LA SALLE VARIOUS (0922-20-031)
Items: 24
County: LA SALLE
Length: 0.0000 MILES
Highway: VARIOUS
District: LAREDO
Control Number: 0922-20-031
DBE Goal: 0.0%
Project: C 922-20-31
Guaranty: $38,000.00
Time: 70 WORKING DAYS
Engineer's Estimate: $966,017.14
Date: 01/07/2026 (5 months ago)
Contract Number: 1263224
Type: STATE PARK IMPROVEMENTS
Project ID: A00211280
Project Description: TEXAS PARK AND WILDLIFE IMPROVEMENTS ALONG THE LIMITS OF THE CHAPARRAL WMA
Mail/Deliver Bids To: N/A
MISAEL AGUILAR
ANGEL MARTINEZ
LA SALLE VARIOUS (0922-20-031)
Project Name: N/A
Project: C 922-20-31
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: CHAPARRAL WMA DR.
Limits To: .
Project Description: TEXAS PARK AND WILDLIFE IMPROVEMENTS ALONG THE LIMITS OF THE CHAPARRAL WMA
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$966,017.14 | |||
| $714,669.37 |
-26.02%
-$251,347.77
|
|||
| $737,876.70 |
-23.62%
-$228,140.44
|
3.25%
$23,207.33
|
||
| $767,925.85 |
-20.51%
-$198,091.29
|
7.45%
$53,256.48
|
-4.07%
-$30,049.15
|
|
| $791,596.52 |
-18.06%
-$174,420.62
|
10.76%
$76,927.15
|
-3.08%
-$23,670.67
|
|
| $846,263.50 |
-12.4%
-$119,753.64
|
18.41%
$131,594.13
|
-6.91%
-$54,666.98
|
|
| $935,516.80 |
-3.16%
-$30,500.34
|
30.9%
$220,847.43
|
-10.55%
-$89,253.30
|
|
| $941,672.87 |
-2.52%
-$24,344.27
|
31.76%
$227,003.50
|
-0.66%
-$6,156.07
|
|
| $964,588.80 |
-0.15%
-$1,428.34
|
34.97%
$249,919.43
|
-2.43%
-$22,915.93
|
E
Engineer's Estimate
$966,017.14
1
Awarded
$714,669.37
Over/Under Est:
-26.02%
-$251,347.77
$737,876.70
Over/Under Est:
-23.62%
-$228,140.44
Amt Left:
3.25%
$23,207.33
$767,925.85
Over/Under Est:
-20.51%
-$198,091.29
Amt Left:
7.45%
$53,256.48
Delta:
-4.07%
-$30,049.15
$791,596.52
Over/Under Est:
-18.06%
-$174,420.62
Amt Left:
10.76%
$76,927.15
Delta:
-3.08%
-$23,670.67
$846,263.50
Over/Under Est:
-12.4%
-$119,753.64
Amt Left:
18.41%
$131,594.13
Delta:
-6.91%
-$54,666.98
$935,516.80
Over/Under Est:
-3.16%
-$30,500.34
Amt Left:
30.9%
$220,847.43
Delta:
-10.55%
-$89,253.30
$941,672.87
Over/Under Est:
-2.52%
-$24,344.27
Amt Left:
31.76%
$227,003.50
Delta:
-0.66%
-$6,156.07
$964,588.80
Over/Under Est:
-0.15%
-$1,428.34
Amt Left:
34.97%
$249,919.43
Delta:
-2.43%
-$22,915.93
| Subcontractor | Percentage | Amount |
|---|---|---|
| AVILA AND SON'S L.L.C. | 8.03% | $57,387.95 |
| HIGHWAY BARRICADES AND SERVICES, LLC | 2.62% | $18,724.34 |
| CLEAR RESTORATION, LLC | 0.87% | $6,217.62 |
| Total: | 11.52% | $82,329.91 |