KAUFMAN SH 274 (0561-01-024)
Items: 49
County: KAUFMAN
Length: N/A
Highway: SH 274
District: DALLAS
Control Number: 0561-01-024
DBE Goal: N/A
Project: STP 2019(719)
Guaranty: N/A
Time: 96 WORKING DAYS
Engineer's Estimate: $3,733,824.66
Date: 04/03/2019 (7 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING PAVMENT AND SLOPE FAIL RPR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,733,824.66 | |||
| $3,753,154.82 |
0.52%
$19,330.16
|
|||
| $3,869,773.09 |
3.64%
$135,948.43
|
3.11%
$116,618.27
|
||
| $4,103,770.70 |
9.91%
$369,946.04
|
9.34%
$350,615.88
|
-6.05%
-$233,997.61
|
|
| $4,182,119.69 |
12.01%
$448,295.03
|
11.43%
$428,964.87
|
-1.91%
-$78,348.99
|
|
| $4,667,115.02 |
25%
$933,290.36
|
24.35%
$913,960.20
|
-11.60%
-$484,995.33
|
|
| $5,080,832.55 |
36.08%
$1,347,007.89
|
35.37%
$1,327,677.73
|
-8.86%
-$413,717.53
|
E
Engineer's Estimate
$3,733,824.66
1
Awarded
$3,753,154.82
Over/Under Est:
0.52%
$19,330.16
$3,869,773.09
Over/Under Est:
3.64%
$135,948.43
Amt Left:
3.11%
$116,618.27
$4,103,770.70
Over/Under Est:
9.91%
$369,946.04
Amt Left:
9.34%
$350,615.88
Delta:
-6.05%
-$233,997.61
$4,182,119.69
Over/Under Est:
12.01%
$448,295.03
Amt Left:
11.43%
$428,964.87
Delta:
-1.91%
-$78,348.99
$4,667,115.02
Over/Under Est:
25%
$933,290.36
Amt Left:
24.35%
$913,960.20
Delta:
-11.60%
-$484,995.33
$5,080,832.55
Over/Under Est:
36.08%
$1,347,007.89
Amt Left:
35.37%
$1,327,677.73
Delta:
-8.86%
-$413,717.53
Bid Items & Bid Tabulations
49
Total
0 of 49