KIMBLE IH 10 (0141-08-051)
Items: 44
County: KIMBLE
Length: 0.0000 MILES
Highway: IH 10
District: SAN ANGELO
Control Number: 0141-08-051
DBE Goal: 6.0%
Project: STP 2025(713)HES
Guaranty: $100,000.00
Time: 554 WORKING DAYS
Engineer's Estimate: $7,328,606.88
Date: 05/01/2025 (1 year ago)
Contract Number: 5253036
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00193243
Contract Type: Federal
Project Description: SAFETY TREAT FIXED OBJECTS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JESUS GARCIA
RANDY BAIZA
KIMBLE IH 10 (0141-08-051)
Project Name: N/A
Project: STP 2025(713)HES
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: SUTTON COUNTY LINE
Limits To: 9.885 MILES E OF SUTTON COUNTY LINE
Project Description: SAFETY TREAT FIXED OBJECTS
MENARD US 190 (0825-01-019)
Project Name: 0825-01-019 US 190 SAFETY TREAT FIXED OB
Project: F 2025(714)
Length: 0.0000 MILES
Project Type: SAFETY IMPROVEMENT PROJECTS
Limits From: US 83
Limits To: MCCULLOCH COUNTY LINE
Project Description: SAFETY TREAT FIXED OBJECTS
SUTTON IH 10 (0141-04-040)
Project Name: 0141-04-040 I-10 T1 RAIL UPGRADE
Project: STP 2025(713)HES
Length: 0.0000 MILES
Project Type: SAFETY IMPROVEMENT PROJECTS
Limits From: US 277
Limits To: 7.558 MILES E OF US 277
Project Description: UPGRADE T1 BRIDGE RAIL
EDWARDS US 377 (0201-04-025)
Project Name: 0201-04-025 US 377 SAFETY TREAT FIXED OB
Project: F 2025(714)
Length: 0.0000 MILES
Project Type: SAFETY IMPROVEMENT PROJECTS
Limits From: 30.3 MI N OF VAL VERDE COUNTY LINE
Limits To: SH 55
Project Description: SAFETY TREAT FIXED OBJECTS
MENARD SH 29 (0396-01-043)
Project Name: 0396-01-043 SH 29 SAFETY TREAT FIXED OB
Project: F 2025(714)
Length: 0.0000 MILES
Project Type: SAFETY IMPROVEMENT PROJECTS
Limits From: US 83
Limits To: MASON COUNTY LINE
Project Description: SAFETY TREAT FIXED OBJECTS
REAL SH 41 (0201-06-034)
Project Name: 0201-06-034 SH 41 SAFETY TREAT FIXED OB
Project: F 2025(714)
Length: 0.0000 MILES
Project Type: SAFETY IMPROVEMENT PROJECTS
Limits From: EDWARDS COUNTY LINE
Limits To: KERR COUNTY LINE
Project Description: SAFETY TREAT FIXED OBJECTS
KIMBLE IH 10 (0141-09-074)
Project Name: 0141-09-074 I-10 T1 RAIL UPGRADE
Project: STP 2025(713)HES
Length: 0.0000 MILES
Project Type: SAFETY IMPROVEMENT PROJECTS
Limits From: 9.9 MILES E OF SUTTON COUNTY LINE
Limits To: SOUTH LLANO RIVER
Project Description: UPGRADE T1 BRIDGE RAIL
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$7,328,606.88 | |||
| $5,866,106.92 |
-19.96%
-$1,462,499.96
|
|||
| $6,760,548.37 |
-7.75%
-$568,058.51
|
15.25%
$894,441.45
|
||
| $7,284,507.58 |
-0.6%
-$44,099.30
|
24.18%
$1,418,400.66
|
-7.75%
-$523,959.21
|
|
| $7,886,867.70 |
7.62%
$558,260.82
|
34.45%
$2,020,760.78
|
-8.27%
-$602,360.12
|
|
| $8,061,816.20 |
10%
$733,209.32
|
37.43%
$2,195,709.28
|
-2.22%
-$174,948.50
|
E
Engineer's Estimate
$7,328,606.88
1
Awarded
$5,866,106.92
Over/Under Est:
-19.96%
-$1,462,499.96
$6,760,548.37
Over/Under Est:
-7.75%
-$568,058.51
Amt Left:
15.25%
$894,441.45
$7,284,507.58
Over/Under Est:
-0.6%
-$44,099.30
Amt Left:
24.18%
$1,418,400.66
Delta:
-7.75%
-$523,959.21
$7,886,867.70
Over/Under Est:
7.62%
$558,260.82
Amt Left:
34.45%
$2,020,760.78
Delta:
-8.27%
-$602,360.12
$8,061,816.20
Over/Under Est:
10%
$733,209.32
Amt Left:
37.43%
$2,195,709.28
Delta:
-2.22%
-$174,948.50
| Subcontractor | Percentage | Amount |
|---|---|---|
| DIIBS SPECIALISTS, LLC | 30.31% | $1,778,017.01 |
| TRP CONSTRUCTION GROUP, LLC | 4.37% | $256,348.87 |
| Total: | 34.68% | $2,034,365.88 |
Bid Items & Bid Tabulations
44
Total
0 of 44
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| Total: | $2,000.00 |