Items: 32

County: JEFFERSON
Length: N/A
Highway: SH 73
District: BEAUMONT
Control Number: 0508-04-183
DBE Goal: 0.0%
Project: STP 2024(852)HES
Guaranty: N/A
Time: 94 WORKING DAYS
Engineer's Estimate: $4,905,916.00
Date: 04/04/2024 (2 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
DAVE COLLINS
RICHARD BRADLEY
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$4,905,916.00
$4,485,762.80
Over/Under Est: -8.56% -$420,153.20
Over/Under Est: 1.42% $69,500.90
Amt Left: 10.92% $489,654.10
Over/Under Est: 1.92% $94,145.80
Amt Left: 11.47% $514,299.00
Delta: -0.50% -$24,644.90
$6,500,041.50
Over/Under Est: 32.49% $1,594,125.50
Amt Left: 44.9% $2,014,278.70
Delta: -30.00% -$1,499,979.70
Subcontractor Percentage Amount
DUSTROL, INC. 1.25% $56,072.04
TRAFFIC SIGNS & LINES, LLC 1.03% $46,203.36
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. 0.91% $40,820.44
SOUTHWEST ENVIRONMENT SERVICES LLC 0.24% $10,765.83
LONESTAR TRAFFIC SAFETY, LLC 0.16% $7,177.22
Total: 3.59% $161,038.89

Bid Items & Bid Tabulations

32 Total 0 of 32
JEFFERSON  |  SH 73  |  BEAUMONT  |  0508-04-183  |  04/04/2024  |  $4,905,916.00  |  STP 2024(852)HES  |  HAZARD ELIM & SAFETY  |  94 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RAGLE CONSTRUCTION, INC.
SCR CIVIL CONSTRUCTION, LLC
TEXAS MATERIALS GROUP, INC.
FNH CONSTRUCTION, LLC
REMOVING CONCRETE(MOW STRIP)
LF 400.000 $15.000 $20.000 $52.000 $172.000 $100.000
SUBGRADE WIDENING (ORD COMP)
STA 142.390 $500.000 $570.000 $1,268.000 $1,990.000 $2,000.000
BACKFILL (TY B)
STA 142.390 $300.000 $210.000 $90.000 $320.000 $450.000
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 19,320.000 $5.000 $0.430 $0.600 $0.600 $2.000
VEGETATIVE WATERING
MG 326.400 $15.000 $35.000 $60.000 $38.000 $100.000
CL C CONC (RAIL FOUNDATION)
CY 60.000 $500.000 $725.000 $1,440.000 $1,750.000 $2,000.000
RIPRAP (CONC)(5 IN)
CY 19.500 $400.000 $950.000 $1,900.000 $2,400.000 $550.000
MOBILIZATION
LS 1.000 $1,674,040.000 $440,000.000 $176,600.000 $485,000.000 $600,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $5,000.000 $15,000.000 $3,850.000 $2,900.000 $8,500.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 180.000 $8.000 $8.970 $11.450 $11.000 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 180.000 $1.000 $4.080 $3.450 $4.000 $9.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 330.000 $80.000 $120.000 $95.000 $140.000 $100.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 17,430.000 $12.000 $2.750 $13.000 $4.670 $30.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 330.000 $20.000 $14.000 $80.000 $25.000 $30.000
PERM CTB (SGL SLOPE) (TY 1) (42 )
LF 17,084.000 $90.000 $115.900 $130.500 $125.000 $200.000
PERM CTB (SGL SLOPE)(TY 1)(TRANSITION)
LF 350.000 $230.000 $240.000 $785.000 $900.000 $400.000
REMOVE METAL BEAM GUARD FENCE
LF 2,695.000 $4.000 $3.500 $4.000 $6.000 $5.000
REMOVE TERMINAL ANCHOR SECTION
EA 6.000 $300.000 $225.000 $258.000 $200.000 $500.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 7.000 $400.000 $250.000 $286.000 $275.000 $500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 8.000 $300.000 $470.000 $538.000 $385.000 $1,500.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 5.000 $2,000.000 $1,650.000 $3,200.000 $1,450.000 $6,500.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,000.000 $800.000 $800.000 $660.000 $3,000.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $12,000.000 $8,350.000 $8,500.000 $9,575.000 $30,000.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 218.000 $20.000 $23.000 $15.000 $28.000 $100.000
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 19,380.000 $1.500 $0.950 $2.300 $1.750 $3.000
PAVEMENT SEALER 6"
LF 19,380.000 $0.200 $0.450 $0.300 $0.250 $3.000
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 19,380.000 $0.500 $0.980 $1.150 $0.750 $1.000
D-GR HMA TY-B PG64-22 (EXEMPT)
TON 4,292.200 $160.000 $255.000 $257.000 $202.000 $130.000
TACK COAT
GAL 1,129.600 $10.000 $10.000 $6.300 $19.500 $10.000
D-GR HMA TY-C SAC-B PG70-22 (EXEMPT)
TON 1,277.800 $180.000 $265.000 $268.000 $240.000 $180.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 1.000 $15,000.000 $25,000.000 $13,000.000 $9,080.000 $25,000.000
TMA (STATIONARY)
DAY 40.000 $800.000 $450.000 $425.000 $447.500 $250.000
Totals: $4,905,916.000 $4,485,762.800 $4,975,416.900 $5,000,061.800 $6,500,041.500