JONES US 83 (0033-05-096)

Items: 31

County: JONES
Length: N/A
Highway: US 83
District: ABILENE
Control Number: 0033-05-096
DBE Goal: N/A
Project: STP 2023(911)HES
Guaranty: N/A
Time: 250 WORKING DAYS
Engineer's Estimate: $12,314,945.91
Date: 06/02/2023 (3 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
BRYCE TURENTINE
CHAD W CARTER
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$12,314,945.91
$10,217,861.88
Over/Under Est: -17.03% -$2,097,084.03
$10,455,477.50
Over/Under Est: -15.1% -$1,859,468.41
Amt Left: 2.33% $237,615.62
$10,811,876.64
Over/Under Est: -12.21% -$1,503,069.27
Amt Left: 5.81% $594,014.76
Delta: -3.41% -$356,399.14
Over/Under Est: -11.5% -$1,416,709.20
Amt Left: 6.66% $680,374.83
Delta: -0.80% -$86,360.07
Over/Under Est: -3.56% -$438,987.96
Amt Left: 16.23% $1,658,096.07
Delta: -8.97% -$977,721.24
$12,800,173.83
Over/Under Est: 3.94% $485,227.92
Amt Left: 25.27% $2,582,311.95
Delta: -7.78% -$924,215.88

Bid Items & Bid Tabulations

31 Total 0 of 31
JONES  |  US 83  |  ABILENE  |  0033-05-096  |  06/02/2023  |  $12,314,945.91  |  STP 2023(911)HES  |  HAZARD ELIM & SAFETY  |  250 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ROADWAY SPECIALTIES, INC.
WEBBER, LLC
HJC FARMS, INC.
MASSANA CONSTRUCTION INC.
SCR CIVIL CONSTRUCTION, LLC
A. L. HELMCAMP, INC.
REMOVING CONCRETE(MOW STRIP)
LF 3,384.000 $5.250 $6.400 $8.000 $12.000 $12.000 $45.000 $16.500
EXCAVATION (ROADWAY)
CY 5,353.000 $9.640 $4.190 $10.500 $15.000 $20.000 $19.000 $34.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 12,925.000 $30.000 $39.210 $13.000 $25.000 $60.000 $32.000 $29.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 320,114.000 $0.750 $0.330 $0.150 $0.260 $0.110 $0.350 $0.120
RIPRAP (CONC)(6 IN)
CY 9.750 $661.560 $1,823.240 $1,500.000 $750.000 $450.000 $4,700.000 $1,200.000
RIPRAP (MOW STRIP)(4 IN)
CY 5,353.000 $550.000 $370.000 $411.000 $480.000 $350.000 $510.000 $498.000
MOBILIZATION
LS 1.000 $1,314,388.920 $1,096,299.760 $1,001,000.000 $500,000.000 $865,039.300 $503,000.000 $1,150,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $12,000.000 $1,109.770 $19,250.000 $5,350.000 $27,500.000 $9,000.000 $22,000.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 666.000 $25.970 $35.490 $26.000 $63.660 $26.000 $30.000 $15.000
CONSTRUCTION EXITS (REMOVE)
SY 666.000 $5.420 $13.650 $10.000 $15.960 $10.000 $12.000 $4.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 2,605.000 $5.180 $4.100 $4.000 $9.790 $3.600 $10.000 $4.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,575.000 $1.090 $0.610 $2.000 $2.060 $1.000 $3.000 $1.200
PERM CTB (SGL SLOPE) (TY 1) (54 )
LF 31,234.000 $103.910 $108.930 $94.100 $135.000 $113.000 $152.000 $155.000
PERM CTB (SGL SLOPE)(TY 1)(TRANSITION)
LF 750.000 $803.550 $405.220 $286.130 $250.000 $460.000 $335.000 $270.000
REMOVE METAL BEAM GUARD FENCE
LF 2,675.000 $1.490 $1.010 $4.000 $2.000 $4.000 $10.000 $7.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 8.000 $227.310 $101.540 $450.000 $200.000 $450.000 $1,000.000 $750.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 13.000 $253.000 $202.970 $400.000 $200.000 $400.000 $1,000.000 $470.000
CABLE BARRIER SYSTEM (TL-4)
LF 144,605.000 $15.000 $12.580 $16.500 $11.500 $12.000 $11.600 $13.000
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 138.000 $5,000.000 $2,409.500 $3,500.000 $3,520.000 $5,500.000 $2,150.000 $3,900.000
GUARDRAIL END TREATMENT (REMOVE)
EA 11.000 $317.330 $304.370 $400.000 $200.000 $400.000 $1,000.000 $850.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 7.000 $27,595.200 $34,473.890 $40,000.000 $35,000.000 $35,500.000 $38,000.000 $33,000.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 132.000 $39.000 $38.430 $55.000 $60.500 $42.000 $70.000 $62.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 44,898.000 $0.580 $1.340 $1.000 $0.830 $0.750 $0.900 $0.850
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 11,227.000 $0.640 $1.160 $1.000 $0.890 $0.810 $0.950 $0.750
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 44,898.000 $0.550 $1.090 $1.000 $0.890 $0.810 $0.950 $0.750
REFL PAV MRKR TY II-C-R
EA 562.000 $3.760 $6.960 $5.000 $4.570 $4.150 $5.000 $11.000
ELIM EXT PAV MRK & MRKS (4")
LF 44,898.000 $0.790 $0.750 $1.000 $0.650 $0.590 $0.700 $0.700
PAV SURF PREP FOR MRK (6")
LF 56,125.000 $0.050 $0.140 $0.500 $0.240 $0.220 $0.300 $0.060
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $14,652.440 $8,872.500 $15,000.000 $12,500.000 $2,500.000 $16,500.000 $20,000.000
TMA (STATIONARY)
DAY 250.000 $307.760 $341.250 $275.000 $200.000 $100.000 $430.000 $250.000
TMA (MOBILE OPERATION)
DAY 15.000 $501.780 $341.250 $750.000 $300.000 $100.000 $900.000 $300.000
Totals: $12,314,945.910 $10,217,861.880 $10,455,477.500 $10,811,876.640 $10,898,236.710 $11,875,957.950 $12,800,173.830