JOHNSON FM 917 (1181-04-049)

Items: 67

County: JOHNSON
Length: 7.5000 MILES
Highway: FM 917
District: FORT WORTH
Control Number: 1181-04-049
DBE Goal: 0.0%
Project: C 1181-4-49
Guaranty: $100,000.00
Time: 299 WORKING DAYS
Engineer's Estimate: $5,966,546.15
Date: 10/08/2025 (8 months ago)
Contract Number: 10253014
Type: RESURFACE ROADWAY
Project ID: A00129683
Project Description: TOM, FULL DEPTH REPAIR, MBGF, PAVEMENT MARKINGS CLEANING AND SEALING JOINTS.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ALFREDO LUERA
SUCHITA POTTA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (8)
E
Engineer's Estimate
$5,966,546.15
$4,574,922.62
Over/Under Est: -23.32% -$1,391,623.53
Over/Under Est: -23.22% -$1,385,402.84
Amt Left: 0.14% $6,220.69
Over/Under Est: -22.36% -$1,334,033.56
Amt Left: 1.26% $57,589.97
Delta: -1.12% -$51,369.28
Over/Under Est: -15.79% -$942,253.37
Amt Left: 9.82% $449,370.16
Delta: -8.46% -$391,780.19
$5,773,264.89
Over/Under Est: -3.24% -$193,281.26
Amt Left: 26.19% $1,198,342.27
Delta: -14.91% -$748,972.11
Over/Under Est: -0.81% -$48,118.20
Amt Left: 29.37% $1,343,505.33
Delta: -2.51% -$145,163.06
Over/Under Est: 0.13% $7,956.01
Amt Left: 30.59% $1,399,579.54
Delta: -0.95% -$56,074.21
Over/Under Est: 15.1% $901,183.74
Amt Left: 50.12% $2,292,807.27
Delta: -14.95% -$893,227.73
Subcontractor Percentage Amount
JR WEST TEXAS CONCRETE LLC 7.21% $329,848.68
FORTSON CONTRACTING, INC. 4.95% $226,456.44
IBCTX, LLC 1.77% $80,975.33
SITE BARRICADES 1.46% $66,793.21
G J SEEDING, LLC 0.83% $37,971.48
SURFACE PREPARATION TECHNOLOGIES, LLC 0.43% $19,671.97
STEEL EFFECTS 0.35% $16,012.07
STRIPE-A-ZONE, LLC 0.00% $0.00
Total: 17.00% $777,729.18

Bid Items & Bid Tabulations

67 Total 0 of 67
JOHNSON  |  FM 917  |  FORT WORTH  |  1181-04-049  |  10/08/2025  |  $5,966,546.15  |  C 1181-4-49  |  RESURF ROADWAY  |  299 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
NORTHEASTERN PAVERS, LLC
AUSTIN BRIDGE & ROAD SERVICES, LP
FOUTSCO PAVING COMPANY, LLC
PEACHTREE CONSTRUCTION, LTD.
OVERLAND CORPORATION
GREY SKY CONSTRUCTION LLC
KNIFE RIVER CORPORATION - SOUTH
TEXAS MATERIALS GROUP, INC.
EMBANK (FNL)(OC)(TY B)
CY 238.000 $47.500 $75.000 $59.670 $50.000 $70.500 $500.000 $50.000 $69.500 $77.000
BACKFILL (TY B)
STA 200.000 $265.000 $200.000 $249.110 $100.000 $310.000 $575.000 $350.000 $409.000 $305.000
HYDRO MULCH SEED (PERM_RURAL_CLAY)
SY 1,444.000 $1.750 $3.000 $1.250 $1.250 $2.650 $3.570 $5.000 $4.750 $4.000
VEGETATIVE WATERING
TGL 50.600 $45.000 $50.000 $206.000 $200.000 $250.000 $205.000 $150.000 $55.500 $77.000
WILDFLOWER SEEDING
AC 0.300 $2,500.000 $13,000.000 $5,000.000 $5,000.000 $12,500.000 $10,000.000 $8,500.000 $13,325.000 $10,750.000
D-GR HMA TY-D PG70-28 (LEVEL-UP)
TON 4,069.000 $140.000 $135.000 $112.280 $185.000 $210.000 $225.000 $180.000 $223.000 $215.000
TACK COAT
GAL 9,434.000 $4.000 $4.000 $0.010 $0.100 $0.100 $4.080 $4.000 $4.000 $4.450
TOM-C PG76-22 SAC-A
TON 6,772.000 $220.000 $180.000 $212.500 $250.000 $190.000 $215.000 $220.000 $236.300 $252.000
TACK COAT
GAL 31,405.000 $4.000 $4.000 $0.010 $0.100 $0.100 $4.080 $4.000 $4.000 $0.100
FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")
SY 5,632.000 $120.000 $85.000 $79.560 $105.000 $95.000 $122.100 $100.000 $138.450 $125.000
PLANE & TEXT ASPH CONC PAV(0" TO 1")
SY 162,160.000 $2.500 $2.000 $2.000 $0.750 $1.800 $2.900 $2.250 $2.900 $2.100
FLOWABLE BACKFILL
CY 5.000 $500.000 $900.000 $972.900 $900.000 $865.000 $972.900 $350.000 $600.000 $900.000
RIPRAP (CONC)(4 IN)
CY 66.000 $880.000 $800.000 $692.300 $600.000 $760.000 $572.520 $550.000 $1,200.000 $775.000
RIPRAP (MOW STRIP)(4 IN)
CY 334.000 $750.000 $775.000 $706.530 $575.000 $725.000 $617.770 $550.000 $1,267.000 $800.000
RIPRAP (STONE COMMON)(GROUT)(18 IN)
CY 42.000 $400.000 $510.000 $390.300 $200.000 $475.000 $343.240 $185.000 $400.000 $535.000
MOBILIZATION
LS 1.000 $518,133.000 $490,000.000 $503,925.760 $255,000.000 $450,000.000 $544,425.000 $600,000.000 $333,715.000 $686,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $17,806.000 $2,500.000 $26,022.820 $16,000.000 $25,000.000 $9,500.000 $15,000.000 $3,750.000 $47,083.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $12,500.000 $49,500.000 $9.000 $25,000.000 $15,000.000 $22,000.000 $20,000.000 $20,000.000 $22,000.000
TMA (STATIONARY)
DAY 610.000 $250.000 $0.010 $0.010 $0.100 $50.000 $170.000 $250.000 $60.000 $1.000
TMA (MOBILE OPERATION)
DAY 98.000 $425.000 $0.010 $0.010 $0.100 $55.000 $170.000 $550.000 $600.000 $1.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 7,160.000 $4.000 $3.250 $3.600 $0.500 $2.950 $1.950 $4.000 $6.000 $2.250
TEMP SEDMT CONT FENCE (REMOVE)
LF 7,160.000 $2.000 $1.500 $1.100 $0.250 $1.350 $1.000 $2.000 $1.350 $1.150
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 200.000 $7.500 $10.500 $5.000 $6.000 $10.000 $9.260 $12.000 $12.350 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 200.000 $2.500 $4.000 $1.250 $1.000 $4.000 $2.000 $6.000 $2.650 $2.120
PCTB (FUR&INST)(F-SHAPE OR SNGL SLP)TY1
LF 390.000 $80.000 $65.000 $120.000 $55.000 $60.000 $105.000 $100.000 $123.000 $65.000
PCTB (MOVE)(F-SHAPE OR SNGL SLP)TY1
LF 390.000 $25.000 $32.000 $30.000 $28.000 $31.000 $15.000 $20.000 $41.000 $33.000
PCTB (REMOVE)(F-SHAPE OR SNGL SLP)TY1
LF 390.000 $22.000 $42.000 $40.000 $36.000 $40.000 $35.000 $20.000 $41.000 $42.000
INTERSECTIONS (ACP)
SY 5,139.000 $70.000 $45.000 $24.090 $34.000 $32.000 $39.250 $45.000 $33.200 $140.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 46,964.000 $0.500 $0.300 $0.140 $0.200 $0.150 $0.250 $0.300 $0.330 $0.420
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 30,275.000 $0.500 $0.350 $0.140 $0.200 $0.150 $0.270 $0.300 $0.330 $0.480
MTL W-BEAM GD FEN (TIM POST)
LF 3,675.000 $30.000 $26.000 $20.600 $22.000 $25.000 $20.600 $25.000 $30.000 $27.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 8.000 $2,500.000 $2,100.000 $1,600.000 $1,590.000 $2,000.000 $1,600.000 $1,850.000 $2,826.600 $2,200.000
SHORT RADIUS (28")
LF 25.000 $500.000 $28.500 $38.000 $70.000 $27.000 $38.000 $100.000 $33.350 $30.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 1.000 $2,000.000 $855.000 $1,250.000 $880.000 $815.000 $1,250.000 $1,850.000 $1,000.000 $875.000
MTL BM GD FEN TRANS (31"-28")(25')
EA 1.000 $5,000.000 $650.000 $750.000 $464.000 $610.000 $750.000 $1,850.000 $750.000 $650.000
REMOVE METAL BEAM GUARD FENCE
LF 3,725.000 $5.000 $3.500 $2.000 $3.000 $3.250 $2.000 $3.000 $4.000 $3.500
REMOVE TERMINAL ANCHOR SECTION
EA 6.000 $400.000 $230.000 $200.000 $200.000 $215.000 $200.000 $500.000 $267.000 $235.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 8.000 $410.000 $285.000 $200.000 $250.000 $270.000 $200.000 $500.000 $335.000 $300.000
GUARDRAIL END TREATMENT (INSTALL)
EA 35.000 $3,413.480 $3,350.000 $2,940.000 $2,523.000 $3,200.000 $2,940.000 $3,850.000 $3,935.000 $3,600.000
GUARDRAIL END TREATMENT (REMOVE)
EA 29.000 $450.000 $285.000 $200.000 $250.000 $275.000 $200.000 $1,500.000 $335.000 $300.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $7,000.000 $2,300.000 $2,700.000 $2,000.000 $2,200.000 $3,000.000 $6,500.000 $4,825.000 $2,300.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $5,500.000 $1,700.000 $1,000.000 $1,500.000 $1,650.000 $1,200.000 $2,500.000 $3,330.000 $1,700.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $12,000.000 $12,000.000 $8,750.000 $10,000.000 $10,850.000 $9,000.000 $21,000.000 $15,465.000 $11,000.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BR)
EA 12.000 $45.000 $25.000 $31.000 $20.000 $22.000 $31.000 $100.000 $26.000 $23.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 74.000 $40.000 $30.000 $35.000 $9.000 $27.000 $35.000 $100.000 $33.000 $30.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 75,049.000 $0.350 $0.190 $0.190 $0.190 $0.210 $0.190 $1.000 $0.250 $0.220
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 2,028.000 $0.500 $0.500 $0.500 $0.500 $0.550 $0.500 $6.000 $0.670 $0.600
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 324.000 $6.500 $2.350 $2.350 $2.350 $2.550 $2.350 $20.000 $3.150 $2.700
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 22.000 $120.000 $85.000 $85.000 $85.000 $92.000 $85.000 $250.000 $113.000 $95.000
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 18.000 $110.000 $95.000 $95.000 $95.000 $103.000 $95.000 $250.000 $126.000 $106.000
WK ZN PAV MRK NON-REMOV(W)36"(YLD TRI)
EA 4.000 $25.000 $45.000 $45.000 $45.000 $49.000 $45.000 $250.000 $60.000 $50.000
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 3,043.000 $0.550 $0.250 $0.250 $0.250 $0.270 $0.250 $1.000 $0.330 $0.300
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 72,551.000 $0.360 $0.190 $0.190 $0.190 $0.210 $0.190 $1.000 $0.250 $0.230
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 3,962.000 $7.000 $2.000 $0.750 $1.000 $2.000 $2.240 $6.000 $1.350 $1.250
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,856.000 $6.000 $2.000 $0.750 $1.000 $2.000 $2.240 $6.000 $1.350 $1.250
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 2,028.000 $2.000 $0.830 $0.830 $0.830 $0.900 $0.830 $6.000 $1.100 $0.900
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 324.000 $15.000 $6.000 $6.000 $6.000 $6.500 $6.000 $20.000 $8.000 $6.500
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 22.000 $160.000 $135.000 $135.000 $135.000 $146.000 $135.000 $250.000 $180.000 $145.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 18.000 $200.000 $145.000 $145.000 $145.000 $157.000 $145.000 $250.000 $194.000 $156.000
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
EA 4.000 $125.000 $45.000 $45.000 $45.000 $50.000 $45.000 $250.000 $60.000 $49.000
RE PROFILE PM TY I(W)6"(SLD)(100MIL)
LF 28,016.000 $2.000 $0.700 $0.700 $0.700 $0.760 $0.700 $0.750 $0.930 $0.800
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 47,033.000 $2.000 $0.490 $0.490 $0.490 $0.530 $0.490 $0.750 $0.650 $0.550
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 3,043.000 $1.000 $0.530 $0.530 $0.530 $0.580 $0.530 $0.750 $0.710 $0.600
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 72,551.000 $1.000 $0.490 $0.490 $0.490 $0.530 $0.490 $0.750 $0.650 $0.550
REFL PAV MRKR TY I-C
EA 97.000 $6.330 $4.150 $4.150 $4.150 $4.500 $4.150 $6.000 $5.530 $4.750
REFL PAV MRKR TY II-A-A
EA 1,779.000 $6.920 $4.000 $4.000 $4.000 $4.350 $4.000 $6.000 $5.330 $4.750
BRIDGE JOINT REPAIR (SEJ)
LF 90.000 $450.000 $250.000 $207.000 $200.000 $550.000 $180.000 $1,000.000 $288.000 $275.000
Totals: $5,966,546.150 $4,574,922.620 $4,581,143.310 $4,632,512.590 $5,024,292.780 $5,773,264.890 $5,918,427.950 $5,974,502.160 $6,867,729.890
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
Total: $20,000.00