KAUFMAN IH0020 (6354-27-001)

Items: 21

County: KAUFMAN
Length: N/A
Highway: IH0020
District: DALLAS
Control Number: 6354-27-001
DBE Goal: N/A
Project: RMC - 635427001
Guaranty: N/A
Time: 730 CALENDAR DAYS
Engineer's Estimate: $534,935.00
Date: 03/05/2020 (6 years ago)
Contract Number: N/A
Type: ON-CALL TRAFFIC CONTROL SERVICES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$534,935.00
$796,050.00
Over/Under Est: 48.81% $261,115.00
Over/Under Est: 69.07% $369,502.50
Amt Left: 13.62% $108,387.50
Over/Under Est: 96.73% $517,436.55
Amt Left: 32.2% $256,321.55
Delta: -16.36% -$147,934.05

Bid Items & Bid Tabulations

21 Total 0 of 21
KAUFMAN  |  IH0020  |  DALLAS  |  6354-27-001  |  03/05/2020  |  $534,935.00  |  RMC - 635427001  |  ON-CALL TRAF CONTROL SERVICES  |  730 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ALTUS TRAFFIC MANAGEMENT LLC
TOTAL HIGHWAY MAINTENANCE, LLC
AREA WIDE PROTECTIVE, INC.
MOBILIZATION (CALLOUT)
EA 150.000 $350.000 $300.000 $375.000 $184.000
MOBILIZATION (EMERGENCY)
EA 25.000 $700.000 $800.000 $1,500.000 $657.130
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 100.000 $140.000 $75.000 $75.000 $180.130
TMA (STATIONARY)
DAY 200.000 $360.000 $775.000 $725.000 $832.970
TMA (MOBILE OPERATION)
HR 2,000.000 $35.000 $89.000 $90.000 $141.070
TMA (MOBILE OPERATIONS) (SNOW & ICE)
HR 500.000 $65.000 $99.000 $90.000 $152.370
1 LN CLOSURE 2 LN RD NO SHOULDERS
HR 600.000 $112.000 $135.000 $135.000 $153.170
1 LN CLOSURE 2 LN RD PAVED SHOULDERS
HR 100.000 $95.000 $135.000 $135.000 $153.560
1 LN CLOSURE 4 LN RD
HR 50.000 $120.000 $135.000 $145.000 $156.070
2 LN CLOSURE 4 LN RD
HR 200.000 $135.000 $158.000 $200.000 $227.750
FREEWAY 1 LANE CLOSURE
HR 500.000 $135.000 $170.000 $250.000 $186.370
FREEWAY 2 LANE CLOSURE
HR 75.000 $125.000 $150.000 $275.000 $241.800
FREEWAY 3 LANE CLOSURE
HR 30.000 $145.000 $225.000 $275.000 $356.810
FREEWAY 4 LANE CLOSURE
HR 30.000 $242.000 $250.000 $275.000 $422.500
EXIT OR ENTRANCE RAMP CLOSURE
HR 200.000 $135.000 $155.000 $250.000 $228.000
COMPLETE FREEWAY CLOSURE
HR 100.000 $95.000 $275.000 $375.000 $546.670
ONE LANE FRONTAGE ROAD CLOSURE
HR 50.000 $130.000 $135.000 $145.000 $156.070
WORK AREA ON SHOULDER
HR 50.000 $120.000 $100.000 $120.000 $144.130
FURNISH ADDITIONAL FLAGGER
HR 250.000 $50.000 $40.000 $30.000 $74.560
PILOT VEHICLE AND OPERATOR
HR 300.000 $55.000 $58.000 $70.000 $115.700
FURNISH ADDITIONAL ARROW BOARD
HR 25.000 $10.000 $2.000 $2.500 $58.940
Totals: $534,935.000 $796,050.000 $904,437.500 $1,052,371.550