Show Job Controls
Bid Cobra

JOHNSON FM 731 (1094-04-016)

Items: 42

County: JOHNSON
Length: N/A
Highway: FM 731
District: FORT WORTH
Control Number: 1094-04-016
DBE Goal: N/A
Project: STP 2019(012)
Guaranty: N/A
Time: 41 WORKING DAYS
Engineer's Estimate: $1,931,143.95
Date: 09/06/2018 (7 years ago)
Contract Number: N/A
Type: BASE RPR, OVERLAY, PAVMT MARK
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$1,931,143.95
$1,866,926.45
Over/Under Est: -3.33% -$64,217.50
Over/Under Est: -2.88% -$55,563.35
Amt Left: 0.46% $8,654.15
Over/Under Est: 5.44% $105,021.95
Amt Left: 9.07% $169,239.45
Delta: -8.56% -$160,585.30
$2,090,232.60
Over/Under Est: 8.24% $159,088.65
Amt Left: 11.96% $223,306.15
Delta: -2.66% -$54,066.70

Bid Items & Bid Tabulations

42 Total 0 of 42
JOHNSON  |  FM 731  |  FORT WORTH  |  1094-04-016  |  09/06/2018  |  $1,931,143.95  |  STP 2019(012)  |  BASE RPR, OVERLAY, PAVMT MARK  |  41 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
PEACHTREE CONSTRUCTION, LTD.
OLDCASTLE MATERIALS TEXAS, INC.
NORTHEASTERN PAVERS, INC.
A. L. HELMCAMP, INC.
REMOVING CONC (DRIVEWAYS)
SY 842.000 $20.000 $28.000 $20.000 $30.000 $40.000
BACKFILL (TY B)
STA 230.000 $150.000 $280.000 $228.250 $225.000 $190.000
D-GR HMA TY C SAC-A PG70-28(LATEX ADD)
TON 14,871.000 $85.000 $85.500 $82.570 $90.000 $94.100
PLAN & TEXT ASPH CONC PAV (2")
SY 19,751.000 $1.300 $1.900 $1.700 $1.750 $1.900
CONC STR REPR(REMOV AND REPL WINGWALL)
CY 1.300 $1,700.000 $4,500.000 $2,500.000 $3,400.000 $10,000.000
MOBILIZATION
LS 1.000 $167,296.150 $110,000.000 $180,200.000 $200,000.000 $151,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $20,000.000 $4,500.000 $13,800.000 $1,200.000 $10,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 500.000 $2.500 $1.500 $2.000 $4.000 $5.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 500.000 $1.000 $0.750 $0.400 $3.000 $2.200
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 1,000.000 $5.000 $5.000 $5.000 $4.000 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,000.000 $1.000 $0.750 $1.000 $2.000 $2.200
INTERSECTIONS (CONC)
SY 94.000 $70.000 $125.000 $103.000 $130.000 $125.000
INTERSECTIONS (ACP)
SY 498.000 $35.000 $19.000 $24.000 $20.000 $22.000
DRIVEWAYS (CONC)
SY 747.000 $70.000 $125.000 $98.000 $130.000 $125.000
DRIVEWAYS (ACP)
SY 3,248.000 $35.000 $17.000 $20.360 $20.000 $22.000
MTL W-BEAM GD FEN (TIM POST)
LF 900.000 $20.000 $22.000 $19.000 $24.000 $22.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,600.000 $2,100.000 $1,500.000 $2,300.000 $1,600.000
REMOVE METAL BEAM GUARD FENCE
LF 850.000 $3.000 $2.100 $3.500 $2.500 $4.000
RM MTL BM GD FEN TRANS (T101)
EA 4.000 $200.000 $110.000 $280.000 $120.000 $350.000
GUARDRAIL END TREATMENT (INSTALL)
EA 10.000 $2,500.000 $3,100.000 $2,500.000 $3,300.000 $2,900.000
GUARDRAIL END TREATMENT (REMOVE)
EA 10.000 $250.000 $55.000 $300.000 $58.000 $370.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 57.000 $20.000 $44.000 $25.000 $50.000 $26.000
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 260.000 $0.300 $0.210 $0.200 $0.200 $0.200
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 46,400.000 $0.300 $0.210 $0.200 $0.200 $0.200
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 2,280.000 $0.300 $0.210 $0.200 $0.200 $0.200
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 37,655.000 $0.300 $0.210 $0.200 $0.200 $0.200
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 50.000 $1.000 $2.000 $1.000 $1.000 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,500.000 $1.000 $2.000 $1.000 $1.000 $1.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,210.000 $1.000 $0.800 $0.740 $0.740 $0.800
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 86.000 $5.000 $3.300 $3.000 $3.000 $3.200
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 190.000 $10.000 $6.500 $6.000 $6.000 $6.500
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 8.000 $150.000 $115.000 $105.000 $105.000 $110.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 10.000 $150.000 $135.000 $125.000 $125.000 $130.000
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 558.000 $10.000 $6.500 $6.000 $6.000 $6.500
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 260.000 $0.400 $0.380 $0.350 $0.350 $0.360
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 46,400.000 $0.400 $0.380 $0.350 $0.350 $0.360
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 2,280.000 $0.400 $0.380 $0.350 $0.350 $0.360
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 37,655.000 $0.400 $0.380 $0.350 $0.350 $0.360
REFL PAV MRKR TY I-C
EA 52.000 $5.000 $3.200 $3.000 $3.000 $3.200
REFL PAV MRKR TY II-A-A
EA 844.000 $5.000 $3.200 $3.000 $3.000 $3.200
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $12,000.000 $6,000.000 $3,570.000 $10,000.000 $7,500.000
TMA (STATIONARY)
EA 2.000 $1,500.000 $10,000.000 $13,696.000 $17,000.000 $20,000.000
Totals: $1,931,143.950 $1,866,926.450 $1,875,580.600 $2,036,165.900 $2,090,232.600