REMOVING CONC (PAV)
|
SY
|
248.000
|
$5.000
|
$12.000
|
$40.000
|
$32.000
|
|
|
REMOVING CONCRETE(MOW STRIP)
|
LF
|
427.000
|
$6.870
|
$13.000
|
$10.000
|
$18.000
|
|
|
REMOVING STAB BASE AND ASPH PAV (2")
|
SY
|
248.000
|
$10.000
|
$10.000
|
$20.250
|
$18.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
571.000
|
$10.000
|
$58.000
|
$17.250
|
$40.000
|
|
|
EXCAVATION (CHANNEL)
|
CY
|
916.000
|
$10.000
|
$15.000
|
$13.250
|
$30.000
|
|
|
SUBGRADE WIDENING (DENS CONT)
|
STA
|
9.910
|
$550.000
|
$100.000
|
$2,443.000
|
$2,150.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
6,154.000
|
$7.510
|
$28.000
|
$24.500
|
$23.000
|
|
|
BLADING
|
HR
|
40.000
|
$120.000
|
$100.000
|
$133.000
|
$264.000
|
|
|
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
|
AC
|
3.120
|
$2,525.000
|
$2,807.070
|
$1,710.000
|
$1,870.000
|
|
|
VEGETATIVE WATERING
|
MG
|
169.400
|
$19.270
|
$20.000
|
$23.000
|
$70.000
|
|
|
PROOF ROLLING
|
HR
|
16.000
|
$100.000
|
$50.000
|
$102.000
|
$134.000
|
|
|
LIME TRT (EXST MATL) (6")
|
SY
|
2,835.000
|
$1.760
|
$6.000
|
$7.500
|
$19.000
|
|
|
LIME (HYD, COM, OR QK(SLURRY))
|
TON
|
42.000
|
$180.000
|
$195.000
|
$240.000
|
$241.000
|
|
|
D-GR HMA(SQ) TY-B PG64-22
|
TON
|
1,111.000
|
$93.000
|
$100.000
|
$100.000
|
$98.000
|
|
|
D-GR HMA(SQ) TY-B PG64-22 (LEVEL UP)
|
TON
|
6.000
|
$152.000
|
$145.000
|
$217.000
|
$1,100.000
|
|
|
TACK COAT
|
GAL
|
149.000
|
$3.500
|
$6.000
|
$4.750
|
$11.000
|
|
|
PLANE ASPH CONC PAV(0" TO 2")
|
SY
|
270.000
|
$2.000
|
$20.000
|
$20.100
|
$44.000
|
|
|
CEM STABIL BKFL
|
CY
|
66.000
|
$75.000
|
$140.000
|
$180.000
|
$222.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
1,431.000
|
$18.490
|
$25.000
|
$60.000
|
$113.000
|
|
|
PRESTR CONC PIL (18 IN SQ)
|
LF
|
1,638.000
|
$140.000
|
$110.000
|
$108.000
|
$199.000
|
|
|
CL C CONC (ABUT)
|
CY
|
51.600
|
$900.000
|
$1,500.000
|
$2,100.000
|
$1,800.000
|
|
|
CL C CONC (CAP)
|
CY
|
20.600
|
$1,046.650
|
$2,100.000
|
$2,500.000
|
$2,200.000
|
|
|
REINF CONC SLAB (SLAB BEAM)
|
SF
|
5,670.000
|
$18.000
|
$22.000
|
$30.850
|
$35.000
|
|
|
APPROACH SLAB
|
CY
|
128.000
|
$365.040
|
$500.000
|
$490.000
|
$517.000
|
|
|
PRESTR CONC SLAB BEAM (4SB12)
|
LF
|
532.000
|
$133.000
|
$185.000
|
$152.000
|
$259.000
|
|
|
PRESTR CONC SLAB BEAM (5SB12)
|
LF
|
665.000
|
$160.000
|
$190.000
|
$147.000
|
$237.000
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
66.000
|
$500.000
|
$525.000
|
$540.000
|
$431.000
|
|
|
RIPRAP (STONE PROTECTION)(18 IN)
|
CY
|
904.000
|
$125.000
|
$170.000
|
$182.000
|
$206.000
|
|
|
RAIL (TY T223)
|
LF
|
318.000
|
$111.680
|
$110.000
|
$169.000
|
$248.000
|
|
|
ARMOR JOINT (SEALED)
|
LF
|
152.000
|
$110.000
|
$90.000
|
$116.000
|
$175.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
240.000
|
$73.400
|
$80.000
|
$48.250
|
$75.000
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
211.000
|
$150.000
|
$125.000
|
$201.000
|
$150.000
|
|
|
RC PIPE (CL III)(60 IN)
|
LF
|
176.000
|
$245.000
|
$280.000
|
$352.000
|
$366.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$800.000
|
$1,500.000
|
$854.000
|
$1,050.000
|
|
|
SET (TY II) (36 IN) (RCP) (6: 1) (P)
|
EA
|
1.000
|
$4,233.210
|
$6,000.000
|
$3,510.000
|
$10,300.000
|
|
|
SET (TY II) (60 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$10,000.000
|
$8,000.000
|
$8,520.000
|
$16,700.000
|
|
|
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
|
EA
|
2.000
|
$13,000.000
|
$100,000.000
|
$64,000.000
|
$51,850.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$100,000.000
|
$200,000.000
|
$250,000.000
|
$111,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
12.000
|
$6,786.700
|
$10,000.000
|
$2,000.000
|
$2,600.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
100.000
|
$33.000
|
$60.790
|
$33.000
|
$36.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
100.000
|
$9.240
|
$14.070
|
$8.150
|
$9.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
444.000
|
$32.000
|
$45.860
|
$24.500
|
$22.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
444.000
|
$9.080
|
$9.620
|
$14.000
|
$9.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (18")
|
LF
|
740.000
|
$5.800
|
$6.840
|
$5.050
|
$5.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
740.000
|
$1.290
|
$2.150
|
$1.030
|
$1.000
|
|
|
ONE-WAY TRAF CONT (PORT TRAF SIG)
|
MO
|
10.000
|
$4,036.000
|
$5,000.000
|
$2,900.000
|
$8,240.000
|
|
|
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
|
LF
|
300.000
|
$30.000
|
$70.000
|
$90.000
|
$96.000
|
|
|
PORT CTB (MOVE)(SGL SLP)(TY 1)
|
LF
|
720.000
|
$4.500
|
$3.000
|
$5.600
|
$24.000
|
|
|
PORT CTB (REMOVE)(SGL SLP)(TY 1)
|
LF
|
270.000
|
$7.000
|
$14.000
|
$29.000
|
$154.000
|
|
|
0512-XXXX PTB (SSCB)(STRUCTURAL)
|
LF
|
215.000
|
$200.000
|
$60.000
|
$105.000
|
$175.000
|
|
|
DRIVEWAYS (BASE)
|
SY
|
960.000
|
$22.000
|
$50.000
|
$25.000
|
$32.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
700.000
|
$21.270
|
$22.750
|
$22.750
|
$24.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
8.000
|
$1,892.700
|
$1,621.000
|
$1,430.000
|
$1,980.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
375.000
|
$2.500
|
$3.000
|
$2.580
|
$2.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
8.000
|
$2,700.000
|
$2,520.000
|
$2,350.000
|
$3,300.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
2.000
|
$350.000
|
$250.000
|
$257.500
|
$220.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
4.000
|
$2,000.000
|
$2,000.000
|
$1,525.000
|
$358.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
6.000
|
$850.000
|
$1,200.000
|
$910.000
|
$622.000
|
|
|
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
|
EA
|
4.000
|
$13,289.580
|
$6,995.000
|
$8,950.000
|
$9,625.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
|
EA
|
15.000
|
$20.000
|
$26.000
|
$15.100
|
$14.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
24.000
|
$26.820
|
$45.000
|
$27.800
|
$34.000
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
540.000
|
$4.000
|
$3.000
|
$3.020
|
$3.000
|
|
|
WK ZN PAV MRK REMOV (TRAF BTN) TY W
|
LF
|
120.000
|
$1.600
|
$2.500
|
$3.020
|
$3.000
|
|
|
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
|
EA
|
4,320.000
|
$3.260
|
$3.000
|
$2.800
|
$3.000
|
|
|
WK ZN PAV MRK REMOV (W)24"(SLD)
|
LF
|
96.000
|
$8.050
|
$5.000
|
$5.800
|
$6.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
170.000
|
$0.950
|
$1.000
|
$3.350
|
$1.000
|
|
|
PAVEMENT SEALER 4"
|
LF
|
3,234.000
|
$0.200
|
$0.250
|
$0.260
|
$0.300
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
|
LF
|
2,264.000
|
$0.340
|
$0.500
|
$0.710
|
$0.750
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
|
LF
|
3,033.000
|
$0.260
|
$0.500
|
$0.710
|
$0.750
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
154.000
|
$3.100
|
$5.000
|
$10.100
|
$11.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
35,955.000
|
$0.390
|
$0.500
|
$0.360
|
$0.400
|
|
|
ELIM EXT PAV MRK & MRKS (24")
|
LF
|
96.000
|
$3.000
|
$3.000
|
$2.850
|
$3.000
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
3,234.000
|
$1.000
|
$0.010
|
$0.310
|
$0.300
|
|
|
SP MIXES SP-D SAC-A PG76-22
|
TON
|
335.000
|
$100.000
|
$125.000
|
$140.000
|
$275.000
|
|
|
TACK COAT
|
GAL
|
243.000
|
$3.370
|
$6.000
|
$11.000
|
$11.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
320.000
|
$60.000
|
$80.000
|
$154.000
|
$96.000
|
|
|
TMA (STATIONARY)
|
DAY
|
320.000
|
$200.000
|
$150.000
|
$308.000
|
$203.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
20.000
|
$200.000
|
$550.000
|
$252.000
|
$1,045.000
|
|
Totals: |
$1,813,049.738
|
$2,465,715.618
|
$2,518,841.980
|
$2,998,441.050
|