Items: 36

County: KAUFMAN
Length: 2.4890 MILES
Highway: FM 3486
District: DALLAS
Control Number: 1494-03-004
DBE Goal: 0.0%
Project: C 1494-3-4
Guaranty: $26,000.00
Time: 45 WORKING DAYS
Engineer's Estimate: $1,309,319.24
Date: 09/04/2025 (9 months ago)
Contract Number: 9253015
Type: REHABILITATE EXISTING ROADWAY
Project ID: A00189017
Project Description: OVERLAY, RUMBLE STRIP AND PAVEMENT MARKINGS.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
NICHOLAS WADLINGTON
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$1,309,319.24
$1,036,224.70
Over/Under Est: -20.86% -$273,094.54
Over/Under Est: -19.67% -$257,585.24
Amt Left: 1.5% $15,509.30
Over/Under Est: -18.26% -$239,117.17
Amt Left: 3.28% $33,977.37
Delta: -1.76% -$18,468.07
Over/Under Est: -15.54% -$203,426.58
Amt Left: 6.72% $69,667.96
Delta: -3.33% -$35,690.59
Over/Under Est: -9.89% -$129,529.66
Amt Left: 13.85% $143,564.88
Delta: -6.68% -$73,896.92
Over/Under Est: 7.19% $94,180.74
Amt Left: 35.44% $367,275.28
Delta: -18.96% -$223,710.40
Subcontractor Percentage Amount
LINEAR TRAFFIC MARKINGS LLC 3.69% $39,280.59
SOUTHERN CROSS CONTRACTORS, LLC 2.13% $22,674.16
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. 1.09% $11,603.21
WEST TEXAS RUMBLE STRIP LLC 0.81% $8,622.57
FLEX SUPPLY, LLC 0.47% $5,003.22
Total: 8.19% $87,183.75

Bid Items & Bid Tabulations

36 Total 0 of 36
KAUFMAN  |  FM 3486  |  DALLAS  |  1494-03-004  |  09/04/2025  |  $1,309,319.24  |  C 1494-3-4  |  REHAB EXIST ROADWAY  |  45 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FOUTSCO PAVING COMPANY, LLC
AUSTIN BRIDGE & ROAD SERVICES, LP
TEXAS MATERIALS GROUP, INC.
PEACHTREE CONSTRUCTION, LTD.
BAKER & COMPANY CONSTRUCTION, LLC
GREY SKY CONSTRUCTION LLC
PREPARING ROW
STA 131.410 $1,000.000 $1.000 $782.290 $130.000 $155.000 $235.000 $1,000.000
BACKFILL (TY A OR B)
STA 131.410 $500.000 $125.000 $135.750 $275.000 $390.000 $370.000 $350.000
COMPOST MANUF TOPSOIL (4")
SY 50.000 $5.000 $30.000 $25.000 $12.500 $28.000 $2.500 $10.000
BLOCK SODDING
SY 50.000 $8.000 $10.000 $15.000 $15.000 $17.000 $25.000 $10.000
DRILL SEED (TEMP_WARM_COOL)
SY 50.000 $0.250 $10.000 $10.000 $11.000 $12.000 $0.650 $10.000
VEGETATIVE WATERING
TGL 15.000 $8.000 $200.000 $1.000 $78.000 $265.000 $100.000 $50.000
SP MIXES SP-C SAC-B PG64-22
TON 5,090.000 $155.000 $150.000 $128.000 $141.000 $147.750 $138.000 $155.000
TACK COAT
GAL 3,183.000 $4.600 $10.000 $4.000 $4.500 $2.300 $7.150 $5.000
PLANE ASPH CONC PAV(0" TO 2")
SY 5,893.000 $4.500 $1.000 $4.780 $3.000 $3.200 $6.200 $6.000
MOBILIZATION
LS 1.000 $115,331.000 $100,000.000 $105,000.000 $104,314.000 $100,000.000 $110,000.000 $130,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $13,500.000 $10,000.000 $17,187.180 $17,000.000 $7,500.000 $21,150.000 $10,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 3.000 $5,000.000 $2,000.000 $2,000.000 $3,750.000 $4,500.000 $3,750.000 $20,000.000
TMA (STATIONARY)
DAY 45.000 $150.000 $1.000 $13.000 $1.000 $122.000 $363.000 $250.000
TMA (MOBILE OPERATION)
DAY 12.000 $250.000 $1.000 $1.000 $1.000 $350.000 $1,800.000 $550.000
ROCK FILTER DAMS (INSTALL) (TY 1)
CY 20.000 $65.000 $1.000 $45.000 $84.000 $47.000 $240.000 $30.000
ROCK FILTER DAMS (REMOVE)
LF 20.000 $8.000 $1.000 $20.000 $31.000 $22.000 $99.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 175.000 $2.500 $1.000 $4.500 $7.400 $5.000 $5.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 175.000 $0.700 $1.000 $1.250 $3.180 $1.300 $2.000 $2.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 966.000 $4.250 $1.000 $5.750 $7.350 $6.000 $5.000 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 966.000 $1.000 $1.000 $1.250 $3.160 $1.300 $1.000 $5.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 26,280.640 $0.150 $0.200 $0.090 $0.220 $0.200 $0.350 $0.500
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 13,140.320 $0.150 $0.400 $0.110 $0.220 $0.200 $0.350 $0.500
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 18.000 $650.000 $650.000 $640.000 $700.000 $650.000 $705.000 $1,150.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 3.000 $950.000 $990.000 $1,135.000 $1,150.000 $990.000 $1,250.000 $1,150.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $1,000.000 $990.000 $1,169.000 $1,150.000 $990.000 $1,285.000 $1,150.000
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
EA 1.000 $1,150.000 $990.000 $1,370.000 $1,150.000 $990.000 $1,510.000 $1,150.000
INSTL OM ASSM (OM-2Z)(WFLX)SRFHH(BI)
EA 29.000 $200.000 $400.000 $179.000 $475.000 $400.000 $197.000 $100.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 661.000 $5.000 $0.100 $0.650 $1.150 $3.500 $3.300 $6.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 63.000 $7.000 $20.000 $20.000 $21.000 $6.800 $8.250 $20.000
RE PM TY II (W) 6" (SLD)
LF 26,469.000 $0.500 $0.210 $0.210 $0.230 $0.240 $0.300 $0.750
RE PM TY II (Y) 6" (SLD)
LF 26,469.000 $0.500 $0.210 $0.210 $0.230 $0.240 $0.300 $0.750
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 26,728.000 $0.700 $0.500 $0.500 $0.550 $0.650 $0.800 $0.750
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 2,124.000 $0.700 $0.550 $0.550 $0.550 $0.650 $1.100 $0.750
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 14,142.000 $0.700 $0.500 $0.500 $0.530 $0.650 $0.800 $0.750
REFL PAV MRKR TY II-A-A
EA 283.000 $5.000 $5.500 $5.500 $6.000 $5.200 $6.600 $6.000
FULL - WIDTH MOWING
CYC 1.000 $3,500.000 $200.000 $1,500.000 $3,150.000 $13,000.000 $5,000.000 $1,500.000
Totals: $1,309,319.244 $1,036,224.696 $1,051,733.989 $1,070,202.071 $1,105,892.662 $1,179,789.586 $1,403,499.980
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $15,000.00
Total: $35,000.00