KERR SH 27 (0142-03-031)

Items: 86

County: KERR
Length: N/A
Highway: SH 27
District: SAN ANTONIO
Control Number: 0142-03-031
DBE Goal: N/A
Project: BR 2022(335)
Guaranty: N/A
Time: 218 WORKING DAYS
Engineer's Estimate: $1,477,040.15
Date: 02/04/2022 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (3)
E
Engineer's Estimate
$1,477,040.15
$1,836,910.46
Over/Under Est: 24.36% $359,870.31
Over/Under Est: 28.96% $427,679.55
Amt Left: 3.69% $67,809.24
$2,496,480.99
Over/Under Est: 69.02% $1,019,440.84
Amt Left: 35.91% $659,570.53
Delta: -31.07% -$591,761.29
Subcontractor Percentage Amount
TEXAS MATERIALS GROUP, INC. 6.44% $129,401.17
BEAIRD DRILLING 4.74% $95,242.48
FLASHER EQUIPMENT COMPANY 3.88% $77,962.20
A K FUQUAY CONSTRUCTION 2.25% $45,210.04
ROADWAY SPECIALTIES, INC. 1.73% $34,761.49
TRP CONSTRUCTION GROUP, LLC 1.42% $28,532.56
PRIMATE CONSTRUCTION, LP 0.62% $12,457.88
DEAN WORD COMPANY, LTD. 0.41% $8,238.27
Total: 21.49% $431,806.09

Bid Items & Bid Tabulations

86 Total 0 of 86
KERR  |  SH 27  |  SAN ANTONIO  |  0142-03-031  |  02/04/2022  |  $1,477,040.15  |  BR 2022(335)  |  BRIDGE REPL  |  218 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SB CONTRACTORS LLC
ACME BRIDGE COMPANY, INC.
J3 COMPANY, LLC
PREPARING ROW
STA 9.000 $3,000.000 $4,000.000 $4,410.000 $5,500.000
REMOVING CONC (RIPRAP)
SY 533.000 $9.000 $14.950 $10.000 $15.000
EXCAVATION (ROADWAY)
CY 2,172.000 $10.000 $14.530 $18.000 $25.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 590.000 $13.000 $11.950 $15.000 $20.000
COMPOST MANUF TOPSOIL (4")
SY 3,160.000 $1.300 $1.960 $3.200 $8.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 339.000 $0.230 $2.650 $2.100 $2.000
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 3,160.000 $0.160 $0.890 $0.400 $0.380
BROADCAST SEED (TEMP)(WARM OR COOL)
SY 3,160.000 $0.180 $0.410 $0.300 $0.280
VEGETATIVE WATERING
MG 27.000 $22.140 $40.850 $46.720 $30.000
SOIL RETENTION BLANKETS (CL 2) (TY F)
SY 3,499.000 $5.000 $3.310 $1.750 $1.650
PROOF ROLLING
HR 112.000 $100.000 $58.410 $32.000 $70.000
FL BS (CIP)(TY D GR 1-2, OR 5)FINAL POS
CY 505.000 $55.000 $79.100 $75.000 $90.000
PRIME COAT(MC-30 OR AE-P)
GAL 364.000 $4.000 $4.340 $4.500 $7.290
AGGR (TY-PB GR-4)
CY 15.000 $81.000 $510.600 $530.000 $513.140
ASPH (AC-15P OR CRS-2P)
GAL 764.000 $4.000 $6.630 $6.900 $8.100
PLANE ASPH CONC PAV (2")
SY 883.000 $2.800 $9.190 $9.500 $12.690
CEM STABIL BKFL
CY 238.000 $80.000 $127.110 $179.000 $175.000
TEMPORARY SPL SHORING
SF 141.000 $15.230 $103.850 $42.400 $65.000
DRILL SHAFT (18 IN)
LF 74.000 $105.000 $241.610 $183.000 $300.000
DRILL SHAFT (36 IN)
LF 296.000 $200.000 $471.790 $400.000 $500.000
CL C CONC (ABUT)
CY 64.800 $960.000 $825.930 $1,080.000 $1,500.000
CL C CONC (CAP)
CY 13.600 $1,150.000 $2,133.300 $1,800.000 $5,000.000
CL C CONC (COLUMN)
CY 28.400 $1,050.000 $1,092.300 $1,110.000 $1,500.000
REINF CONC SLAB
SF 9,430.000 $18.000 $19.480 $23.000 $32.000
APPROACH SLAB
CY 96.600 $560.000 $476.020 $688.000 $750.000
PRESTR CONC GIRDER (TX40)
LF 1,221.060 $145.000 $207.100 $233.500 $340.000
RIPRAP (CONC)(5 IN)
CY 11.000 $440.000 $462.230 $550.000 $550.000
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 236.000 $420.000 $277.460 $550.000 $550.000
RIPRAP (STONE COMMON)(DRY)(8 IN)
CY 30.000 $350.000 $229.260 $164.000 $200.000
RIPRAP (MOW STRIP)(4 IN)
CY 17.000 $418.000 $471.470 $700.000 $750.000
RAIL (TY T223)
LF 470.000 $120.000 $95.520 $82.800 $175.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 97.000 $120.000 $136.200 $150.000 $135.000
RC PIPE (CL III)(24 IN)
LF 44.000 $88.000 $80.860 $96.500 $150.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $2,000.000 $1,511.300 $2,000.000 $3,500.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $62,000.000 $59,528.900 $95,000.000 $125,000.000
MOBILIZATION
LS 1.000 $134,281.280 $183,000.000 $153,000.000 $130,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $8,000.000 $5,000.000 $1,940.000 $5,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 43.000 $24.000 $35.540 $29.700 $28.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 186.000 $29.070 $39.140 $33.900 $37.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 32.000 $60.000 $100.900 $74.200 $70.000
ROCK FILTER DAMS (REMOVE)
LF 261.000 $8.600 $10.510 $14.800 $14.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 156.000 $22.300 $20.220 $19.100 $18.000
CONSTRUCTION EXITS (REMOVE)
SY 156.000 $6.660 $8.070 $2.100 $2.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 80.000 $86.490 $56.170 $73.500 $82.060
TEMP SEDMT CONT FENCE (INSTALL)
LF 738.000 $2.440 $4.240 $3.700 $3.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 738.000 $0.620 $0.610 $1.600 $1.500
ONE-WAY TRAF CONT (PILOT CAR)
HR 80.000 $120.000 $204.240 $144.000 $125.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 9.000 $3,800.000 $2,757.280 $2,860.000 $5,500.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 1,050.000 $34.000 $65.000 $16.500 $50.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 960.000 $4.630 $4.020 $3.100 $25.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 1,050.000 $7.070 $11.600 $16.500 $25.000
DRIVEWAYS (ACP)(TYPE 1)
SY 218.000 $32.000 $80.050 $67.900 $90.000
MTL W-BEAM GD FEN (TIM POST)
LF 87.500 $25.000 $45.130 $46.900 $55.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,400.000 $2,088.220 $2,520.000 $2,200.000
REMOVE METAL BEAM GUARD FENCE
LF 500.000 $3.000 $2.510 $2.600 $4.000
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $195.000 $313.810 $326.000 $350.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,000.000 $3,635.070 $3,770.000 $4,000.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $1,500.000 $510.600 $1,060.000 $1,000.000
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $730.000 $510.610 $795.000 $750.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL2)
EA 4.000 $7,500.000 $8,000.000 $9,290.000 $10,000.000
MAILBOX INSTALL-S (TWG-POST) TY 1
EA 1.000 $250.000 $239.080 $286.000 $450.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
EA 1.000 $670.000 $887.650 $641.000 $900.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $860.000 $1,019.770 $769.000 $1,000.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $1,000.000 $1,489.430 $1,050.000 $1,500.000
REMOVE SM RD SN SUP&AM
EA 5.000 $90.000 $127.650 $101.000 $125.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 16.000 $18.800 $18.260 $31.800 $25.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 20.000 $21.000 $14.510 $10.600 $25.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 16.000 $26.310 $23.050 $31.800 $35.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 4,127.000 $0.270 $0.760 $0.800 $0.750
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 24.000 $6.000 $51.060 $53.000 $50.000
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 800.000 $0.280 $2.040 $2.100 $2.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 514.000 $0.620 $3.070 $3.200 $3.000
PAVEMENT SEALER 4"
LF 6,740.000 $0.130 $0.200 $0.210 $0.200
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 3,370.000 $0.590 $2.450 $2.550 $2.400
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 3,370.000 $0.590 $2.450 $2.550 $2.400
REFL PAV MRKR TY II-A-A
EA 68.000 $3.300 $20.430 $21.200 $20.000
ELIM EXT PAV MRK & MRKS (4")
LF 4,736.000 $0.350 $1.500 $1.550 $1.470
FULL - WIDTH MOWING
CYC 4.000 $2,500.000 $1,225.450 $1,120.000 $1,000.000
LITTER REMOVAL
CYC 10.000 $600.000 $714.850 $338.000 $1,000.000
TACK COAT
GAL 265.000 $3.000 $4.080 $4.250 $3.240
SP MIXES SP-C SAC-B PG70-22 (EXEMPT)
TON 508.000 $88.000 $194.030 $201.000 $198.780
INSTALL BRIDGE IDENTIFICATION NUMBERS
EA 2.000 $250.000 $459.540 $113.000 $250.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 18.000 $73.000 $153.180 $106.000 $150.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $9,000.000 $15,000.000 $12,100.000 $8,000.000
TMA (STATIONARY)
DAY 4.000 $180.000 $318.410 $194.000 $500.000
TMA (MOBILE OPERATION)
DAY 11.000 $220.000 $357.420 $194.000 $1,000.000
Totals: $1,477,040.150 $1,836,910.477 $1,904,719.700 $2,496,480.990