KLEBERG VA (0916-02-022)
Items: 49
County: KLEBERG
Length: N/A
Highway: VA
District: CORPUS CHRISTI
Control Number: 0916-02-022
DBE Goal: N/A
Project: STP 2022(086)SRS
Guaranty: N/A
Time: 102 WORKING DAYS
Engineer's Estimate: $828,114.50
Date: 12/01/2022 (3 years ago)
Contract Number: N/A
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Mail/Deliver Bids To: N/A
LUCIO RAMOS
RENE ZAVALA
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$828,114.50 | |||
| $797,183.75 |
-3.74%
-$30,930.75
|
|||
| $942,095.00 |
13.76%
$113,980.50
|
18.18%
$144,911.25
|
||
| $986,163.60 |
19.09%
$158,049.10
|
23.71%
$188,979.85
|
-4.68%
-$44,068.60
|
|
| $1,062,852.00 |
28.35%
$234,737.50
|
33.33%
$265,668.25
|
-7.78%
-$76,688.40
|
|
| $1,102,742.00 |
33.16%
$274,627.50
|
38.33%
$305,558.25
|
-3.75%
-$39,890.00
|
|
| $1,228,483.05 |
48.35%
$400,368.55
|
54.1%
$431,299.30
|
-11.40%
-$125,741.05
|
E
Engineer's Estimate
$828,114.50
1
Awarded
$797,183.75
Over/Under Est:
-3.74%
-$30,930.75
$942,095.00
Over/Under Est:
13.76%
$113,980.50
Amt Left:
18.18%
$144,911.25
$986,163.60
Over/Under Est:
19.09%
$158,049.10
Amt Left:
23.71%
$188,979.85
Delta:
-4.68%
-$44,068.60
$1,062,852.00
Over/Under Est:
28.35%
$234,737.50
Amt Left:
33.33%
$265,668.25
Delta:
-7.78%
-$76,688.40
$1,102,742.00
Over/Under Est:
33.16%
$274,627.50
Amt Left:
38.33%
$305,558.25
Delta:
-3.75%
-$39,890.00
$1,228,483.05
Over/Under Est:
48.35%
$400,368.55
Amt Left:
54.1%
$431,299.30
Delta:
-11.40%
-$125,741.05
Bid Items & Bid Tabulations
49
Total
0 of 49