KERR FM 1341 (1135-03-030)
Items: 49
County: KERR
Length: N/A
Highway: FM 1341
District: SAN ANTONIO
Control Number: 1135-03-030
DBE Goal: 400.0%
Project: BR 2024(939)
Guaranty: N/A
Time: 52 WORKING DAYS
Engineer's Estimate: $1,489,991.91
Date: 04/04/2024 (2 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
ANDRES GONZALEZ
ROBERTO MADRIGAL
Bidders (9)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,489,991.91 | |||
| $1,193,211.00 |
-19.92%
-$296,780.91
|
|||
| $1,415,239.26 |
-5.02%
-$74,752.65
|
18.61%
$222,028.26
|
||
| $1,429,578.42 |
-4.05%
-$60,413.49
|
19.81%
$236,367.42
|
-1.01%
-$14,339.16
|
|
| $1,512,306.00 |
1.5%
$22,314.09
|
26.74%
$319,095.00
|
-5.79%
-$82,727.58
|
|
| $1,681,744.70 |
12.87%
$191,752.79
|
40.94%
$488,533.70
|
-11.20%
-$169,438.70
|
|
| $1,943,819.50 |
30.46%
$453,827.59
|
62.91%
$750,608.50
|
-15.58%
-$262,074.80
|
|
| $1,997,331.20 |
34.05%
$507,339.29
|
67.39%
$804,120.20
|
-2.75%
-$53,511.70
|
|
| $2,108,860.50 |
41.54%
$618,868.59
|
76.74%
$915,649.50
|
-5.58%
-$111,529.30
|
|
| $2,145,998.88 |
44.03%
$656,006.97
|
79.85%
$952,787.88
|
-1.76%
-$37,138.38
|
E
Engineer's Estimate
$1,489,991.91
1
Awarded
$1,193,211.00
Over/Under Est:
-19.92%
-$296,780.91
$1,415,239.26
Over/Under Est:
-5.02%
-$74,752.65
Amt Left:
18.61%
$222,028.26
$1,429,578.42
Over/Under Est:
-4.05%
-$60,413.49
Amt Left:
19.81%
$236,367.42
Delta:
-1.01%
-$14,339.16
$1,512,306.00
Over/Under Est:
1.5%
$22,314.09
Amt Left:
26.74%
$319,095.00
Delta:
-5.79%
-$82,727.58
$1,681,744.70
Over/Under Est:
12.87%
$191,752.79
Amt Left:
40.94%
$488,533.70
Delta:
-11.20%
-$169,438.70
$1,943,819.50
Over/Under Est:
30.46%
$453,827.59
Amt Left:
62.91%
$750,608.50
Delta:
-15.58%
-$262,074.80
$1,997,331.20
Over/Under Est:
34.05%
$507,339.29
Amt Left:
67.39%
$804,120.20
Delta:
-2.75%
-$53,511.70
$2,108,860.50
Over/Under Est:
41.54%
$618,868.59
Amt Left:
76.74%
$915,649.50
Delta:
-5.58%
-$111,529.30
$2,145,998.88
Over/Under Est:
44.03%
$656,006.97
Amt Left:
79.85%
$952,787.88
Delta:
-1.76%
-$37,138.38
| Subcontractor | Percentage | Amount |
|---|---|---|
| LONE STAR PAVING COMPANY | 12.75% | $152,134.40 |
| LONE STAR EROSION CONTROL | 2.98% | $35,557.69 |
| A3 CONSTRUCTION INC. | 2.92% | $34,841.76 |
| FRANK JR REINFORCEMENT LLC | 2.12% | $25,296.07 |
| SOUTH TEXAS TRAFFIC ALLIANCE INC. | 1.43% | $17,062.92 |
| FLASHER EQUIPMENT COMPANY | 1.28% | $15,273.10 |
| 1 PRIORITY ENVIRONMENTAL SERVICES, LLC | 0.31% | $3,698.95 |
| Total: | 23.79% | $283,864.89 |
Bid Items & Bid Tabulations
49
Total
0 of 49