KENDALL IH 10 (0072-05-096)
Items: 18
County: KENDALL
Length: N/A
Highway: IH 10
District: SAN ANTONIO
Control Number: 0072-05-096
DBE Goal: N/A
Project: STP 2023(673)HES
Guaranty: N/A
Time: 160 WORKING DAYS
Engineer's Estimate: $2,854,419.34
Date: 06/27/2023 (2 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
EDUARDO VILLALON
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,854,419.34 | |||
| $2,404,185.20 |
-15.77%
-$450,234.14
|
|||
| $2,455,973.16 |
-13.96%
-$398,446.18
|
2.15%
$51,787.96
|
||
| $2,533,205.83 |
-11.25%
-$321,213.51
|
5.37%
$129,020.63
|
-3.14%
-$77,232.67
|
|
| $2,698,552.40 |
-5.46%
-$155,866.94
|
12.24%
$294,367.20
|
-6.53%
-$165,346.57
|
|
| $2,954,420.53 |
3.5%
$100,001.19
|
22.89%
$550,235.33
|
-9.48%
-$255,868.13
|
|
| $2,970,845.35 |
4.08%
$116,426.01
|
23.57%
$566,660.15
|
-0.56%
-$16,424.82
|
|
| $3,499,674.50 |
22.61%
$645,255.16
|
45.57%
$1,095,489.30
|
-17.80%
-$528,829.15
|
E
Engineer's Estimate
$2,854,419.34
1
Awarded
$2,404,185.20
Over/Under Est:
-15.77%
-$450,234.14
$2,455,973.16
Over/Under Est:
-13.96%
-$398,446.18
Amt Left:
2.15%
$51,787.96
$2,533,205.83
Over/Under Est:
-11.25%
-$321,213.51
Amt Left:
5.37%
$129,020.63
Delta:
-3.14%
-$77,232.67
$2,698,552.40
Over/Under Est:
-5.46%
-$155,866.94
Amt Left:
12.24%
$294,367.20
Delta:
-6.53%
-$165,346.57
$2,954,420.53
Over/Under Est:
3.5%
$100,001.19
Amt Left:
22.89%
$550,235.33
Delta:
-9.48%
-$255,868.13
$2,970,845.35
Over/Under Est:
4.08%
$116,426.01
Amt Left:
23.57%
$566,660.15
Delta:
-0.56%
-$16,424.82
$3,499,674.50
Over/Under Est:
22.61%
$645,255.16
Amt Left:
45.57%
$1,095,489.30
Delta:
-17.80%
-$528,829.15
| Subcontractor | Percentage | Amount |
|---|---|---|
| ENVIRONMENTAL SAFETY SERVICES, INC. | 5.05% | $121,411.35 |
| Total: | 5.05% | $121,411.35 |
Bid Items & Bid Tabulations
18
Total
0 of 18