JOHNSON US0067 (6330-32-001)
Items: 22
County: JOHNSON
Length: N/A
Highway: US0067
District: FORT WORTH
Control Number: 6330-32-001
DBE Goal: N/A
Project: RMC - 633032001
Guaranty: N/A
Time: 67 W
Engineer's Estimate: $788,248.90
Date: 09/06/2018 (7 years ago)
Contract Number: N/A
Type: SLOPE REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$788,248.90 | |||
| $756,360.61 |
-4.05%
-$31,888.29
|
|||
| $1,028,815.05 |
30.52%
$240,566.15
|
36.02%
$272,454.44
|
||
| $1,323,104.50 |
67.85%
$534,855.60
|
74.93%
$566,743.89
|
-28.60%
-$294,289.45
|
|
| $1,331,605.00 |
68.93%
$543,356.10
|
76.05%
$575,244.39
|
-0.64%
-$8,500.50
|
|
| $1,449,659.50 |
83.91%
$661,410.60
|
91.66%
$693,298.89
|
-8.87%
-$118,054.50
|
|
| $1,676,772.08 |
112.72%
$888,523.18
|
121.69%
$920,411.47
|
-15.67%
-$227,112.58
|
|
| $1,968,317.00 |
149.71%
$1,180,068.10
|
160.24%
$1,211,956.39
|
-17.39%
-$291,544.92
|
|
| $2,064,592.00 |
161.92%
$1,276,343.10
|
172.96%
$1,308,231.39
|
-4.89%
-$96,275.00
|
E
Engineer's Estimate
$788,248.90
1
Awarded
$756,360.61
Over/Under Est:
-4.05%
-$31,888.29
$1,028,815.05
Over/Under Est:
30.52%
$240,566.15
Amt Left:
36.02%
$272,454.44
$1,323,104.50
Over/Under Est:
67.85%
$534,855.60
Amt Left:
74.93%
$566,743.89
Delta:
-28.60%
-$294,289.45
$1,331,605.00
Over/Under Est:
68.93%
$543,356.10
Amt Left:
76.05%
$575,244.39
Delta:
-0.64%
-$8,500.50
$1,449,659.50
Over/Under Est:
83.91%
$661,410.60
Amt Left:
91.66%
$693,298.89
Delta:
-8.87%
-$118,054.50
$1,676,772.08
Over/Under Est:
112.72%
$888,523.18
Amt Left:
121.69%
$920,411.47
Delta:
-15.67%
-$227,112.58
$1,968,317.00
Over/Under Est:
149.71%
$1,180,068.10
Amt Left:
160.24%
$1,211,956.39
Delta:
-17.39%
-$291,544.92
$2,064,592.00
Over/Under Est:
161.92%
$1,276,343.10
Amt Left:
172.96%
$1,308,231.39
Delta:
-4.89%
-$96,275.00
Bid Items & Bid Tabulations
22
Total
0 of 22