KARNES US 181 (0100-05-001)

Items: 20

County: KARNES
Length: N/A
Highway: US 181
District: CORPUS CHRISTI
Control Number: 0100-05-001
DBE Goal: N/A
Project: BR 2019(669)
Guaranty: N/A
Time: 33 WORKING DAYS
Engineer's Estimate: $923,889.00
Date: 06/01/2022 (4 years ago)
Contract Number: N/A
Type: BRIDGE MAINTENANCE
Mail/Deliver Bids To: N/A
NICK NOVOSAD
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$923,889.00
1
$786,452.20
Over/Under Est: -14.88% -$137,436.80
Over/Under Est: -12.18% -$112,509.00
Amt Left: 3.17% $24,927.80
Over/Under Est: 10.89% $100,574.80
Amt Left: 30.26% $238,011.60
Delta: -26.26% -$213,083.80
Subcontractor Percentage Amount
LONE STAR PAVING COMPANY 8.69% $89,004.63
S&S BRIDGE PAINTING 6.83% $69,954.16
HIGHWAY BARRICADES AND SERVICES, LLC 0.89% $9,115.55
Total: 16.41% $168,074.34

Bid Items & Bid Tabulations

20 Total 0 of 20
KARNES  |  US 181  |  CORPUS CHRISTI  |  0100-05-001  |  06/01/2022  |  $923,889.00  |  BR 2019(669)  |  BRIDGE MAINT  |  33 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RELMCO, INC.
STRUCTURAL INTEGRITY GROUP LLC
GIBSON & ASSOCIATES, INC.
PLANE ASPH CONC PAV(0" TO 1")
SY 2,607.000 $7.780 $8.000 $12.000 $5.500
ROCK BACKFILL
CY 5.000 $75.000 $300.000 $600.000 $750.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 100.000 $187.660 $225.000 $255.000 $350.000
CLEANING AND SEALING EXIST JOINTS(CL7)
LF 528.000 $32.970 $40.000 $41.000 $74.000
CLEAN & PAINT EXIST STR (SPL PROT SYS)
LS 1.000 $200,000.000 $77,000.000 $93,000.000 $85,000.000
MILLING CONCRETE SLAB (1/4IN)
SY 2,607.000 $13.200 $8.000 $15.000 $5.500
MOBILIZATION
LS 1.000 $82,659.360 $60,000.000 $63,000.000 $112,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $7,318.000 $25,000.000 $17,250.000 $29,900.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 80.000 $4.050 $10.000 $3.000 $15.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 80.000 $1.290 $5.000 $2.000 $5.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 54.000 $0.570 $10.000 $2.500 $20.000
REFL PAV MRKR TY II-A-A
EA 14.000 $3.690 $50.000 $13.250 $22.000
PAV SURF PREP FOR MRK (4")
LF 2,134.000 $0.010 $2.000 $0.500 $1.100
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 250.000 $68.960 $85.000 $90.000 $106.000
CARBON FIBER REINF POLYMER PROTECTION
SF 100.000 $40.970 $200.000 $275.000 $325.000
POLYESTER POLYMER CONC OVERLAY (1-1/2")
SY 2,607.000 $192.000 $160.000 $167.500 $215.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 80.000 $43.630 $300.000 $1.000 $80.000
MULTIPOLYMER PAV MRK (W)(4")(SLD)
LF 1,067.000 $1.380 $3.300 $5.500 $6.600
MULTIPOLYMER PAV MRK (Y)(4")(SLD)
LF 1,067.000 $1.380 $3.300 $5.500 $6.600
TMA (STATIONARY)
DAY 66.000 $98.520 $250.000 $1.000 $240.000
Totals: $923,889.000 $786,452.200 $811,380.000 $1,024,463.800