KERR FM 1341 (1135-03-030)

Items: 49

County: KERR
Length: N/A
Highway: FM 1341
District: SAN ANTONIO
Control Number: 1135-03-030
DBE Goal: 400.0%
Project: BR 2024(939)
Guaranty: N/A
Time: 52 WORKING DAYS
Engineer's Estimate: $1,489,991.91
Date: 04/04/2024 (2 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
ANDRES GONZALEZ
ROBERTO MADRIGAL
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (9)
E
Engineer's Estimate
$1,489,991.91
$1,193,211.00
Over/Under Est: -19.92% -$296,780.91
Over/Under Est: -5.02% -$74,752.65
Amt Left: 18.61% $222,028.26
$1,429,578.42
Over/Under Est: -4.05% -$60,413.49
Amt Left: 19.81% $236,367.42
Delta: -1.01% -$14,339.16
$1,512,306.00
Over/Under Est: 1.5% $22,314.09
Amt Left: 26.74% $319,095.00
Delta: -5.79% -$82,727.58
Over/Under Est: 12.87% $191,752.79
Amt Left: 40.94% $488,533.70
Delta: -11.20% -$169,438.70
Over/Under Est: 30.46% $453,827.59
Amt Left: 62.91% $750,608.50
Delta: -15.58% -$262,074.80
$1,997,331.20
Over/Under Est: 34.05% $507,339.29
Amt Left: 67.39% $804,120.20
Delta: -2.75% -$53,511.70
$2,108,860.50
Over/Under Est: 41.54% $618,868.59
Amt Left: 76.74% $915,649.50
Delta: -5.58% -$111,529.30
Over/Under Est: 44.03% $656,006.97
Amt Left: 79.85% $952,787.88
Delta: -1.76% -$37,138.38
Subcontractor Percentage Amount
LONE STAR PAVING COMPANY 12.75% $152,134.40
LONE STAR EROSION CONTROL 2.98% $35,557.69
A3 CONSTRUCTION INC. 2.92% $34,841.76
FRANK JR REINFORCEMENT LLC 2.12% $25,296.07
SOUTH TEXAS TRAFFIC ALLIANCE INC. 1.43% $17,062.92
FLASHER EQUIPMENT COMPANY 1.28% $15,273.10
1 PRIORITY ENVIRONMENTAL SERVICES, LLC 0.31% $3,698.95
Total: 23.79% $283,864.89

Bid Items & Bid Tabulations

49 Total 0 of 49
KERR  |  FM 1341  |  SAN ANTONIO  |  1135-03-030  |  04/04/2024  |  $1,489,991.91  |  BR 2024(939)  |  BRIDGE REPL  |  52 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
J3 COMPANY, LLC
DEAN WORD COMPANY, LTD.
C. E. BARKER, LTD.
STX CIVIL
R CONSTRUCTION CIVIL, LLC
LUCANIA CONTRACTORS LLC
ALLEN KELLER COMPANY
ICOS MANAGEMENT, LLC
ACME BRIDGE COMPANY, INC.
PREPARING ROW
STA 7.000 $2,000.000 $700.000 $9,250.000 $10,000.000 $4,682.000 $5,000.000 $1,500.000 $15,000.000 $4,400.000 $5,130.000
REMOVING CONC (RIPRAP)
SY 915.000 $40.000 $30.000 $11.920 $24.870 $19.000 $20.000 $35.000 $25.750 $165.000 $27.700
REMOV STAB BASE & ASPH PAV (8"-20")
SY 1,526.000 $15.000 $12.000 $10.600 $13.570 $25.000 $15.000 $40.000 $15.000 $176.000 $10.200
EXCAVATION (ROADWAY)
CY 352.000 $33.000 $20.000 $21.740 $39.430 $9.000 $22.000 $40.000 $26.800 $66.000 $41.900
EXCAVATION (CHANNEL)
CY 768.000 $25.000 $30.000 $8.740 $39.430 $15.000 $30.000 $50.000 $21.250 $66.000 $35.200
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 122.000 $40.000 $30.000 $70.350 $60.750 $21.000 $18.000 $120.000 $56.000 $110.000 $41.100
FURNISHING AND PLACING TOPSOIL (4")
SY 469.000 $5.750 $10.000 $4.240 $18.660 $2.000 $8.000 $10.000 $16.750 $11.000 $4.350
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 469.000 $1.500 $2.000 $1.130 $2.670 $0.500 $3.500 $1.250 $2.950 $1.000 $1.150
VEGETATIVE WATERING
MG 8.000 $87.000 $120.000 $55.070 $74.600 $15.000 $40.000 $100.000 $130.900 $1.000 $105.000
PROOF ROLLING
HR 61.000 $108.000 $80.000 $115.690 $101.660 $170.000 $80.000 $140.000 $205.150 $440.000 $127.000
CEM STABIL BKFL
CY 88.000 $221.000 $300.000 $186.310 $186.510 $225.000 $65.000 $240.000 $345.000 $440.000 $384.000
TRENCH EXCAVATION PROTECTION
LF 59.000 $105.000 $30.000 $13.590 $63.220 $8.000 $5.000 $15.000 $156.600 $165.000 $23.200
CL C CONC (RAC-R)
CY 23.000 $2,980.000 $1,750.000 $375.000 $2,068.620 $2,328.000 $2,500.000 $700.000 $3,000.000 $1,650.000 $1,440.000
RIPRAP (CONC)(5 IN)
CY 212.000 $421.000 $400.000 $467.890 $565.910 $558.000 $750.000 $480.000 $845.750 $660.000 $783.000
RIPRAP (MOW STRIP)(4 IN)
CY 24.000 $556.000 $720.000 $694.360 $746.030 $616.000 $800.000 $500.000 $1,080.650 $660.000 $1,460.000
RAIL (TY T223)
LF 375.000 $209.000 $150.000 $187.660 $281.260 $260.000 $175.000 $250.000 $454.750 $1,100.000 $150.000
CONC BOX CULV (12 FT X 6 FT)
LF 216.000 $2,200.000 $1,900.000 $2,022.500 $1,454.550 $2,204.000 $2,400.000 $3,500.000 $2,739.000 $1,050.000 $3,600.000
WINGWALL (PW - 1) (HW=8 FT)
EA 2.000 $50,000.000 $47,000.000 $77,061.050 $41,297.810 $77,098.000 $125,000.000 $50,000.000 $101,800.000 $33,000.000 $160,000.000
REMOV STR (PIPE)
LF 420.000 $55.000 $50.000 $26.230 $49.740 $21.000 $65.000 $170.000 $38.300 $55.000 $29.800
REMOV STR (SMALL FENCE)
LF 100.000 $7.750 $3.000 $12.570 $9.330 $5.000 $2.000 $6.000 $18.900 $11.000 $30.500
MOBILIZATION
LS 1.000 $131,813.360 $55,000.000 $142,500.000 $150,000.000 $120,000.000 $75,000.000 $185,000.000 $195,000.000 $60,000.000 $174,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $10,000.000 $5,000.000 $3,795.890 $6,216.880 $2,051.000 $9,400.000 $3,200.000 $5,141.000 $1.000 $4,340.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 50.000 $82.500 $90.000 $90.240 $93.260 $80.000 $97.000 $100.000 $121.000 $11.000 $91.500
ROCK FILTER DAMS (REMOVE)
LF 50.000 $15.500 $20.000 $16.250 $12.430 $15.000 $75.000 $18.000 $32.650 $11.000 $16.500
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 112.000 $31.000 $30.000 $27.600 $24.870 $40.000 $42.000 $30.000 $25.150 $1.000 $28.000
CONSTRUCTION EXITS (REMOVE)
SY 112.000 $16.250 $10.000 $8.720 $12.430 $15.000 $30.000 $9.500 $9.250 $1.000 $8.800
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,291.000 $9.250 $8.000 $7.520 $9.330 $8.000 $5.000 $8.250 $7.350 $11.000 $7.600
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,291.000 $1.750 $1.000 $0.970 $2.670 $1.500 $1.200 $1.000 $1.250 $1.000 $0.980
MTL W-BEAM GD FEN (TIM POST)
LF 112.500 $33.000 $30.000 $28.490 $31.820 $36.000 $28.000 $45.000 $29.100 $55.000 $29.300
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,975.000 $1,300.000 $1,337.740 $2,471.540 $2,819.000 $2,200.000 $3,000.000 $3,248.000 $6,600.000 $1,870.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,725.000 $1,200.000 $1,176.420 $1,514.480 $1,727.000 $1,650.000 $2,000.000 $1,385.000 $3,300.000 $1,210.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,060.000 $2,500.000 $2,565.340 $4,057.460 $4,628.000 $3,450.000 $3,000.000 $3,710.650 $7,100.000 $2,640.000
WIRE FENCE (TY B)
LF 100.000 $41.000 $48.000 $50.680 $37.300 $35.000 $45.000 $15.000 $44.850 $55.000 $30.000
RELOCATE EXISTING MAILBOX
EA 1.000 $405.000 $450.000 $495.690 $746.030 $334.000 $800.000 $350.000 $438.600 $1,100.000 $477.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $787.000 $950.000 $1,046.450 $373.010 $821.000 $1,300.000 $850.000 $925.950 $1,100.000 $1,010.000
IN SM RD SN SUP&AM TYFRP(1)UA(P)
EA 1.000 $1,000.000 $600.000 $660.920 $746.030 $152.000 $1,100.000 $150.000 $584.800 $1,100.000 $636.000
REMOVE SM RD SN SUP&AM
EA 1.000 $250.000 $150.000 $165.240 $124.340 $21.000 $400.000 $20.000 $146.200 $550.000 $159.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 15.000 $14.750 $45.000 $37.950 $20.870 $24.000 $25.000 $40.000 $19.100 $66.000 $47.700
REFL PAV MRK TY II (W) 6" (SLD)
LF 1,942.000 $0.200 $0.950 $1.050 $0.300 $2.000 $1.000 $1.250 $0.950 $6.000 $1.000
REFL PAV MRK TY II (Y) 6" (SLD)
LF 1,942.000 $0.200 $0.950 $1.050 $0.300 $2.000 $1.000 $1.250 $0.950 $6.000 $1.000
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
LF 1,942.000 $1.000 $2.050 $2.270 $0.930 $4.000 $2.000 $6.000 $2.000 $6.000 $2.150
REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL)
LF 1,942.000 $1.000 $2.050 $2.270 $0.930 $4.000 $2.000 $6.000 $2.000 $6.000 $2.150
REFL PAV MRKR TY II-A-A
EA 26.000 $5.000 $12.500 $13.750 $4.970 $8.000 $20.000 $12.000 $12.200 $6.000 $13.300
D-GR HMA TY-B PG64-22 (EXEMPT)
TON 1,062.000 $97.000 $120.000 $150.000 $129.490 $131.000 $100.000 $160.000 $101.350 $275.000 $115.000
TACK COAT
GAL 462.000 $5.000 $5.000 $4.500 $4.260 $5.000 $13.000 $6.000 $3.900 $11.000 $4.250
D-GR HMA TY-C SAC-B PG70-22 (EXEMPT)
TON 262.000 $210.000 $165.000 $165.000 $154.530 $164.000 $150.000 $225.000 $141.350 $275.000 $143.000
BONDING COURSE
GAL 457.000 $4.750 $5.000 $5.000 $4.260 $5.000 $10.000 $6.000 $3.900 $11.000 $4.250
INSTALL BRIDGE IDENTIFICATION NUMBERS
EA 2.000 $344.000 $250.000 $200.350 $466.270 $1,000.000 $650.000 $500.000 $325.000 $2,200.000 $679.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 8.000 $12,870.000 $4,500.000 $6,432.550 $12,433.750 $6,686.000 $15,000.000 $8,700.000 $7,475.000 $1.000 $19,700.000
Totals: $1,489,991.910 $1,193,211.000 $1,415,239.265 $1,429,578.420 $1,512,306.000 $1,681,744.700 $1,943,819.500 $1,997,331.200 $2,108,860.500 $2,145,998.880