Show Job Controls
Bid Cobra

KIMBLE FM2169 (6349-14-001)

Items: 54

County: KIMBLE
Length: N/A
Highway: FM2169
District: SAN ANGELO
Control Number: 6349-14-001
DBE Goal: N/A
Project: RMC - 634914001
Guaranty: N/A
Time: 61 W
Engineer's Estimate: $973,823.00
Date: 11/05/2019 (6 years ago)
Contract Number: N/A
Type: FLOOD DAMAGE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$973,823.00
1
$1,068,115.00
Over/Under Est: 9.68% $94,292.00
$1,294,482.50
Over/Under Est: 32.93% $320,659.50
Amt Left: 21.19% $226,367.50
$1,363,976.00
Over/Under Est: 40.06% $390,153.00
Amt Left: 27.7% $295,861.00
Delta: -5.37% -$69,493.50
$1,407,105.50
Over/Under Est: 44.49% $433,282.50
Amt Left: 31.74% $338,990.50
Delta: -3.16% -$43,129.50
Over/Under Est: 53.17% $517,809.07
Amt Left: 39.65% $423,517.07
Delta: -6.01% -$84,526.57
Over/Under Est: 63.43% $617,740.15
Amt Left: 49.01% $523,448.15
Delta: -6.70% -$99,931.08

Bid Items & Bid Tabulations

54 Total 0 of 54
KIMBLE  |  FM2169  |  SAN ANGELO  |  6349-14-001  |  11/05/2019  |  $973,823.00  |  RMC - 634914001  |  FLOOD DAMAGE  |  61 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
RELMCO, INC.
MPB, INC.
3LW CIVIL LLC
FNH CONSTRUCTION, LLC
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
ACME BRIDGE COMPANY, INC.
PREPARING ROW
STA 10.000 $3,000.000 $10,000.000 $750.000 $1,000.000 $9,500.000 $3,311.670 $8,500.000
PREPARING ROW (TREE) (6" TO 24" DIA)
EA 1.000 $1,500.000 $1,500.000 $750.000 $2,000.000 $2,000.000 $3,590.350 $3,580.000
PREPARING ROW (TREE) (36" TO 48" DIA)
EA 1.000 $3,000.000 $2,500.000 $750.000 $3,000.000 $5,000.000 $10,771.040 $3,580.000
REMOVING CONC (PAV)
SY 2,321.000 $25.000 $15.000 $11.000 $19.000 $25.000 $42.890 $25.800
REMOVING CONC (RIPRAP)
SY 419.000 $20.000 $15.000 $11.000 $23.000 $30.000 $43.940 $38.200
REMOVING CONC (SIDEWALKS)
SY 220.000 $20.000 $15.000 $10.500 $40.000 $30.000 $41.840 $23.400
REMOVING CONC (CURB AND GUTTER)
LF 868.000 $6.500 $12.000 $2.000 $13.000 $15.000 $19.390 $6.800
REMOVING CONC (RETAINING WALLS)
SY 61.000 $30.000 $30.000 $25.000 $100.000 $30.000 $301.810 $142.000
REMOVING CONC (MISC)
CY 91.000 $225.000 $40.000 $55.000 $150.000 $30.000 $303.470 $72.200
REMOVING STAB BASE AND ASPH PAV (4")
SY 2,569.000 $4.000 $2.500 $2.000 $8.000 $12.000 $10.470 $6.100
EXCAVATION (ROADWAY)
CY 73.000 $20.000 $15.000 $20.000 $25.000 $30.000 $48.210 $44.800
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 826.000 $20.000 $18.000 $38.000 $35.000 $50.000 $82.360 $52.800
ROAD GRADER WORK (ORD COMP)
SY 2,569.000 $4.000 $2.500 $2.000 $3.000 $6.500 $8.760 $2.700
FURNISHING AND PLACING TOPSOIL (4")
SY 250.000 $5.000 $10.000 $13.000 $6.000 $10.000 $17.020 $9.600
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 250.000 $1.000 $2.000 $0.400 $2.000 $10.000 $3.820 $4.650
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 250.000 $6.000 $4.000 $2.000 $4.000 $10.000 $6.020 $4.650
PROOF ROLLING
HR 7.000 $80.000 $100.000 $100.000 $1,000.000 $150.000 $129.870 $108.000
PRIME COAT (MC-30)
GAL 511.000 $4.000 $8.000 $6.000 $7.000 $10.000 $10.960 $8.100
LRA PAV TY-I GR-C
TON 539.000 $115.000 $95.000 $127.000 $135.000 $250.000 $144.720 $186.000
CONC PVMT (CONT REINF - CRCP) (8")
SY 2,321.000 $90.000 $78.000 $190.000 $130.000 $150.000 $164.700 $168.000
FLOWABLE BACKFILL
CY 33.000 $500.000 $185.000 $325.000 $300.000 $350.000 $387.370 $458.000
TRENCH EXCAVATION PROTECTION
LF 274.000 $15.000 $100.000 $50.000 $75.000 $5.000 $18.440 $356.000
RETAINING WALL (CONC BLOCK)
SF 595.000 $40.000 $75.000 $45.000 $150.000 $65.000 $71.830 $125.000
CONC STR REPAIR (STANDARD)
SF 25.000 $400.000 $150.000 $180.000 $240.000 $1,000.000 $317.370 $348.000
RIPRAP (CONC)(6 IN)
CY 299.000 $750.000 $900.000 $1,100.000 $750.000 $650.000 $604.810 $800.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 131.000 $150.000 $165.000 $325.000 $210.000 $185.000 $230.260 $444.000
CLEANING AND SEALING EXISTING JOINTS
LF 500.000 $25.000 $30.000 $21.000 $40.000 $50.000 $31.770 $43.600
CMP AR (GAL STL DES 6)
LF 25.000 $500.000 $125.000 $145.000 $200.000 $100.000 $321.080 $236.000
REMOV STR (PIPE)
LF 100.000 $30.000 $20.000 $2.500 $40.000 $30.000 $50.930 $29.600
MOBILIZATION
LS 1.000 $90,000.000 $100,000.000 $110,000.000 $250,000.000 $140,000.000 $199,787.960 $140,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $4,000.000 $9,750.000 $3,000.000 $10,000.000 $8,500.000 $1,413.430 $10,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 449.000 $20.000 $5.000 $6.000 $3.000 $4.000 $13.490 $3.100
TEMP SEDMT CONT FENCE (REMOVE)
LF 449.000 $1.000 $2.000 $0.500 $1.000 $2.000 $3.590 $1.550
CONC CURB & GUTTER (TY II)
LF 1,067.000 $30.000 $22.000 $43.000 $40.000 $35.000 $29.400 $25.000
CONC SIDEWALKS (6")
SY 220.000 $80.000 $60.000 $91.600 $120.000 $65.000 $172.920 $65.000
MTL W-BEAM GD FEN (STEEL POST)
LF 75.000 $65.000 $35.000 $32.000 $32.000 $35.000 $62.220 $100.000
MTL BEAM GD FEN TRANS (TL2)
EA 2.000 $1,100.000 $1,600.000 $1,060.000 $1,200.000 $1,850.000 $3,914.610 $2,100.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,000.000 $1,600.000 $1,175.000 $1,400.000 $1,850.000 $999.610 $2,000.000
MTL BM GD FEN TRANS (NON - SYM)
EA 2.000 $900.000 $1,600.000 $755.000 $1,000.000 $1,850.000 $2,814.610 $2,000.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,000.000 $2,500.000 $2,581.000 $2,700.000 $2,850.000 $2,814.610 $5,100.000
CONDT (PVC) (SCH 80) (4")
LF 100.000 $25.000 $20.000 $25.000 $25.000 $40.000 $12.290 $98.700
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 1.000 $650.000 $522.500 $710.000 $590.000 $850.000 $727.920 $739.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $700.000 $687.500 $725.000 $700.000 $850.000 $727.920 $972.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T-EXAL)
EA 1.000 $1,000.000 $874.500 $1,000.000 $700.000 $850.000 $947.920 $1,240.000
IN SM RD SN SUP&AM TY10BWG(1)SB(P)
EA 1.000 $700.000 $489.500 $710.000 $700.000 $850.000 $947.920 $692.000
IN SM RD SN SUP&AM TY10BWG(1)SB(T)
EA 1.000 $750.000 $643.500 $830.000 $800.000 $850.000 $947.920 $910.000
IN SM RD SN SUP&AM TYFRP(1)UB(P)
EA 2.000 $650.000 $627.000 $830.000 $800.000 $850.000 $617.920 $887.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 2.000 $900.000 $715.000 $815.000 $700.000 $850.000 $617.920 $1,010.000
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 1,100.000 $0.400 $3.570 $3.000 $3.000 $3.000 $3.420 $3.900
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 1,100.000 $0.400 $3.570 $3.000 $3.000 $3.000 $3.420 $3.900
REFL PAV MRKR TY II-A-A
EA 14.000 $4.000 $27.500 $10.000 $6.000 $15.000 $20.230 $29.400
DRAIN INLET CLEANING
EA 14.000 $250.000 $1,800.000 $1,415.000 $445.000 $1,500.000 $1,665.120 $1,500.000
RETROFIT DET WARN SURF(SURF APP OR CIP)
EA 2.000 $900.000 $1,100.000 $500.000 $1,100.000 $2,500.000 $669.610 $709.000
TMA (MOBILE OPERATION)
HR 2.000 $500.000 $500.000 $250.000 $600.000 $2,000.000 $853.660 $311.000
Totals: $973,823.000 $1,068,115.000 $1,294,482.500 $1,363,976.000 $1,407,105.500 $1,491,632.070 $1,591,563.150