 $25,000.000 $10,000.000 $20,000.000 $1.100 $17,000.000
TMA (STATIONARY)
DAY 100.000 $175.000 $250.000 $0.010 $300.000 $1.000 $300.000 $500.000 $200.000 $1.100 $195.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 20.000 $20.000 $5.000 $4.160 $5.000 $10.000 $82.780 $12.290 $15.000 $1.100 $91.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 20.000 $10.000 $1.000 $1.160 $1.000 $1.000 $26.880 $12.290 $3.000 $1.100 $30.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 220.000 $10.000 $10.000 $6.530 $6.000 $10.000 $6.670 $12.290 $13.000 $1.100 $8.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 220.000 $1.040 $1.000 $1.370 $1.000 $1.000 $2.460 $6.290 $5.000 $1.100 $3.000
CONC CURB & GUTTER (TY II)
LF 253.000 $80.000 $55.000 $34.340 $40.000 $60.000 $60.000 $84.000 $50.000 $60.230 $112.000
DRIVEWAYS (CONC)
SY 1,264.000 $125.000 $110.000 $120.000 $120.000 $150.000 $105.000 $124.000 $200.000 $149.450 $129.000
DRIVEWAYS (ACP)
SY 72.000 $65.000 $75.000 $65.090 $100.000 $130.000 $100.000 $150.000 $150.000 $110.360 $274.000
DRIVEWAYS (BASE)
SY 231.000 $35.000 $35.000 $23.750 $30.000 $70.000 $60.000 $80.000 $60.000 $36.240 $128.000
CONC SIDEWALKS (5")
SY 6,488.000 $95.000 $73.630 $78.660 $100.000 $115.000 $100.000 $90.500 $90.000 $138.340 $97.000
CURB RAMPS (TY 3)
EA 1.000 $3,700.000 $1,800.000 $1,300.000 $3,000.000 $2,500.000 $4,000.000 $7,500.000 $3,500.000 $2,909.400 $3,911.000
CURB RAMPS (TY 7)
EA 42.000 $3,700.000 $1,500.000 $4,150.000 $3,000.000 $2,200.000 $4,000.000 $3,750.000 $3,500.000 $2,909.400 $2,871.000
CURB RAMPS (TY 21)
EA 1.000 $3,900.000 $2,500.000 $3,088.860 $3,000.000 $3,000.000 $4,000.000 $7,500.000 $3,500.000 $2,909.400 $2,871.000
CONC SIDEWALKS (SPECIAL)
SY 2.000 $400.000 $350.000 $139.260 $200.000 $500.000 $1,000.000 $2,500.000 $600.000 $2,686.920 $7,250.000
CONCRETE SIDEWALK (RETAINING WALL)
CY 27.000 $750.000 $1,150.000 $200.000 $1,000.000 $550.000 $500.000 $1,000.000 $500.000 $1,334.900 $1,400.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 12.000 $740.000 $750.000 $713.000 $800.000 $900.000 $1,500.000 $726.000 $1,000.000 $665.500 $710.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 30.000 $650.000 $350.000 $470.000 $500.000 $100.000 $1,000.000 $714.000 $1,000.000 $654.500 $697.000
INSTL OM SM RD SIGN (1-OM-CON)Y
EA 14.000 $15.000 $750.000 $15.000 $20.000 $40.000 $100.000 $30.900 $50.000 $27.500 $30.500
INSTL OM SM RD SIGN (1-OM-CON)R
EA 34.000 $15.000 $750.000 $13.000 $20.000 $40.000 $100.000 $30.900 $50.000 $27.500 $30.500
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 105.000 $8.000 $30.000 $7.080 $25.000 $12.000 $26.880 $53.150 $55.000 $33.000 $29.500
PAV SURF PREP FOR MRK (24")
LF 105.000 $4.000 $20.000 $1.030 $25.000 $8.000 $26.880 $41.150 $30.000 $22.000 $29.500
Totals: $1,759,908.940 $1,345,111.440 $1,487,006.370 $1,583,420.000 $1,614,876.500 $1,649,861.750 $1,695,450.220 $1,757,931.000 $1,887,110.100 $2,072,341.910
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $16,410.41
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $32,820.83
Total: $49,231.24