Items: 26

County: KERR
Length: 2.4610 MILES
Highway: US 87
District: SAN ANTONIO
Control Number: 0072-03-020
DBE Goal: 0.0%
Project: F 2026(376)
Guaranty: $33,000.00
Time: 48 WORKING DAYS
Engineer's Estimate: $1,671,570.50
Date: 02/05/2026 (4 months ago)
Contract Number: 2263221
Type: RESURFACE ROADWAY
Project ID: A00218310
Contract Type: Federal
Project Description: MICROSURFACE AND PAVEMENT MARKINGS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ANDRES GONZALEZ
ROBERTO MADRIGAL
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$1,671,570.50
$1,631,748.01
Over/Under Est: -2.38% -$39,822.49
Over/Under Est: -2.06% -$34,451.65
Amt Left: 0.33% $5,370.84
Over/Under Est: 14.87% $248,549.50
Amt Left: 17.67% $288,371.99
Delta: -17.29% -$283,001.15

Bid Items & Bid Tabulations

26 Total 0 of 26
KERR  |  US 87  |  SAN ANTONIO  |  0072-03-020  |  02/05/2026  |  $1,671,570.50  |  F 2026(376)  |  RESURF ROADWAY  |  48 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
INTERMOUNTAIN SLURRY SEAL, INC.
CACTUS TRANSPORT II, LLC
VSS INTERNATIONAL, INC.
MICROSURFACING
TON 3,936.000 $300.000 $307.000 $255.000 $300.000
MOBILIZATION
LS 1.000 $36,000.000 $20,000.000 $32,000.000 $97,645.870
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $12,000.000 $15,000.000 $4,500.000 $5,400.000
TMA (STATIONARY)
DAY 96.000 $180.000 $150.000 $1,150.000 $1,080.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,388.000 $0.630 $0.250 $0.550 $3.240
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 11,501.000 $0.350 $0.250 $0.550 $3.240
REFL PAV MRK TY I (W)8"(LNDP)(100MIL)
LF 63.000 $1.570 $1.200 $1.200 $1.300
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 5,185.000 $0.880 $0.900 $0.950 $0.970
REFL PAV MRK TY I (Y)8"(SLD)(060MIL)
LF 420.000 $0.720 $1.000 $0.950 $1.080
RE PROFILE PM TY I(W)6"(SLD)(100MIL)
LF 111,045.000 $0.670 $0.670 $0.750 $0.720
RE PROFILE PM TY I(Y)6"(SLD)(100MIL)
LF 107,075.000 $0.650 $0.670 $0.750 $0.720
RE PROFILE PM TY I(Y)6"(BRK)(100MIL)
LF 6,290.000 $0.640 $0.690 $0.600 $0.750
PAVEMENT SLER 6"
LF 231,000.000 $0.230 $0.250 $0.190 $0.270
PAVEMENT SLER 8"
LF 5,668.000 $0.380 $0.320 $0.350 $0.350
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 6,590.000 $0.490 $0.550 $0.600 $0.590
PREFAB PM TY C (W)(24")(SLD)
LF 510.000 $11.710 $12.000 $12.000 $12.960
PREFAB PM TY C (W)(ARROW)
EA 42.000 $208.650 $190.000 $230.000 $205.200
PREFAB PM TY C (W)(WORD)
EA 16.000 $234.470 $200.000 $275.000 $216.000
PREFAB PM TY C (W)(36")(YLD TRI)
EA 42.000 $28.560 $50.000 $60.000 $54.000
PREFAB PM TY C (Y)(24")(SLD)
LF 305.000 $11.830 $12.000 $12.000 $12.960
PREFAB PM TY C (Y)(MED NOSE)
EA 7.000 $250.000 $250.000 $400.000 $270.000
REFL PAV MRKR TY I-C
EA 437.000 $3.890 $4.500 $4.500 $4.860
REFL PAV MRKR TY II-A-A
EA 1,834.000 $3.650 $4.500 $4.500 $4.860
REFL PAV MRKR TY II-C-R
EA 81.000 $4.010 $4.500 $4.500 $4.860
ELIM EXT PM & MRKS (4")
LF 195,010.000 $0.180 $0.250 $0.300 $0.250
BONDING COURSE
GAL 31,497.000 $3.690 $1.200 $4.750 $5.000
Totals: $1,671,570.500 $1,631,748.010 $1,637,118.850 $1,920,120.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $50,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $2,000.00
Total: $53,000.00