Show Job Controls
Bid Cobra

KINNEY US0277 (6350-91-001)

Items: 35

County: KINNEY
Length: N/A
Highway: US0277
District: LAREDO
Control Number: 6350-91-001
DBE Goal: N/A
Project: RMC - 635091001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $299,459.21
Date: 10/09/2019 (6 years ago)
Contract Number: N/A
Type: INSTALL PAVE MARKINGS AND MARKERS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$299,459.21
$285,848.13
Over/Under Est: -4.55% -$13,611.08
Over/Under Est: 6.97% $20,878.81
Amt Left: 12.07% $34,489.89
Over/Under Est: 30.92% $92,603.54
Amt Left: 37.16% $106,214.62
Delta: -22.39% -$71,724.73

Bid Items & Bid Tabulations

35 Total 0 of 35
KINNEY  |  US0277  |  LAREDO  |  6350-91-001  |  10/09/2019  |  $299,459.21  |  RMC - 635091001  |  INSTL PAVE MRK AND MARKERS  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
REPUBLIC TRAFFIC SAFETY, INC.
PAVEMENT MARKINGS INC.
TRP CONSTRUCTION GROUP, LLC
MOBILIZATION (CALLOUT 1)
EA 2.000 $500.000 $1,000.000 $500.000 $3,000.000
MOBILIZATION (CALLOUT 2)
EA 2.000 $500.000 $500.000 $100.000 $3,000.000
MOBILIZATION (CALLOUT 3)
EA 2.000 $500.000 $250.000 $100.000 $3,000.000
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 124.000 $3.000 $1.000 $2.800 $8.500
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 124.000 $3.000 $1.250 $2.900 $8.500
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 10,589.000 $0.750 $0.900 $0.900 $1.000
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 622.000 $5.500 $2.500 $4.900 $3.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 6,923.000 $3.100 $4.500 $4.500 $6.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 116.000 $70.000 $90.000 $80.000 $125.000
REFL PAV MRK TY I(W)(DBL ARROW)(100MIL)
EA 11.000 $130.000 $120.000 $200.000 $170.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 35.000 $130.000 $120.000 $180.000 $140.000
REFL PAV MRK TY I (W)(RR XING)(100MIL)
EA 5.000 $250.000 $500.000 $420.000 $500.000
REF PAV MRK TY I(W)18"(YLD TRI)(100MIL)
EA 124.000 $14.000 $25.000 $12.000 $40.000
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
EA 124.000 $20.000 $45.000 $24.000 $40.000
REFL PAV MRK TY I (Y)4"(DOT)(100MIL)
LF 124.000 $2.750 $1.000 $2.900 $8.500
REFL PAV MRK TY I (Y)8"(SLD)(100MIL)
LF 497.000 $2.000 $0.850 $2.600 $2.150
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 932.000 $3.750 $4.250 $5.400 $6.000
PAVEMENT SEALER 4"
LF 1,569.000 $1.000 $0.250 $1.400 $1.000
PAVEMENT SEALER 8"
LF 1,696.000 $1.100 $0.350 $1.150 $1.000
PAVEMENT SEALER 24"
LF 2,665.000 $1.400 $0.850 $1.200 $1.200
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 62,102.000 $0.250 $0.250 $0.280 $0.350
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 247,752.000 $0.280 $0.240 $0.270 $0.300
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 49,682.000 $0.340 $0.240 $0.300 $0.350
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 298,004.000 $0.280 $0.230 $0.280 $0.300
REFL PAV MRKR TY I-A
EA 1,074.000 $1.350 $4.000 $2.400 $3.500
REFL PAV MRKR TY I-C
EA 1,830.000 $3.500 $4.000 $3.800 $3.500
REFL PAV MRKR TY II-A-A
EA 6,211.000 $3.000 $4.000 $3.200 $3.500
REFL PAV MRKR TY II-C-R
EA 373.000 $5.400 $4.000 $5.400 $3.500
ELIM EXT PAV MRK & MRKS (4")
LF 24,841.000 $0.200 $0.200 $0.300 $0.400
ELIM EXT PAV MRK & MRKS (8")
LF 1,282.000 $1.100 $0.400 $0.800 $0.800
ELIM EXT PAV MRK & MRKS (12")
LF 124.000 $3.500 $0.600 $3.000 $8.500
ELIM EXT PAV MRK & MRKS (24")
LF 4,034.000 $1.500 $1.000 $2.000 $3.500
ELIM EXT PAV MRK & MRKS (ARROW)
EA 69.000 $40.000 $20.000 $40.000 $75.000
ELIM EXT PAV MRK & MRKS (DBL ARROW)
EA 4.000 $120.000 $25.000 $140.000 $250.000
ELIM EXT PAV MRK & MRKS (WORD)
EA 23.000 $65.000 $20.000 $80.000 $75.000
Totals: $299,459.210 $285,848.130 $320,338.020 $392,062.750