JOHNSON FM0731 (6376-33-001)

Items: 10

County: JOHNSON
Length: N/A
Highway: FM0731
District: FORT WORTH
Control Number: 6376-33-001
DBE Goal: N/A
Project: RMC - 637633001
Guaranty: N/A
Time: 40 W
Engineer's Estimate: $513,779.30
Date: 03/05/2021 (5 years ago)
Contract Number: N/A
Type: REFLECTORIZED PAVEMENT MARKINGS & MARKERS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (5)
E
Engineer's Estimate
$513,779.30
$309,754.33
Over/Under Est: -39.71% -$204,024.97
Over/Under Est: -24.28% -$124,749.12
Amt Left: 25.59% $79,275.85
Over/Under Est: -22.62% -$116,199.97
Amt Left: 28.35% $87,825.00
Delta: -2.20% -$8,549.15
$459,297.79
Over/Under Est: -10.6% -$54,481.51
Amt Left: 48.28% $149,543.46
Delta: -15.52% -$61,718.46
Over/Under Est: -7.74% -$39,769.62
Amt Left: 53.03% $164,255.35
Delta: -3.20% -$14,711.89

Bid Items & Bid Tabulations

10 Total 0 of 10
JOHNSON  |  FM0731  |  FORT WORTH  |  6376-33-001  |  03/05/2021  |  $513,779.30  |  RMC - 637633001  |  REFLECTORIZED PAVMT MRK & MARKERS  |  40 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
STRIPE-A-ZONE, INC.
STRIPING TECHNOLOGY, L.P.
TRP CONSTRUCTION GROUP, LLC
BATTERSON, LLP
PMI PAVEMENT MARKING, LLC
MOBILIZATION (CALLOUT)
EA 1.000 $2,500.000 $1.000 $500.000 $2,500.000 $15,000.000 $7,500.000
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 262,463.000 $0.230 $0.130 $0.155 $0.180 $0.220 $0.210
REFL PAV MRK TY I (W)8"(SLD)(060MIL)
LF 10,989.000 $0.490 $0.420 $0.660 $0.450 $0.370 $0.450
RE PM W/RET REQ TY I (Y)4"(BRK)(060MIL)
LF 35,030.000 $0.170 $0.160 $0.280 $0.210 $0.190 $0.230
RE PM W/RET REQ TY I (Y)4"(SLD)(060MIL)
LF 354,920.000 $0.190 $0.160 $0.230 $0.190 $0.190 $0.230
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 353,338.000 $0.550 $0.420 $0.485 $0.480 $0.470 $0.550
REFL PAV MRKR TY II-A-A
EA 7,270.000 $3.360 $3.400 $2.850 $3.000 $3.000 $2.950
ELIM EXT PAV MRK & MRKS (4")
LF 353,338.000 $0.400 $0.100 $0.125 $0.200 $0.280 $0.250
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 86.000 $90.000 $1.000 $100.000 $45.000 $250.000 $125.000
TMA (MOBILE OPERATION)
DAY 86.000 $50.000 $1.000 $50.000 $25.000 $1.000 $22.000
Totals: $513,779.300 $309,754.330 $389,030.185 $397,579.330 $459,297.790 $474,009.680