Show Job Controls
Bid Cobra

JEFFERSON VARIOUS (0920-00-149)

Items: 77

County: JEFFERSON
Length: 0.0000 MILES
Highway: VARIOUS
District: BEAUMONT
Control Number: 0920-00-149
DBE Goal: 4.0%
Project: F 2025(217)
Guaranty: $60,000.00
Time: 337 WORKING DAYS
Engineer's Estimate: $3,021,840.60
Date: 01/07/2025 (1 year ago)
Contract Number: 1253018
Type: BICYCLE AND PEDESTRIAN IMPROVEMENTS
Project ID: A00183266
Contract Type: Federal
Project Description: FY 24 DISTRICTWIDE ADA PROJECT. ALONG COLLEGE ST - FROM PINCHBACK RD TO IH 10
Mail/Deliver Bids To: N/A
DAVE COLLINS
RICHARD BRADLEY
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$3,021,840.60
$2,688,466.62
Over/Under Est: -11.03% -$333,373.98
$2,969,542.00
Over/Under Est: -1.73% -$52,298.60
Amt Left: 10.45% $281,075.38
$2,999,598.99
Over/Under Est: -0.74% -$22,241.61
Amt Left: 11.57% $311,132.37
Delta: -1.01% -$30,056.99
Over/Under Est: 18.95% $572,648.69
Amt Left: 33.7% $906,022.67
Delta: -19.83% -$594,890.30
Subcontractor Percentage Amount
COLTER CONCRETE, LLC 10.87% $292,236.32
THIRD COAST SERVICES LLC 8.63% $232,014.67
TRAFFIC SIGNS & LINES, LLC 5.72% $153,780.29
WEBER-BALKE FOUNDATION COMPANY, INC 3.13% $84,149.01
Total: 28.35% $762,180.29

Bid Items & Bid Tabulations

77 Total 0 of 77
JEFFERSON  |  VARIOUS  |  BEAUMONT  |  0920-00-149  |  01/07/2025  |  $3,021,840.60  |  F 2025(217)  |  BICYCLE AND PEDESTRIAN IMPRVS  |  337 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TI-ZACK CONCRETE, LLC
STX CIVIL
TALBERT COMPANIES LLC
RAGLE CONSTRUCTION, INC.
PREPARING ROW
STA 3.000 $3,000.000 $1,100.000 $6,000.000 $11,000.000 $95,000.000
TREE PROTECTION (INSTALL)
EA 3.000 $185.000 $1.100 $600.000 $385.000 $885.000
TREE PROTECTION (REMOVE)
EA 3.000 $25.000 $1.100 $300.000 $165.000 $375.000
REMOV CONC (PAV)
SY 234.000 $10.000 $34.100 $45.000 $25.830 $30.000
REMOV CONC (DRIVEWAYS)
SY 2,358.000 $30.000 $23.690 $21.000 $28.050 $28.000
REMOV CONC (SIDEWALK, RAMP OR SUP)
SY 358.000 $30.000 $22.290 $21.000 $38.500 $22.000
REMOV CONC (CURB OR CURB & GUTTER)
LF 1,971.000 $25.000 $12.150 $14.000 $36.890 $10.000
REMOV CONC (MISC)
SY 46.000 $30.000 $34.700 $30.000 $86.900 $55.000
RMV (2"-6") TRT/UNTRT BASE & ASPH PAV
SY 29.000 $10.000 $55.030 $14.000 $50.080 $24.000
FURN & PLACE TOPSOIL (4")
SY 212.000 $8.000 $3.760 $5.000 $9.350 $13.000
BLOCK SODDING
SY 212.000 $8.000 $11.000 $8.000 $16.500 $15.000
PRESTR CONC PIL (16 IN SQ)
LF 344.000 $160.000 $264.000 $393.000 $174.340 $245.000
DRILL SHAFT (30 IN)
LF 8.000 $325.000 $255.150 $350.000 $255.150 $183.000
CL A CONC (FLUME)
CY 0.370 $1,500.000 $2,202.220 $2,000.000 $770.000 $2,400.000
CL C CONC (ABUT)
CY 16.800 $2,000.000 $2,420.000 $1,200.000 $1,430.000 $1,500.000
CL C CONC (ABUT)(EXTEND)
CY 1.400 $5,500.000 $3,300.000 $3,000.000 $2,750.000 $5,500.000
REINF CONC SLAB (EXTEND SLAB)
SF 569.000 $50.000 $66.000 $31.000 $40.700 $100.000
RIPRAP (CONC)(5 IN)
CY 44.000 $950.000 $1,100.000 $750.000 $770.000 $725.000
STR STEEL (MISC NON-BRIDGE)
LB 115.000 $25.000 $5.500 $185.000 $35.200 $65.000
RAIL (TY PR11)
LF 157.200 $200.000 $161.700 $210.000 $161.700 $150.000
RAIL (HANDRAIL)(TY B)
LF 160.000 $200.000 $143.000 $210.000 $143.000 $150.000
RAIL (HANDRAIL)(TY F)
LF 76.000 $200.000 $176.000 $210.000 $176.000 $225.000
GRATE
EA 8.000 $5,000.000 $2,202.220 $5,000.000 $2,750.000 $2,600.000
ADJUSTING MANHOLES
EA 43.000 $2,000.000 $185.580 $2,200.000 $2,420.000 $1,200.000
ADJUSTING INLETS
EA 1.000 $1,400.000 $7,980.000 $3,500.000 $1,872.940 $1,275.000
REMOV STR (BRIDGE SLAB)
EA 1.000 $45,000.000 $99,000.000 $25,000.000 $44,000.000 $400,000.000
REMOVE STR (RAIL)
LF 110.000 $300.000 $110.000 $50.000 $44.000 $75.000
MOBILIZATION
LS 1.000 $298,437.600 $285,610.070 $270,000.000 $427,346.000 $350,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 23.000 $5,000.000 $2,200.000 $5,000.000 $11,000.000 $7,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 337.000 $170.000 $1.100 $100.000 $148.500 $50.000
TMA (STATIONARY)
DAY 337.000 $300.000 $1.100 $190.000 $361.050 $50.000
TEMP SDMT CONT FENCE (INLET PROTECTION)
LF 167.000 $11.000 $1.100 $11.000 $12.100 $5.000
CONC CURB (TY II)
LF 596.000 $47.000 $49.640 $35.000 $54.320 $17.000
CONC CURB (TY F1)
LF 119.000 $150.000 $163.800 $325.000 $104.500 $210.000
DRIVEWAYS (CONC)
SY 2,358.000 $200.000 $122.460 $165.000 $121.000 $150.000
CONC SIDEWALKS (4")
SY 5,236.000 $110.000 $111.030 $110.000 $104.500 $62.000
CURB RAMPS (TY 1)
EA 9.000 $2,500.000 $2,003.070 $3,500.000 $2,970.000 $2,100.000
CURB RAMPS (TY 2)
EA 1.000 $2,600.000 $2,003.070 $3,500.000 $3,190.000 $2,500.000
CURB RAMPS (TY 5)
EA 5.000 $3,400.000 $2,003.070 $3,500.000 $2,970.000 $2,300.000
CURB RAMPS (TY 6)
EA 8.000 $3,000.000 $2,003.070 $3,500.000 $2,970.000 $1,650.000
CURB RAMPS (TY 7)
EA 25.000 $2,900.000 $2,003.070 $3,500.000 $3,300.000 $2,500.000
CURB RAMPS (TY 10)
EA 1.000 $2,700.000 $2,003.070 $3,500.000 $3,630.000 $3,050.000
CONC SIDEWALKS (SPECIAL)
SY 13.000 $500.000 $539.420 $350.000 $275.000 $3,500.000
RELOCATE EXISTING MAILBOX
EA 1.000 $500.000 $357.500 $350.000 $357.500 $325.000
RELOCATE RD IL ASM (TRANS-BASE)
EA 1.000 $4,000.000 $4,344.150 $5,141.000 $4,344.150 $2,617.000
CONDT (PVC) (SCH 40) (2")
LF 10.000 $26.000 $45.820 $55.000 $45.820 $13.850
CONDT (PVC) (SCH 80) (3")
LF 155.000 $20.000 $36.230 $43.000 $36.230 $22.650
ELEC CONDR (NO.8) BARE
LF 155.000 $2.000 $1.550 $2.000 $1.550 $2.000
ELEC CONDR (NO.6) BARE
LF 10.000 $3.000 $1.720 $2.000 $1.720 $2.000
ELEC CONDR (NO.6) INSULATED
LF 80.000 $3.000 $2.010 $3.000 $2.010 $2.310
GROUND BOX TY A (122311)W/APRON
EA 1.000 $1,500.000 $3,401.170 $4,025.000 $3,401.170 $1,223.000
GROUND BOX TY D (162922)W/APRON
EA 2.000 $1,500.000 $2,755.190 $3,261.000 $2,755.190 $1,241.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 4.000 $900.000 $715.000 $800.000 $715.000 $650.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 12.000 $550.000 $517.000 $550.000 $517.000 $470.000
REMOVE SM RD SN (FOUNDATION ONLY)
EA 2.000 $130.000 $104.500 $200.000 $104.500 $1,115.820
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 13.000 $2.000 $22.000 $26.500 $22.000 $20.000
RE PM TY II (W) 4" (SLD)
LF 15.000 $2.000 $11.000 $13.500 $11.000 $10.000
RE PM TY II (W) 8" (SLD)
LF 13.000 $2.000 $22.000 $26.500 $22.000 $20.000
RE PM TY II (Y) 4" (SLD)
LF 13.000 $2.000 $11.000 $13.500 $11.000 $10.000
REFL PAV MRK TY I (W)4"(SLD)(090MIL)
LF 15.000 $6.000 $11.000 $13.500 $11.000 $10.000
REFL PAV MRK TY I (Y)4"(SLD)(090MIL)
LF 13.000 $6.000 $11.000 $13.500 $11.000 $10.000
PREFAB PM TY C (W)(24")(SLD)
LF 2,424.000 $20.000 $8.970 $11.000 $8.970 $8.150
ELIM EXT PM & MRKS (4")
LF 97.000 $1.000 $1.100 $1.500 $1.100 $1.000
ELIM EXT PM & MRKS (8")
LF 6.000 $1.000 $2.200 $3.000 $2.200 $2.000
ELIM EXT PM & MRKS (24")
LF 359.000 $7.000 $3.300 $4.000 $3.300 $3.000
PAV SURF PREP FOR MRK (4")
LF 28.000 $1.000 $1.100 $1.500 $1.100 $1.000
PAV SURF PREP FOR MRK (8")
LF 13.000 $1.000 $2.200 $3.000 $2.200 $2.000
PAV SURF PREP FOR MRK (24")
LF 2,424.000 $1.000 $1.100 $1.500 $1.100 $1.000
INSTALL HWY TRF SIG (ISOLATED)
EA 4.000 $15,000.000 $26,505.270 $31,400.000 $26,505.270 $22,783.000
PED SIG SEC (LED)(COUNTDOWN)
EA 28.000 $730.000 $1,063.020 $1,258.000 $1,063.020 $590.000
TRF SIG CBL (TY A)(14 AWG)(5 CONDR)
LF 3,965.000 $3.000 $2.880 $3.500 $2.882 $2.200
TRF SIG CBL (TY C)(14 AWG)(2 CONDR)
LF 3,845.000 $3.000 $1.400 $2.000 $1.400 $1.800
PED POLE ASSEMBLY
EA 12.000 $2,000.000 $2,268.960 $2,685.000 $2,268.960 $3,817.000
PED DETECT PUSH BUTTON (APS)
EA 28.000 $1,000.000 $1,268.380 $1,525.000 $1,268.380 $797.000
PED DETECTOR CONTROLLER UNIT
EA 4.000 $3,200.000 $4,546.010 $5,380.000 $4,546.010 $3,767.000
SHRUB PLANTING AND REMOVAL
EA 8.000 $200.000 $605.000 $500.000 $82.500 $450.000
PREFAB PED STL TRUSS BRG SPAN (155 FT)
EA 1.000 $355,000.000 $495,000.000 $327,500.000 $225,500.000 $750,000.000
Totals: $3,021,840.600 $2,688,466.621 $2,969,542.000 $2,999,598.990 $3,594,489.290