Show Job Controls
Bid Cobra

JOHNSON FM 2331 (2417-02-016)

Items: 27

County: JOHNSON
Length: N/A
Highway: FM 2331
District: FORT WORTH
Control Number: 2417-02-016
DBE Goal: N/A
Project: STP 1802(382)
Guaranty: N/A
Time: 64 WORKING DAYS
Engineer's Estimate: $1,640,814.92
Date: 07/10/2018 (7 years ago)
Contract Number: N/A
Type: BS REPR, MILL, OV, PAV MK, MBGF
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$1,640,814.92
$1,839,667.79
Over/Under Est: 12.12% $198,852.87
Over/Under Est: 18.06% $296,375.19
Amt Left: 5.3% $97,522.32
Over/Under Est: 26.4% $433,208.36
Amt Left: 12.74% $234,355.49
Delta: -7.06% -$136,833.17
Over/Under Est: 72.67% $1,192,445.38
Amt Left: 54.01% $993,592.51
Delta: -36.61% -$759,237.02

Bid Items & Bid Tabulations

27 Total 0 of 27
JOHNSON  |  FM 2331  |  FORT WORTH  |  2417-02-016  |  07/10/2018  |  $1,640,814.92  |  STP 1802(382)  |  BS REPR, MILL, OV, PAV MK, MBGF  |  64 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
PEACHTREE CONSTRUCTION, LTD.
OLDCASTLE MATERIALS TEXAS, INC.
BICK'S CONSTRUCTION, INC.
NORTHEASTERN PAVERS, INC.
BACKFILL (TY A)
STA 20.000 $200.000 $380.000 $530.000 $200.000 $350.000
SALV, HAUL & STKPL RCL APH PV (0 TO 2")
SY 110.000 $5.000 $40.000 $41.000 $7.250 $60.000
D-GR HMA (SQ) TY-D PG64_22(LEVEL-UP)
TON 2,050.000 $100.000 $94.000 $96.000 $111.000 $160.000
TOM (ASPHALT) PG 76-22
TON 420.000 $200.000 $135.000 $135.000 $143.370 $185.000
TOM-C (AGGREGATE) SAC-A
TON 6,150.000 $100.000 $135.000 $135.000 $143.370 $185.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(12")
SY 7,200.000 $55.000 $67.000 $70.000 $86.400 $100.000
MOBILIZATION
LS 1.000 $105,380.420 $100,000.000 $132,800.000 $131,925.000 $300,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $10,000.000 $5,000.000 $23,000.000 $615.000 $2,500.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 500.000 $6.750 $10.000 $5.000 $5.000 $0.010
BIODEG EROSN CONT LOGS (REMOVE)
LF 500.000 $1.000 $5.000 $1.000 $5.000 $0.010
MTL W-BEAM GD FEN (TIM POST)
LF 600.000 $20.000 $21.000 $26.550 $22.750 $35.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 7.000 $1,450.000 $1,600.000 $1,785.000 $1,886.000 $3,000.000
SHORT RADIUS
LF 50.000 $110.000 $40.000 $47.250 $40.500 $62.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 1.000 $750.000 $1,000.000 $1,035.000 $942.000 $1,450.000
REMOVE METAL BEAM GUARD FENCE
LF 600.000 $8.000 $4.400 $5.750 $3.000 $5.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 7.000 $200.000 $380.000 $253.000 $200.000 $310.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $2,250.000 $2,800.000 $2,805.000 $2,750.000 $4,200.000
GUARDRAIL END TREATMENT (REMOVE)
EA 9.000 $250.000 $380.000 $253.000 $200.000 $300.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 8,706.000 $1.000 $1.500 $1.060 $1.500 $1.000
REFL PAV MRK TY I (W)12"(SLD)(090MIL)
LF 140.000 $2.500 $3.100 $2.800 $2.780 $8.000
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 85,223.000 $0.500 $0.320 $0.300 $0.290 $0.350
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 7,440.000 $0.500 $0.390 $0.360 $0.350 $0.590
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 41,169.000 $0.500 $0.320 $0.300 $0.290 $0.350
PREFAB PAV MRK TY B (W)(RR XING)
EA 2.000 $950.000 $1,050.000 $955.000 $950.000 $675.000
REFL PAV MRKR TY II-A-A
EA 965.000 $2.500 $3.350 $3.050 $3.000 $3.500
TMA (STATIONARY)
DAY 100.000 $600.000 $225.000 $112.000 $238.150 $750.000
TMA (MOBILE OPERATION)
HR 15.000 $125.000 $35.000 $100.000 $50.000 $1,500.000
Totals: $1,640,814.920 $1,839,667.790 $1,937,190.110 $2,074,023.280 $2,833,260.300