Show Job Controls
Bid Cobra

JIM WELLS FM 1930 (0990-02-015)

Items: 15

County: JIM WELLS
Length: 0.0000 MILES
Highway: FM 1930
District: CORPUS CHRISTI
Control Number: 0990-02-015
DBE Goal: 0.0%
Project: STP 2026(671)HRR
Guaranty: $10,000.00
Time: 16 WORKING DAYS
Engineer's Estimate: $440,635.56
Date: 06/02/2026 (8 days ago) Changed
Contract Number: 6263211
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00212685
Contract Type: Federal Waived
Project Description: INSTALL PREFORMED EDGELINE AND CENTERLINE RUMBLE STRIPS.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ROBERTO JIMENEZ
LUCIA ADAME
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$440,635.56
Over/Under Est: -15.07% -$66,415.96
Over/Under Est: -12.76% -$56,208.54
Amt Left: 2.73% $10,207.42
$401,203.47
Over/Under Est: -8.95% -$39,432.09
Amt Left: 7.21% $26,983.87
Delta: -4.36% -$16,776.45
$414,708.64
Over/Under Est: -5.88% -$25,926.92
Amt Left: 10.82% $40,489.04
Delta: -3.37% -$13,505.17
$466,904.03
Over/Under Est: 5.96% $26,268.47
Amt Left: 24.77% $92,684.43
Delta: -12.59% -$52,195.39

Bid Items & Bid Tabulations

15 Total 0 of 15
JIM WELLS  |  FM 1930  |  CORPUS CHRISTI  |  0990-02-015  |  06/02/2026  |  $440,635.56  |  STP 2026(671)HRR  |  HAZARD ELIM & SAFETY  |  16 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TRP INFRASTRUCTURE SERVICES, LLC
PAVEMENT MARKINGS INC.
STRIPE-A-ZONE, LLC
L&L COMPANY
STRIPE LINES, INC.
MOBILIZATION
LS 1.000 $38,391.000 $3,700.000 $5,000.000 $5,000.000 $1.000 $12,500.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 1.000 $1,000.000 $1,500.000 $10.000 $2,000.000 $1.000 $150.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 8.000 $1,500.000 $50.000 $10.000 $50.000 $500.000 $1.000
TMA (MOBILE OPERATION)
DAY 28.000 $275.500 $400.000 $10.000 $1.000 $1.000 $15.000
REFL PAV MRK TY I (W)6"(SLD)(090MIL)
LF 256,678.000 $0.500 $0.400 $0.440 $0.490 $0.480 $0.470
REFL PAV MRK TY I (Y)6"(BRK)(090MIL)
LF 30,855.000 $0.630 $0.600 $0.620 $0.510 $0.480 $0.470
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
LF 107,060.000 $0.500 $0.440 $0.480 $0.510 $0.480 $0.470
PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE)
LF 28,870.000 $2.800 $3.000 $2.900 $3.050 $3.500 $4.390
PREFAB PM TY C (W)(24")(SLD)
LF 43.000 $15.400 $21.000 $16.800 $15.000 $11.000 $11.090
PREFAB PM TY C (W)(RR XING)
EA 2.000 $517.000 $700.000 $680.000 $450.000 $500.000 $397.250
PRFB RUMBLE STRIP (BLK)(1')(EDGELINE)
LF 29,162.000 $2.800 $3.000 $3.200 $3.050 $3.500 $4.390
REFL PAV MRKR TY II-A-A
EA 3,090.000 $4.500 $3.500 $4.200 $5.500 $4.000 $3.240
ELIM EXT PM & MRKS (24")
LF 43.000 $4.770 $5.000 $6.000 $3.000 $3.000 $4.890
ELIM EXT PM & MRKS (RR XING)
EA 2.000 $135.500 $50.000 $100.000 $200.000 $100.000 $50.000
PREFORMED IN-LANE (TRANS) RUMBLE STRIP
LF 80.000 $20.700 $20.000 $38.000 $20.000 $50.000 $25.170
Totals: $440,635.560 $374,219.600 $384,427.020 $401,203.470 $414,708.640 $466,904.030
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $2,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $9,598.00
Total: $11,598.00