KERR VARIOUS (0915-15-101)
Items: 35
County: KERR
Length: 0.0000 MILES
Highway: VARIOUS
District: SAN ANTONIO
Control Number: 0915-15-101
DBE Goal: 0.0%
Project: C 915-15-101
Guaranty: $22,000.00
Time: 62 WORKING DAYS
Engineer's Estimate: $1,115,562.83
Date: 02/07/2025 (1 year ago)
Contract Number: 2253229
Type: STATE PARK IMPROVEMENTS
Project ID: A00207189
Project Description: SEAL COAT ROADS, PARKING, AND PULLOUTS WITHIN THE WMA
Mail/Deliver Bids To: N/A
RICARDO GONZALEZ
ANDRES GONZALEZ
ROBERTO MADRIGAL
KERR VARIOUS (0915-15-101)
Project Name: N/A
Project: C 915-15-101
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: KERR WILDLIFE MANAGEMENT AREA
Limits To: .
Project Description: SEAL COAT ROADS, PARKING, AND PULLOUTS WITHIN THE WMA
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,115,562.83 | |||
| $908,186.10 |
-18.59%
-$207,376.73
|
|||
| $995,652.00 |
-10.75%
-$119,910.83
|
9.63%
$87,465.90
|
||
| $1,124,976.30 |
0.84%
$9,413.47
|
23.87%
$216,790.20
|
-12.99%
-$129,324.30
|
|
| $1,337,977.29 |
19.94%
$222,414.46
|
47.32%
$429,791.19
|
-18.93%
-$213,000.99
|
|
| $1,356,922.02 |
21.64%
$241,359.19
|
49.41%
$448,735.92
|
-1.42%
-$18,944.73
|
|
| $1,455,421.20 |
30.47%
$339,858.37
|
60.26%
$547,235.10
|
-7.26%
-$98,499.18
|
|
| $2,503,279.80 |
124.4%
$1,387,716.97
|
175.64%
$1,595,093.70
|
-72.00%
-$1,047,858.60
|
E
Engineer's Estimate
$1,115,562.83
1
Awarded
$908,186.10
Over/Under Est:
-18.59%
-$207,376.73
$995,652.00
Over/Under Est:
-10.75%
-$119,910.83
Amt Left:
9.63%
$87,465.90
$1,124,976.30
Over/Under Est:
0.84%
$9,413.47
Amt Left:
23.87%
$216,790.20
Delta:
-12.99%
-$129,324.30
$1,337,977.29
Over/Under Est:
19.94%
$222,414.46
Amt Left:
47.32%
$429,791.19
Delta:
-18.93%
-$213,000.99
$1,356,922.02
Over/Under Est:
21.64%
$241,359.19
Amt Left:
49.41%
$448,735.92
Delta:
-1.42%
-$18,944.73
$1,455,421.20
Over/Under Est:
30.47%
$339,858.37
Amt Left:
60.26%
$547,235.10
Delta:
-7.26%
-$98,499.18
$2,503,279.80
Over/Under Est:
124.4%
$1,387,716.97
Amt Left:
175.64%
$1,595,093.70
Delta:
-72.00%
-$1,047,858.60
| Subcontractor | Percentage | Amount |
|---|---|---|
| STRIPE IT UP, LLC | 7.69% | $69,839.51 |
| GREYCO CONSTRUCTION, LLC | 6.39% | $58,033.09 |
| Total: | 14.08% | $127,872.60 |
Bid Items & Bid Tabulations
35
Total
0 of 35