KAUFMAN US0080 (6461-60-001)

Items: 18

County: KAUFMAN
Length: N/A
Highway: US0080
District: DALLAS
Control Number: 6461-60-001
DBE Goal: 0.0%
Project: RMC - 646160001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $284,080.00
Date: 05/08/2024 (2 years ago)
Contract Number: N/A
Type: MISCELLANEOUS CONCRETE REPAIR
Mail/Deliver Bids To: N/A
LANE SELMAN
PHILLIP HANCOCK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$284,080.00
$237,950.00
Over/Under Est: -16.24% -$46,130.00
$271,735.00
Over/Under Est: -4.35% -$12,345.00
Amt Left: 14.2% $33,785.00
Over/Under Est: -0.32% -$902.00
Amt Left: 19.01% $45,228.00
Delta: -4.21% -$11,443.00
Over/Under Est: 7.66% $21,770.00
Amt Left: 28.54% $67,900.00
Delta: -8.01% -$22,672.00
Over/Under Est: 10.86% $30,847.50
Amt Left: 32.35% $76,977.50
Delta: -2.97% -$9,077.50
$322,950.00
Over/Under Est: 13.68% $38,870.00
Amt Left: 35.72% $85,000.00
Delta: -2.55% -$8,022.50

Bid Items & Bid Tabulations

18 Total 0 of 18
KAUFMAN  |  US0080  |  DALLAS  |  6461-60-001  |  05/08/2024  |  $284,080.00  |  RMC - 646160001  |  MISCELLANEOUS CONC REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GARRET SHIELDS INFRASTRUCTURE
RHINO EQUITY, LLC
RISE UP CONSTRUCTION LLC
SHALOM SERVICES CORPORATION
GIBSON & ASSOCIATES, INC.
IBCTX, LLC
REMOVING CONC (RIPRAP)
SY 40.000 $80.000 $50.000 $85.000 $45.000 $40.000 $180.000 $65.000
REMOVING CONC (CURB)
LF 25.000 $50.000 $50.000 $38.000 $45.000 $40.000 $74.000 $65.000
REMOVING CONC (CURB AND GUTTER)
LF 25.000 $60.000 $50.000 $38.000 $45.000 $80.000 $132.500 $75.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 10.000 $99.000 $100.000 $680.000 $5.000 $50.000 $550.000 $160.000
BACKFILL (TY A OR B)
CY 15.000 $200.000 $100.000 $254.000 $45.000 $50.000 $300.000 $160.000
FLOWABLE BACKFILL
CY 50.000 $500.000 $500.000 $680.000 $399.000 $600.000 $500.000 $300.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 500.000 $250.000 $200.000 $225.000 $200.000 $260.000 $210.000 $280.000
RIPRAP (CONC)(4 IN)
CY 75.000 $800.000 $500.000 $500.000 $789.000 $600.000 $1,200.000 $1,100.000
RIPRAP (STONE COMMON)(DRY)(18 IN)
CY 50.000 $300.000 $300.000 $255.000 $325.000 $280.000 $325.000 $375.000
MOBILIZATION (CALLOUT)
EA 8.000 $2,000.000 $1,000.000 $4,000.000 $1.000 $4,000.000 $1,850.000 $2,500.000
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 30.000 $120.000 $100.000 $25.000 $455.000 $300.000 $180.000 $200.000
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 30.000 $19.000 $40.000 $25.000 $25.000 $300.000 $53.000 $150.000
PORT CTB (ALIGNING)
LF 60.000 $20.000 $100.000 $25.000 $25.000 $80.000 $75.000 $110.000
CONC CURB (TY I)
LF 25.000 $26.000 $50.000 $125.000 $56.000 $240.000 $147.000 $140.000
CONC CURB & GUTTER (TY II)
LF 30.000 $84.000 $100.000 $125.000 $56.000 $260.000 $180.000 $150.000
CONCRETE RAIL REPAIR (MISC)
LF 10.000 $400.000 $500.000 $300.000 $400.000 $240.000 $655.000 $750.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 40.000 $115.000 $50.000 $255.000 $1.000 $240.000 $100.000 $50.000
TMA (STATIONARY)
DAY 40.000 $400.000 $600.000 $100.000 $1,500.000 $10.000 $260.000 $50.000
Totals: $284,080.000 $237,950.000 $271,735.000 $283,178.000 $305,850.000 $314,927.500 $322,950.000