Show Job Controls
Bid Cobra

JOHNSON FM 731 (1094-04-010)

Items: 85

County: JOHNSON
Length: 0.1340 MILES
Highway: FM 731
District: FORT WORTH
Control Number: 1094-04-010
DBE Goal: 4.0%
Project: BR 2025(573)
Guaranty: $74,000.00
Time: 152 WORKING DAYS
Engineer's Estimate: $3,591,277.58
Date: 03/05/2025 (1 year ago)
Contract Number: 3253219
Type: BRIDGE REPLACEMENT
Project ID: A00044436
Contract Type: Federal
Project Description: REPLACE BRIDGE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DANIEL POOLE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$3,591,277.58
$3,569,153.54
Over/Under Est: -0.62% -$22,124.04
Over/Under Est: 4.18% $150,253.33
Amt Left: 4.83% $172,377.37
Over/Under Est: 20.28% $728,470.95
Amt Left: 21.03% $750,594.99
Delta: -15.45% -$578,217.62
Subcontractor Percentage Amount
TUCAN CONTRACTING, LLC 25.91% $930,508.62
STOIC CIVIL CONSTRUCTION, INC. 12.59% $452,146.02
PEACHTREE CONSTRUCTION, LTD. 5.87% $210,809.94
JAMESBOY, LLC 5.47% $196,444.70
BEAIRD DRILLING SERVICES, INC. 3.82% $137,188.07
FARR FOUNDATION, INC. 3.15% $113,126.29
USA SWPPP INSPECTIONS, INC.DBA USA EROSION 1.33% $47,764.43
LINDAMOOD, INC. 0.84% $30,167.01
DIIBS SPECIALISTS, LLC 0.79% $28,371.35
TRP CONSTRUCTION GROUP, LLC 0.72% $25,857.44
CIVIL TREE SOLUTIONS, LLC 0.66% $23,702.65
TEX OP CONSTRUCTION, LP 0.37% $13,287.85
K&A REBAR & POST-TENSION LLC 0.13% $4,668.70
Total: 61.65% $2,214,043.07

Bid Items & Bid Tabulations

85 Total 0 of 85
JOHNSON  |  FM 731  |  FORT WORTH  |  1094-04-010  |  03/05/2025  |  $3,591,277.58  |  BR 2025(573)  |  BRIDGE REPL  |  152 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TALBERT COMPANIES LLC
COPPELL CONSTRUCTION CO., INC.
ED BELL CONSTRUCTION COMPANY
PREPARING ROW
STA 7.060 $14,279.000 $3,620.890 $4,000.000 $35,000.000
REMOV CONC (RIPRAP)
SY 211.000 $50.000 $101.899 $25.000 $42.000
RMV (12") TRT/UNTRT BASE & ASPH PAV
SY 1,724.000 $60.000 $8.224 $23.000 $7.500
EXCAV (ROADWAY)
CY 654.000 $37.000 $57.534 $42.000 $55.000
EMBANK (FNL)(DC)(TY C)
CY 618.000 $25.000 $31.304 $57.000 $55.000
BACKFILL (TY B)
STA 6.220 $335.000 $413.875 $4,000.000 $1,000.000
COMPOST MANUF TOPSOIL (4")
SY 1,942.000 $5.100 $19.103 $5.000 $11.250
BROADCAST SEED (PERM_URBAN_CLAY)
SY 3,089.000 $0.700 $1.881 $0.800 $6.000
DRILL SEED (TEMP_WARM)
SY 1,545.000 $0.300 $0.484 $1.200 $0.750
DRILL SEED (TEMP_COOL)
SY 1,545.000 $0.300 $0.570 $1.200 $0.750
VEGETATIVE WATERING
TGL 109.000 $116.000 $161.250 $50.000 $3.000
FL BS (CMP IN PLC)(TY A GR 1-2) (4")
SY 2,036.000 $20.000 $21.500 $27.000 $26.000
PRIME COAT (MC-30)
GAL 611.000 $11.000 $21.500 $22.000 $25.000
D-GR HMA TY-B PG64-22
TON 814.000 $237.000 $171.194 $144.000 $160.000
SP MIXES SP-C SAC-A PG70-28
TON 231.000 $206.000 $212.850 $222.000 $250.000
TACK COAT
GAL 401.000 $10.000 $2.688 $8.000 $9.000
CEM STABIL BKFL
CY 164.000 $248.000 $214.875 $350.000 $400.000
TEMPORARY SPL SHORING
SF 5,592.000 $51.000 $64.500 $63.000 $75.000
DRILL SHAFT (36 IN)
LF 592.000 $383.000 $249.400 $370.000 $350.000
CL C CONC (ABUT)(HPC)
CY 45.200 $1,787.000 $1,664.519 $1,700.000 $2,500.000
CL C CONC (CAP)(HPC)
CY 41.600 $2,024.000 $1,612.715 $1,500.000 $2,000.000
CL C CONC (COLUMN)(HPC)
CY 31.400 $2,013.000 $2,046.445 $1,600.000 $2,250.000
REINF CONC SLAB (HPC)
SF 5,500.000 $34.000 $34.400 $39.000 $40.000
APPROACH SLAB (HPC)
CY 91.900 $930.000 $967.500 $1,050.000 $1,250.000
RETAINING WALL (MSE)
SF 3,825.000 $93.000 $138.675 $106.000 $150.000
PRESTR CONC GIRDER (TX28)
LF 651.020 $242.000 $212.044 $333.000 $450.000
RIPRAP (CONC)(5 IN)
CY 75.000 $845.000 $752.500 $450.000 $850.000
RIPRAP (MOW STRIP)(5 IN)
CY 53.000 $584.000 $467.625 $750.000 $900.000
RAIL (TY T223)(HPC)
LF 737.000 $119.000 $162.626 $155.000 $150.000
SEALED EXPANSION JOINT (4 IN) (SEJ - B)
LF 98.500 $200.000 $168.775 $190.000 $150.000
GABION MATTRESSES (GALV)(18 IN)
SY 660.000 $306.000 $182.750 $235.000 $187.000
GABIONS (3' X 3')(GALV)
CY 273.000 $315.000 $413.875 $250.000 $425.000
GABION (1.5' X 3')(GALV)
CY 46.000 $210.000 $236.500 $455.000 $242.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $45,000.000 $32,389.750 $230,000.000 $60,000.000
MOBILIZATION
LS 1.000 $320,000.000 $263,850.000 $330,000.000 $376,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $15,000.000 $8,062.500 $15,000.000 $15,750.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $11,482.000 $12,933.024 $15,000.000 $8,500.000
TMA (STATIONARY)
DAY 8.000 $240.000 $268.750 $350.000 $315.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 69.000 $35.000 $58.974 $37.000 $55.000
ROCK FILTER DAMS (REMOVE)
LF 69.000 $15.000 $24.209 $25.000 $31.000
CONSTRUCTION EXITS (INSTALL) (TY 2)
SY 312.000 $36.000 $50.514 $45.000 $80.000
CONSTRUCTION EXITS (REMOVE)
SY 312.000 $16.000 $21.274 $10.000 $40.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,459.000 $4.000 $5.966 $3.500 $3.650
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,459.000 $1.400 $2.354 $1.000 $1.250
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 60.000 $8.000 $8.105 $7.000 $8.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 60.000 $3.000 $3.408 $2.000 $2.000
CONSTRUCTING DETOURS
SY 198.000 $95.000 $182.750 $165.000 $180.200
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 10.000 $6,624.000 $4,300.000 $5,000.000 $7,375.330
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 1,350.000 $72.000 $99.975 $86.000 $50.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 480.000 $18.000 $22.210 $16.000 $12.500
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 1,350.000 $25.000 $21.500 $19.000 $25.000
PORT CTB (PINNING)
EA 32.000 $70.000 $50.000 $90.000 $75.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 1,887.000 $0.600 $3.150 $4.000 $2.500
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 1,109.000 $0.400 $1.129 $4.000 $3.750
MTL W-BEAM GD FEN (TIM POST)
LF 200.000 $32.000 $26.875 $25.000 $25.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,295.000 $2,096.250 $1,750.000 $3,017.570
MTL W-BEAM GD FEN ADJUSTMENT
LF 25.000 $21.000 $12.900 $25.000 $25.000
SHORT RADIUS (28")
LF 25.000 $454.000 $48.375 $35.000 $50.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 1.000 $522.000 $913.750 $875.000 $1,000.000
REMOVE METAL BEAM GUARD FENCE
LF 525.000 $5.000 $2.688 $2.250 $3.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 4.000 $284.000 $268.750 $150.000 $200.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 4.000 $300.000 $268.750 $150.000 $350.000
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $3,035.000 $3,225.000 $3,000.000 $3,000.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $2,647.000 $1,612.500 $2,500.000 $2,000.000
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $1,500.000 $967.500 $1,000.000 $1,000.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 4.000 $12,462.000 $9,137.500 $8,700.000 $9,450.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 2.000 $311.000 $344.000 $320.000 $295.000
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 1.000 $530.000 $419.250 $390.000 $295.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $814.000 $827.750 $770.000 $610.000
REMOVE SM RD SN SUP&AM
EA 2.000 $200.000 $145.125 $135.000 $150.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 11.000 $40.000 $10.750 $25.000 $18.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 12.000 $57.000 $25.800 $29.000 $30.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 4.000 $100.000 $48.375 $60.000 $60.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 505.000 $1.400 $0.376 $0.750 $2.000
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 4,020.000 $1.600 $1.440 $1.000 $1.500
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 48.000 $11.000 $14.642 $10.000 $15.750
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 144.000 $4.000 $1.075 $10.000 $7.500
RE PM TY II (W) 6" (SLD)
LF 2,963.000 $1.200 $1.000 $0.500 $1.500
RE PM TY II (Y) 6" (SLD)
LF 2,160.000 $1.400 $0.957 $0.500 $1.500
TY I HIGH PERF PM (W)6"(SLD)(100MIL)
LF 3,673.000 $1.600 $0.849 $1.000 $2.000
TY I HIGH PERF PM (Y)6"(SLD)(100MIL)
LF 2,870.000 $1.600 $0.849 $1.000 $2.000
REFL PAV MRKR TY II-A-A
EA 37.000 $9.000 $11.682 $10.000 $15.000
ELIM EXT PM & MRKS (4")
LF 6,880.000 $2.200 $0.699 $0.750 $0.700
ELIM EXT PM & MRKS (RUMBLE STRIP)
LF 2,075.000 $1.700 $80.518 $0.750 $6.000
PAV SURF PREP FOR MRK (6")
LF 5,123.000 $0.500 $1.140 $0.600 $0.500
Totals: $3,591,277.580 $3,569,156.237 $3,741,530.910 $4,319,748.530
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $20,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $20,000.00
Total: $40,000.00