Bid Cobra

JEFFERSON US0090 (6338-55-001)

Items: 16

County: JEFFERSON
Length: N/A
Highway: US0090
District: BEAUMONT
Control Number: 6338-55-001
DBE Goal: N/A
Project: BPM - 633855001
Guaranty: N/A
Time: 34 W
Engineer's Estimate: $154,748.00
Date: 01/09/2019 (7 years ago)
Contract Number: N/A
Type: RIPRAP AND SCOUR REPAIRS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$154,748.00
$141,495.00
Over/Under Est: -8.56% -$13,253.00
Over/Under Est: -8.35% -$12,924.00
Amt Left: 0.23% $329.00
Over/Under Est: 5.17% $8,002.00
Amt Left: 15.02% $21,255.00
Delta: -14.75% -$20,926.00
Over/Under Est: 23.5% $36,367.00
Amt Left: 35.07% $49,620.00
Delta: -17.43% -$28,365.00

Bid Items & Bid Tabulations

16 Total 0 of 16
JEFFERSON  |  US0090  |  BEAUMONT  |  6338-55-001  |  01/09/2019  |  $154,748.00  |  BPM - 633855001  |  RIPRAP AND SCOUR REPAIRS  |  34 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
WIDGEON CONSTRUCTION, INC.
CHAMPION INFRASTRUCTURE, LLC
TALBRAN ENTERPRISES LLC
FNH CONSTRUCTION, LLC
PREP ROW (TREE)(LESS THAN 24" DIA)
EA 1.000 $900.000 $1,070.000 $400.000 $2,000.000 $5,000.000
REMOVING CONC (RIPRAP)
CY 50.000 $125.000 $45.000 $150.000 $50.000 $100.000
EXCAVATION (CHANNEL)
CY 40.000 $70.000 $48.000 $50.000 $150.000 $50.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 180.000 $25.000 $68.000 $42.000 $35.000 $35.000
SPEC EXCAV WORK (BACKHOE)
HR 40.000 $180.000 $165.000 $120.000 $150.000 $200.000
BLOCK SODDING
SY 28.000 $20.000 $12.000 $18.000 $10.000 $30.000
VEGETATIVE WATERING
MG 20.000 $50.000 $200.000 $80.000 $75.000 $100.000
RIPRAP (CONC)(5 IN)
CY 41.000 $450.000 $567.000 $680.000 $400.000 $700.000
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 287.000 $250.000 $178.000 $140.000 $150.000 $185.000
RC PIPE (CL III)(24 IN)
LF 12.000 $100.000 $117.000 $210.000 $100.000 $150.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $2,000.000 $2,219.000 $3,200.000 $2,200.000 $2,500.000
REMOV STR (PIPE)
LF 6.000 $25.000 $165.000 $100.000 $50.000 $50.000
MOBILIZATION
LS 1.000 $14,068.000 $11,960.000 $20,000.000 $25,000.000 $20,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $2,500.000 $2,300.000 $3,200.000 $10,000.000 $8,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 148.000 $40.000 $48.000 $35.000 $40.000 $60.000
TMA (STATIONARY)
DAY 34.000 $250.000 $175.000 $150.000 $350.000 $550.000
Totals: $154,748.000 $141,495.000 $141,824.000 $162,750.000 $191,115.000