KNOX US 82 (0133-02-025)

Items: 68

County: KNOX
Length: N/A
Highway: US 82
District: CHILDRESS
Control Number: 0133-02-025
DBE Goal: N/A
Project: NH 2019(590)
Guaranty: N/A
Time: 204 WORKING DAYS
Engineer's Estimate: $10,556,027.50
Date: 04/03/2019 (7 years ago)
Contract Number: N/A
Type: SUPER 2
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$10,556,027.50
$11,182,988.22
Over/Under Est: 5.94% $626,960.72
$11,326,430.73
Over/Under Est: 7.3% $770,403.23
Amt Left: 1.28% $143,442.51
Over/Under Est: 21.9% $2,311,608.29
Amt Left: 15.06% $1,684,647.57
Delta: -13.61% -$1,541,205.06

Bid Items & Bid Tabulations

68 Total 0 of 68
KNOX  |  US 82  |  CHILDRESS  |  0133-02-025  |  04/03/2019  |  $10,556,027.50  |  NH 2019(590)  |  SUPER 2  |  204 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
A. L. HELMCAMP, INC.
DUININCK, INC.
KIEWIT INFRASTRUCTURE SOUTH CO.
PREPARING ROW
STA 3.000 $2,000.000 $5,000.000 $3,300.000 $3,525.960
REMOVE CONC (WINGWALL)
CY 4.160 $500.000 $425.000 $430.000 $467.120
REMOVING CONC (HEADWALL)
CY 0.980 $600.000 $425.000 $430.000 $467.120
EXCAVATION (SPECIAL)
CY 309.650 $25.000 $15.000 $50.500 $11.680
SUBGRADE WIDENING (DENS CONT)
STA 582.000 $380.000 $1,000.000 $430.000 $262.200
EMBANKMENT (FINAL)(ORD COMP)(TY D)
CY 26.390 $30.000 $60.000 $65.000 $122.740
BACKFILL (TY B)
STA 609.000 $180.000 $260.000 $77.000 $426.550
DRILL SEEDING (PERM) (RURAL) (SANDY)
AC 35.000 $320.000 $415.000 $340.000 $665.350
DRILL SEEDING (TEMP) (WARM)
AC 17.000 $350.000 $365.000 $295.000 $528.690
DRILL SEEDING (TEMP) (COOL)
AC 17.000 $350.000 $425.000 $355.000 $528.690
VEGETATIVE WATERING
MG 1,347.000 $20.000 $16.000 $24.500 $41.410
EMULS ASPH (EROSN CONT)(CSS-1H)
GAL 27,216.000 $3.100 $3.000 $3.700 $3.760
D-GR HMA(SQ) TY-D PG70-22
TON 5,275.000 $115.000 $128.000 $105.000 $128.000
D-GR HMA TY-B PG70-22
TON 11,274.000 $95.000 $128.000 $115.000 $107.000
D-GR HMA TY-D SAC-A PG 76-28
TON 58,302.000 $105.000 $94.000 $107.000 $120.000
PLANE ASPH CONC PAV(0" TO 3")
SY 1,778.000 $3.500 $3.000 $8.200 $7.030
CL C CONC (MISC)
CY 1.360 $1,100.000 $2,100.000 $2,100.000 $2,335.620
RIPRAP (CONC)(CL B)
CY 55.100 $550.000 $435.000 $445.000 $484.640
RIPRAP (STONE PROTECTION)(24 IN)
CY 90.000 $150.000 $140.000 $190.000 $139.030
RIPRAP (MOW STRIP)(4 IN)
CY 99.000 $640.000 $510.000 $805.000 $875.860
CMP (GAL STL 36 IN)
LF 72.000 $75.000 $80.000 $80.500 $87.590
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
LF 55.000 $450.000 $420.000 $425.000 $461.290
CONC BOX CULV (3 FT X 3 FT)(EXTEND)
LF 109.000 $435.000 $420.000 $405.000 $437.930
CONC BOX CULV (4 FT X 2 FT)(EXTEND)
LF 8.000 $510.000 $500.000 $495.000 $537.190
CONC BOX CULV (4 FT X 4 FT)(EXTEND)
LF 60.000 $420.000 $525.000 $545.000 $589.740
CONC BOX CULV (5 FT X 5 FT)(EXTEND)
LF 90.000 $700.000 $600.000 $600.000 $653.970
CONC BOX CULV (6 FT X 6 FT)(EXTEND)
LF 130.000 $750.000 $770.000 $785.000 $852.500
CONC BOX CULV (8 FT X 6 FT)(EXTEND)
LF 30.000 $850.000 $1,000.000 $1,000.000 $1,097.740
CONC BOX CULV (8 FT X 8 FT)(EXTEND)
LF 106.000 $900.000 $1,100.000 $1,100.000 $1,167.810
CONC BOX CULV (5 FT X 6.5 FT)(EXTEND)
LF 20.000 $850.000 $900.000 $915.000 $992.640
WINGWALL (FW - 0) (HW=3 FT)
EA 9.000 $6,100.000 $5,500.000 $5,400.000 $5,839.060
WINGWALL (FW - 0) (HW=4 FT)
EA 8.000 $6,500.000 $5,800.000 $5,700.000 $6,189.400
WINGWALL (FW - 0) (HW=5 FT)
EA 6.000 $6,200.000 $10,000.000 $10,500.000 $11,327.770
WINGWALL (PW - 1) (HW=4 FT)
EA 1.000 $10,000.000 $15,000.000 $15,500.000 $16,933.270
WINGWALL (PW - 1) (HW=6 FT)
EA 4.000 $14,000.000 $9,000.000 $8,900.000 $9,634.440
WINGWALL (PW - 1) (HW=7 FT)
EA 8.000 $19,000.000 $31,000.000 $32,000.000 $35,034.350
WINGWALL (PW - 1) (HW=9 FT)
EA 6.000 $22,000.000 $49,000.000 $50,500.000 $54,887.140
CLEAN EXIST CULVERTS
EA 8.000 $1,800.000 $2,800.000 $2,700.000 $2,919.530
REMOV STR (PIPE)
LF 74.000 $30.000 $14.000 $13.000 $14.010
MOBILIZATION
LS 1.000 $770,000.000 $948,000.000 $850,000.000 $1,129,055.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $11,000.000 $8,000.000 $15,000.000 $30,000.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 3,240.000 $3.500 $6.000 $5.000 $5.450
RUMBLE STRIPS (SHOULDER)
LF 115,588.000 $0.150 $0.120 $0.130 $0.230
RUMBLE STRIPS (CENTERLINE)
LF 61,503.000 $0.300 $0.120 $0.170 $0.280
MTL W-BEAM GD FEN (STEEL POST)
LF 1,404.000 $27.000 $26.000 $29.000 $31.530
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 196.000 $55.000 $82.000 $59.000 $64.230
REMOVE METAL BEAM GUARD FENCE
LF 3,000.000 $4.200 $3.200 $3.200 $3.500
REMOVE TERMINAL ANCHOR SECTION
EA 18.000 $240.000 $370.000 $320.000 $350.340
GUARDRAIL END TREATMENT (INSTALL)
EA 12.000 $2,800.000 $3,200.000 $3,200.000 $3,503.430
GUARDRAIL END TREATMENT (REMOVE)
EA 18.000 $280.000 $370.000 $320.000 $350.340
WIRE FENCE (TY C)
LF 175.000 $20.000 $9.000 $11.000 $9.410
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 14.000 $575.000 $580.000 $940.000 $642.300
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 4.000 $1,300.000 $920.000 $1,300.000 $1,021.840
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 23.000 $600.000 $440.000 $805.000 $490.480
REMOVE SM RD SN SUP&AM
EA 3.000 $150.000 $110.000 $105.000 $116.780
INSTL DEL ASSM (D-SW)SZ (BRF)GF1
EA 36.000 $28.000 $25.000 $43.000 $46.710
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 78.000 $93.000 $48.000 $145.000 $52.550
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 6,125.000 $1.100 $0.600 $1.050 $2.340
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 1,726.000 $1.100 $1.200 $0.860 $1.340
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 10.000 $108.000 $131.000 $215.000 $145.980
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 12,865.000 $0.350 $0.450 $0.380 $0.510
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 123,270.000 $0.350 $0.410 $0.380 $0.470
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 7,250.000 $0.350 $0.450 $0.380 $0.510
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 104,750.000 $0.350 $0.410 $0.380 $0.470
REFL PAV MRKR TY I-C
EA 655.000 $3.400 $4.000 $3.200 $4.380
REFL PAV MRKR TY II-A-A
EA 1,541.000 $3.500 $4.000 $3.200 $4.380
TMA (STATIONARY)
DAY 150.000 $300.000 $300.000 $300.000 $263.420
TMA (MOBILE OPERATION)
HR 32.000 $50.000 $80.000 $96.500 $78.780
Totals: $10,556,027.500 $11,182,988.220 $11,326,430.735 $12,867,635.825