Show Job Controls
Bid Cobra

KLEBERG SH0141 (6412-41-001)

Items: 12

County: KLEBERG
Length: N/A
Highway: SH0141
District: CORPUS CHRISTI
Control Number: 6412-41-001
DBE Goal: N/A
Project: BPM - 641241001
Guaranty: N/A
Time: 51 W
Engineer's Estimate: $224,706.00
Date: 10/18/2022 (3 years ago)
Contract Number: N/A
Type: BRIDGE PREVENTATIVE MAINTENANCE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$224,706.00
$195,810.00
Over/Under Est: -12.86% -$28,896.00
Over/Under Est: 3.16% $7,102.00
Amt Left: 18.38% $35,998.00
Over/Under Est: 49.2% $110,564.00
Amt Left: 71.22% $139,460.00
Delta: -44.63% -$103,462.00
Over/Under Est: 61.02% $137,114.00
Amt Left: 84.78% $166,010.00
Delta: -7.92% -$26,550.00

Bid Items & Bid Tabulations

12 Total 0 of 12
KLEBERG  |  SH0141  |  CORPUS CHRISTI  |  6412-41-001  |  10/18/2022  |  $224,706.00  |  BPM - 641241001  |  BRIDGE PREVENT MAINT  |  51 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
TALBRAN ENTERPRISES LLC
CROSS PLUS CONSTRUCTION, LLC
LUCANIA CONSTRUCTION LLC
SCR CIVIL CONSTRUCTION, LLC
REMOVING CONC (RIPRAP)
SY 460.000 $60.000 $76.000 $44.000 $143.000 $70.000
CEM STABIL BKFL
CY 264.000 $200.000 $200.000 $165.000 $120.000 $260.000
FLOWABLE BACKFILL
CY 4.000 $500.000 $600.000 $550.000 $700.000 $1,500.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 131.000 $200.000 $210.000 $193.000 $350.000 $300.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 114.000 $300.000 $260.000 $275.000 $700.000 $770.000
MOBILIZATION
LS 1.000 $19,686.000 $20,000.000 $27,500.000 $27,000.000 $36,100.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $6,000.000 $4,000.000 $5,500.000 $2,500.000 $6,100.000
DEBRIS REMOVAL (SPOT DEBRIS)
MI 0.010 $10,000.000 $50,000.000 $5,500.000 $400,000.000 $100,000.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 40.000 $50.000 $155.000 $55.000 $250.000 $365.000
REPLACE ELASTOMERIC BEARING PADS
EA 1.000 $20,000.000 $9,000.000 $16,500.000 $8,000.000 $21,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 58.000 $100.000 $5.000 $220.000 $120.000 $100.000
TMA (STATIONARY)
DAY 102.000 $160.000 $5.000 $330.000 $450.000 $300.000
Totals: $224,706.000 $195,810.000 $231,808.000 $335,270.000 $361,820.000