Show Job Controls
Bid Cobra

JEFFERSON US 69 (0065-07-062)

Items: 198

County: JEFFERSON
Length: N/A
Highway: US 69
District: BEAUMONT
Control Number: 0065-07-062
DBE Goal: N/A
Project: NH 2019(818)
Guaranty: N/A
Time: 412 WORKING DAYS
Engineer's Estimate: $21,091,620.91
Date: 04/02/2019 (7 years ago)
Contract Number: N/A
Type: WIDEN FREEWAY FROM 4 TO 6 LANES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$21,091,620.91
$21,735,071.85
Over/Under Est: 3.05% $643,450.94
Over/Under Est: 11.43% $2,409,874.66
Amt Left: 8.13% $1,766,423.72
Over/Under Est: 18.03% $3,802,971.43
Amt Left: 14.54% $3,159,520.49
Delta: -5.93% -$1,393,096.77
Over/Under Est: 23.25% $4,903,046.28
Amt Left: 19.6% $4,259,595.34
Delta: -4.42% -$1,100,074.85
Subcontractor Percentage Amount
TEXAS MATERIALS GROUP, INC. 22.22% $5,545,842.62
JOHN REED AND COMPANY, LLC 15.71% $3,921,025.54
J & M CONTRACTING, COMPANY 4.91% $1,225,476.48
THIRD COAST SERVICES LLC 3.37% $841,111.14
INTECH CONTRACTING LLC 2.60% $648,928.48
RAGLE CONSTRUCTION, INC. 1.63% $406,828.24
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. 1.40% $349,423.03
CREATIVE PAVING CONCEPTS, LLC 1.05% $262,067.27
CRABTREE BARRICADE SYSTEMS, INC. 1.01% $252,083.76
MIK INDUSTRIAL, LLC 0.60% $149,752.73
CREACOM, INC. 0.34% $84,859.88
CEN TEX HYDROSEED, INC. 0.31% $77,372.24
FARR FOUNDATION, INC. 0.28% $69,884.61
TEXAS CUTTING & CORING GP, INC. 0.27% $67,388.73
AREA WIDE PROTECTIVE, INC. 0.19% $47,421.70
JB PINNACLE GROUP, LLC 0.15% $37,438.18
HIGHWAY 1 LLC 0.10% $24,958.79
HOUSTON SAWING & DRILLING 0.02% $4,991.76
CPAVE, INC. 0.00% $0.00
Total: 56.16% $14,016,855.18

Bid Items & Bid Tabulations

198 Total 0 of 198
JEFFERSON  |  US 69  |  BEAUMONT  |  0065-07-062  |  04/02/2019  |  $21,091,620.91  |  NH 2019(818)  |  WIDEN FREEWAY FROM 4 TO 6 LANES  |  412 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ANGEL BROTHERS HOLDINGS CORP.
JAMES CONSTRUCTION GROUP, L.L.C.
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
TEXAS MATERIALS GROUP, INC.
PREPARING ROW
STA 107.000 $3,500.000 $4,500.000 $20,961.000 $7,100.000 $17,450.000
REMOVING CONC (PAV)
SY 2,507.000 $10.000 $14.000 $9.760 $5.000 $7.250
REMOVING CONC (RIPRAP)
SY 3,096.000 $11.000 $19.000 $7.730 $6.000 $6.500
REMOVING CONC (CTB)
LF 3,550.000 $9.000 $23.010 $7.330 $15.000 $18.190
REMOVING STAB BASE & ASPH PAV (8"-14")
SY 33,137.000 $3.750 $8.000 $8.060 $5.500 $7.100
OBLITERATING ABANDONED ROAD
SY 3,025.000 $15.000 $12.000 $5.680 $9.000 $9.500
EXCAVATION (ROADWAY)
CY 28,630.000 $12.000 $19.000 $9.330 $11.000 $17.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 22,072.000 $12.000 $23.500 $21.140 $9.000 $41.000
FURNISHING AND PLACING TOPSOIL (4")
SY 64,098.000 $1.500 $2.500 $0.340 $4.500 $3.900
BLOCK SODDING
SY 5,853.000 $6.000 $5.000 $5.000 $6.000 $6.000
BROADCAST SEED (TEMP) (WARM)
SY 32,050.000 $0.250 $0.250 $0.120 $0.200 $0.130
BROADCAST SEED (TEMP) (COOL)
SY 32,050.000 $0.250 $0.250 $0.120 $0.200 $0.130
CELL FBR MLCH SEED(PERM)(URBAN)(CLAY)
SY 64,098.000 $0.500 $0.500 $0.240 $0.400 $0.290
VEGETATIVE WATERING
MG 1,621.000 $20.000 $20.000 $20.870 $25.000 $24.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 5,406.000 $1.250 $2.250 $1.190 $1.500 $1.200
PROOF ROLLING
HR 174.000 $100.000 $120.000 $71.370 $100.000 $100.000
LIME TRT (EXST MATL) (6")
SY 71,247.000 $4.000 $4.100 $2.970 $5.000 $4.500
LIME (HYD, COM, OR QK(SLURRY))
TON 961.000 $180.000 $232.000 $199.950 $220.000 $200.000
CEM TRT(PLNT MX) (CL L)(TYA)(GR1-2)(6")
SY 63,693.000 $14.000 $19.000 $20.670 $25.000 $18.000
CEM TRT(PLN MX)(CL L)(TYA)(GR1-2)(10")
SY 3,209.000 $35.000 $35.000 $37.350 $45.000 $36.000
ASPHALT STAB BASE (GR 2)(PG 64)
TON 14,936.000 $77.000 $83.000 $99.150 $70.000 $87.000
PRIME COAT(MC-30 OR AE-P)
GAL 16,727.000 $4.000 $4.000 $5.310 $4.000 $4.600
D-GR HMA(SQ) TY-C PG70-22
TON 518.000 $70.000 $84.000 $200.670 $120.000 $150.000
D-GR HMA TY-D PG 70-22 (LEVEL-UP)
TON 8,460.000 $110.000 $72.000 $113.320 $102.000 $100.000
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 12,093.000 $130.000 $125.000 $177.060 $125.000 $120.000
PLANE ASPH CONC PAV (3 1/2")
SY 63,952.000 $3.000 $3.400 $2.290 $2.000 $2.300
CONC PVMT (CONT REINF - CRCP) (10")
SY 2,506.000 $100.000 $81.000 $60.120 $65.000 $80.000
FULL - DEPTH REPAIR CPJR (15")
SY 2.000 $500.000 $4,300.000 $525.760 $125.000 $3,400.000
CEM STABIL BKFL
CY 2,018.000 $80.000 $110.000 $76.940 $110.000 $76.000
CUT & RESTORING PAV
SY 80.000 $100.000 $155.000 $100.310 $125.000 $400.000
TRENCH EXCAVATION PROTECTION
LF 2,862.000 $5.000 $15.000 $5.400 $1.500 $23.500
DRILL SHAFT (18 IN)
LF 468.000 $65.000 $98.500 $73.470 $85.000 $105.000
DRILL SHAFT (36 IN)
LF 1,196.000 $180.000 $240.000 $256.890 $225.000 $276.000
DRILL SHAFT (42 IN)
LF 34.000 $235.000 $1,100.000 $447.450 $250.000 $760.000
DRILL SHAFT (48 IN)
LF 2,536.000 $550.000 $420.000 $454.610 $450.000 $480.000
DRILL SHAFT (SIGN MTS) (24 IN)
LF 76.000 $220.000 $450.000 $200.000 $225.000 $180.000
DRILL SHAFT (SIGN MTS) (48 IN)
LF 175.000 $500.000 $1,126.000 $763.000 $775.000 $450.000
DRILL SHAFT (SIGN MTS) (54 IN)
LF 120.000 $500.000 $1,225.000 $872.000 $1,000.000 $550.000
CL C CONC (ABUT)(HPC)(EXTEND)
CY 104.400 $1,100.000 $1,700.000 $1,262.080 $1,200.000 $2,667.000
CL C CONC (CAP)(HPC)(EXTEND)
CY 266.600 $2,600.000 $1,600.000 $1,581.160 $1,400.000 $1,870.000
CL C CONC (COLUMN)(HPC)
CY 154.700 $1,000.000 $1,300.000 $713.610 $1,600.000 $1,560.000
CL C CONC (RAIL FOUNDATION)
CY 199.000 $400.000 $510.000 $813.320 $400.000 $654.000
REINF CONC SLAB (EXTEND SLAB)(HPC)
SF 44,221.000 $30.000 $18.500 $26.060 $40.000 $33.000
APPROACH SLAB (EXTEND) (HPC)
CY 155.300 $535.000 $740.000 $512.040 $600.000 $750.000
RETAINING WALL (CONC BLOCK)
SF 13,737.000 $60.000 $28.000 $28.620 $45.000 $41.000
PRESTR CONC GIRDER (TX28)
LF 4,182.420 $147.000 $175.000 $124.790 $175.000 $167.000
PRESTR CONC GIRDER (TX40)
LF 1,293.840 $130.000 $195.000 $173.150 $185.000 $170.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 1,452.000 $10.000 $45.000 $3.730 $40.000 $14.400
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 35.000 $970.000 $180.000 $253.710 $165.000 $151.000
CONC STR REPAIR (STANDARD)
SF 420.000 $211.000 $60.000 $169.000 $65.000 $49.000
RIPRAP (CONC)(4 IN)
CY 116.800 $400.000 $560.000 $328.770 $500.000 $550.000
RIPRAP (CONC)(5 IN)
CY 105.000 $500.000 $615.000 $375.280 $500.000 $550.000
RIPRAP (CONC)(6 IN)
CY 41.000 $445.000 $545.000 $375.300 $500.000 $550.000
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 326.000 $460.000 $620.000 $284.890 $500.000 $680.000
RIPRAP (CONC)(FLUME)
CY 116.000 $440.000 $615.000 $592.050 $500.000 $550.000
RIPRAP (MOW STRIP)(4 IN)
CY 174.000 $445.000 $700.000 $592.050 $500.000 $580.000
CLEANING AND SEALING EXIST JOINTS(CL3)
LF 726.000 $25.000 $8.500 $17.860 $8.000 $6.750
CLEANING AND SEALING EXIST JOINTS(CL7)
LF 152.000 $20.000 $56.000 $25.310 $60.000 $47.000
CLEANING AND SEALING JOINTS (CL 3)
LF 302.000 $30.000 $10.500 $18.840 $10.000 $8.600
CLEAN & PAINT EXIST STR (SYSTEM II)
LS 1.000 $450,000.000 $400,000.000 $827,000.000 $900,000.000 $1,000,000.000
SPOT CLEAN & PAINT EXT STR(SPL PRT SYS)
LS 1.000 $20,000.000 $225,000.000 $162,577.000 $200,000.000 $250,000.000
RAIL (TY SSTR)(HPC)
LF 1,880.400 $42.000 $88.500 $52.000 $80.000 $52.000
RAIL (TY SSTR) (W/DRAIN SLOTS)
LF 1,419.000 $60.000 $92.000 $44.470 $70.000 $56.000
SEALED EXPANSION JOINT (5 IN) (SEJ - A)
LF 110.000 $100.000 $86.000 $136.300 $200.000 $210.000
HEADER TYPE EXPANSION JOINT
LF 542.000 $160.000 $151.000 $150.940 $100.000 $80.000
CONC BOX CULV (4 FT X 2 FT)
LF 131.000 $200.000 $400.000 $236.460 $600.000 $440.000
RC PIPE (CL III)(18 IN)
LF 525.000 $60.000 $59.000 $50.990 $125.000 $106.000
RC PIPE (CL III)(24 IN)
LF 1,447.000 $70.000 $120.000 $59.140 $135.000 $117.000
RC PIPE (CL III)(30 IN)
LF 1,160.000 $90.000 $155.000 $73.410 $195.000 $200.000
MANH (COMPL)(PRM)(48IN)
EA 1.000 $3,850.000 $3,200.000 $7,739.810 $10,000.000 $4,800.000
INLET (COMPL)(PCO)(5FT)(RIGHT)
EA 2.000 $4,675.000 $6,100.000 $3,405.000 $10,000.000 $6,720.000
INLET(COMPL)(PSL)(SFG)(3FTX5FT-3FTX5FT)
EA 49.000 $5,200.000 $5,600.000 $3,618.740 $10,000.000 $4,075.000
SET (TY I)(S= 4 FT)(HW= 2 FT)(4:1) (C)
EA 4.000 $6,600.000 $4,800.000 $3,707.990 $10,000.000 $5,400.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 10.000 $1,000.000 $990.000 $1,734.660 $2,000.000 $1,220.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 4.000 $800.000 $1,050.000 $1,825.600 $4,000.000 $1,270.000
ADJUSTING INLET (CAP)
EA 2.000 $2,000.000 $2,500.000 $966.510 $2,000.000 $1,160.000
REMOV STR (SET)
EA 4.000 $500.000 $680.000 $740.210 $2,500.000 $840.000
REMOV STR (PIPE)
LF 3,636.000 $150.000 $32.000 $7.360 $65.000 $14.500
REMOVE STR (RAIL)
LF 150.000 $16.000 $27.000 $4.000 $35.000 $2.800
MOBILIZATION
LS 1.000 $1,760,000.000 $1,519,000.000 $2,300,000.000 $2,250,000.000 $2,550,500.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 28.000 $6,500.000 $930.000 $18,195.260 $15,000.000 $8,000.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 156.000 $35.000 $30.750 $39.500 $40.000 $41.000
CONSTRUCTION EXITS (REMOVE)
SY 156.000 $10.000 $12.400 $9.000 $15.000 $9.300
BACKHOE WORK (EROSION & SEDMT CONT)
HR 128.000 $140.000 $171.000 $118.640 $175.000 $185.000
BULLDOZER WORK (EROSION & SEDMT CONT)
HR 128.000 $140.000 $194.000 $97.560 $250.000 $140.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,763.000 $5.000 $4.500 $3.000 $4.000 $3.100
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,763.000 $2.000 $2.000 $1.000 $2.000 $1.200
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 830.000 $5.000 $8.750 $5.500 $6.000 $5.700
BIODEG EROSN CONT LOGS (REMOVE)
LF 830.000 $2.000 $2.500 $1.000 $1.500 $1.200
CONSTRUCTING DETOURS (TY 1)
SY 2,615.000 $80.000 $79.000 $109.470 $90.000 $112.000
CONSTRUCTING DETOURS (TY 2)
SY 4,628.000 $65.000 $25.000 $25.770 $100.000 $33.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 10,530.000 $40.000 $61.000 $46.460 $65.000 $73.000
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 1,680.000 $40.000 $66.000 $48.160 $50.000 $84.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 80.000 $40.000 $82.750 $45.990 $55.000 $104.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 28,010.000 $10.000 $12.000 $5.710 $10.000 $8.850
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 820.000 $10.000 $14.000 $9.330 $15.000 $26.850
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 80.000 $10.000 $21.000 $11.680 $35.000 $54.800
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 9,780.000 $10.000 $12.500 $6.940 $12.000 $10.800
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 1,680.000 $10.000 $14.000 $5.760 $21.000 $9.250
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 80.000 $10.000 $21.000 $5.760 $17.000 $32.700
PERM CTB (SGL SLOPE) (TY 1) (42 )
LF 3,490.000 $55.000 $79.000 $43.190 $75.000 $73.250
PERM CTB (TRAN SSCB TO CTB) (MOD)
LF 30.000 $300.000 $75.000 $113.270 $350.000 $452.000
CONC CURB (TY I)
LF 2,649.000 $20.000 $24.000 $3.970 $15.000 $26.850
CONC CURB (TY II)
LF 5,964.000 $20.000 $24.000 $3.970 $15.000 $20.200
DRIVEWAYS (ACP)
SY 173.000 $50.000 $34.000 $94.460 $80.000 $48.500
DRIVEWAYS (CONC) (FAST TRACK)
SY 24.000 $100.000 $185.000 $150.530 $150.000 $270.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 18,536.000 $0.200 $0.600 $0.480 $0.400 $0.360
MTL W-BEAM GD FEN (TIM POST)
LF 3,600.000 $22.000 $27.000 $19.500 $24.000 $20.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 6.000 $2,000.000 $1,700.000 $1,380.000 $2,000.000 $1,435.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 6.000 $1,300.000 $1,200.000 $1,030.000 $1,100.000 $1,070.000
REMOVE METAL BEAM GUARD FENCE
LF 1,150.000 $4.000 $2.500 $4.000 $3.000 $4.150
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $430.000 $185.000 $250.000 $225.000 $255.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 3.000 $255.000 $185.000 $250.000 $130.000 $255.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 6.000 $443.000 $370.000 $250.000 $250.000 $255.000
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $2,500.000 $3,400.000 $2,350.000 $3,200.000 $2,400.000
GUARDRAIL END TREATMENT (REMOVE)
EA 3.000 $610.000 $308.000 $250.000 $300.000 $255.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 8.000 $3,000.000 $1,850.000 $2,000.000 $3,000.000 $2,020.000
CRASH CUSH ATTEN (REMOVE)
EA 5.000 $1,790.000 $1,500.000 $900.000 $1,500.000 $910.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 7.000 $13,290.000 $40,000.000 $21,000.000 $25,000.000 $21,200.000
CRASH CUSH ATTEN (INSTL)(L)(W)(TL3)
EA 1.000 $36,500.000 $64,000.000 $34,000.000 $38,000.000 $34,200.000
REMOVE RD IL ASM (TRANS-BASE)
EA 36.000 $514.000 $310.000 $475.000 $600.000 $510.000
REMOVE RD IL ASM (U/P)
EA 14.000 $177.000 $310.000 $790.000 $1,000.000 $170.000
IN RD IL (U/P) (TY 2) (150W EQ) LED
EA 10.000 $16.000 $2,800.000 $1,640.000 $2,000.000 $1,150.000
CONDT (PVC) (SCH 40) (2")
LF 1,030.000 $7.250 $9.500 $16.900 $21.000 $8.300
CONDT (PVC) (SCH 80) (2") (BORE)
LF 162.000 $20.000 $21.000 $52.200 $65.000 $21.000
CONDT (PVC) (SCH 80) (3")
LF 150.000 $13.450 $11.000 $21.000 $26.000 $10.250
CONDT (PVC) (SCH 80) (3") (BORE)
LF 270.000 $25.000 $23.000 $34.100 $42.000 $30.000
CONDT (RM) (3/4")
LF 396.000 $23.500 $18.000 $68.900 $85.000 $30.000
CONDT (RM) (1 1/2")
LF 120.000 $20.000 $21.000 $40.100 $50.000 $31.000
ELEC CONDR (NO.10) BARE
LF 496.000 $3.400 $2.000 $1.850 $3.000 $4.150
ELEC CONDR (NO.10) INSULATED
LF 992.000 $4.000 $2.000 $1.850 $3.000 $1.800
ELEC CONDR (NO.8) BARE
LF 1,479.000 $1.500 $2.250 $1.900 $3.000 $1.800
ELEC CONDR (NO.8) INSULATED
LF 3,042.000 $1.500 $2.250 $2.000 $3.000 $1.800
ELEC CONDR (NO.6) BARE
LF 420.000 $1.500 $2.250 $2.050 $3.000 $150.000
ELEC CONDR (NO.6) INSULATED
LF 840.000 $1.500 $2.500 $2.200 $3.000 $135.000
GROUND BOX TY A (122311)W/APRON
EA 15.000 $1,000.000 $2,100.000 $1,950.000 $2,500.000 $1,200.000
ELC SRV TY A 240/480 060(NS)SS(T)TP(O)
EA 3.000 $6,500.000 $7,000.000 $8,160.000 $10,000.000 $9,000.000
ELC SRV TY D 120/240 060(NS)GS(N)GC(O)
EA 2.000 $7,500.000 $7,200.000 $8,465.000 $12,000.000 $9,000.000
ALUMINUM SIGNS (TY G)
SF 294.000 $28.000 $31.000 $27.090 $37.000 $31.200
ALUMINUM SIGNS (TY O)
SF 945.000 $25.000 $30.000 $22.480 $39.000 $66.000
REPLACE EXISTING ALUMINUM SIGNS(TY O)
SF 156.000 $25.000 $38.000 $30.000 $51.000 $57.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 23.000 $500.000 $495.000 $455.000 $1,000.000 $410.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 21.000 $600.000 $710.000 $656.000 $1,250.000 $625.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 15.000 $710.000 $860.000 $857.000 $1,250.000 $815.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 8.000 $765.000 $990.000 $818.000 $1,300.000 $795.000
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
EA 6.000 $2,180.000 $3,000.000 $285.000 $4,500.000 $1,884.000
REMOVE SM RD SN SUP&AM
EA 49.000 $80.000 $155.000 $150.000 $100.000 $67.000
INSTALL LRSS (STRUCT STEEL)
LB 3,402.000 $7.000 $11.000 $6.770 $100.000 $7.200
REMOVE LRSA
EA 7.000 $9,000.000 $2,500.000 $1,000.000 $0.600 $830.000
INS OH SN SUP(30 FT CANT)
EA 6.000 $29,000.000 $32,000.000 $22,930.000 $1.500 $34,800.000
INS OH SN SUP(40 FT CANT)
EA 3.000 $32,000.000 $38,000.000 $28,855.000 $1.500 $37,200.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND
EA 24.000 $45.000 $52.000 $25.000 $2.250 $90.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 8.000 $23.000 $12.500 $25.000 $2.000 $46.500
INSTL DEL ASSM (D-SY)SZ 1(FLX)GND
EA 6.000 $33.000 $50.000 $50.000 $1.500 $15.500
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI)
EA 36.000 $18.000 $9.500 $17.500 $7.000 $46.500
INSTL DEL ASSM (D-DW)SZ 1(FLX)GND
EA 34.000 $76.000 $62.000 $45.000 $0.600 $15.500
INSTL DEL ASSM (D-DY)SZ 1(FLX)GND
EA 26.000 $90.000 $50.000 $45.000 $0.600 $46.500
INSTL DEL ASSM (D-DW)SZ 1(BRF)GF2
EA 80.000 $24.000 $37.000 $20.000 $0.600 $21.500
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 5,210.000 $0.500 $1.500 $0.300 $1.000 $0.360
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 20,080.000 $0.300 $0.750 $0.300 $1.500 $0.360
WK ZN PAV MRK NON-REMOV (W)(ENTR GORE)
EA 3.000 $400.000 $493.000 $365.000 $500.000 $375.000
WK ZN PAV MRK NON-REMOV (W)(EXIT GORE)
EA 3.000 $400.000 $493.000 $325.000 $500.000 $335.000
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 20,660.000 $0.300 $0.450 $0.300 $2.000 $0.360
WK ZN PAV MRK NON-REMOV (Y)6"(DOT)
LF 8,529.000 $1.000 $0.450 $0.100 $3.000 $0.120
WK ZN PAV MRK REMOV (W)4"(BRK)
LF 19,360.000 $1.000 $1.250 $0.460 $1.000 $0.550
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 73,995.000 $1.000 $0.950 $0.460 $1.000 $0.550
WK ZN PAV MRK REMOV (W)8"(SLD)
LF 1,090.000 $1.500 $1.250 $1.000 $2.000 $1.200
WK ZN PAV MRK REMOV (W)12"(LNDP)
LF 426.000 $3.500 $6.200 $2.500 $7.000 $2.550
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 72,690.000 $1.000 $0.950 $0.460 $1.000 $0.470
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 11,900.000 $1.500 $1.000 $1.750 $1.000 $2.150
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,400.000 $1.100 $1.000 $1.600 $1.000 $2.150
REFL PAV MRK TY I (W)12"(LNDP)(100MIL)
LF 1,584.000 $3.000 $3.100 $1.750 $7.000 $1.800
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 3,000.000 $2.500 $3.000 $1.600 $7.000 $1.650
REFL PAV MRK TY I (Y)8"(SLD)(100MIL)
LF 2,222.000 $1.000 $1.900 $0.950 $3.000 $0.960
REFL PAV MRK TY I (Y)12"(SLD)(100MIL)
LF 1,128.000 $3.000 $4.950 $5.000 $7.000 $6.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 12,790.000 $0.500 $0.500 $0.450 $1.000 $0.540
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 31,675.000 $0.500 $0.500 $0.450 $1.000 $0.540
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 32,243.000 $0.500 $0.500 $0.450 $1.000 $0.540
PREFAB PAV MRK TY C (W) (ARROW)
EA 8.000 $218.390 $430.000 $350.000 $500.000 $360.000
PREFAB PAV MRK TY C (W) (U-ST ARROW)
EA 6.000 $550.000 $430.000 $200.000 $500.000 $240.000
PREFAB PAV MRK TY C (W) (LNDP ARROW)
EA 11.000 $630.000 $500.000 $200.000 $500.000 $240.000
PREFAB PAV MRK TY C (W) (WORD)
EA 8.000 $300.000 $370.000 $400.000 $500.000 $415.000
REFL PAV MRKR TY II-A-A
EA 226.000 $4.250 $4.300 $3.000 $4.000 $3.100
REFL PAV MRKR TY II-C-R
EA 2,265.000 $4.000 $5.000 $3.000 $4.000 $3.100
ELIM EXT PAV MRK & MRKS (4")
LF 56,305.000 $0.500 $1.000 $0.400 $1.000 $0.410
ELIM EXT PAV MRK & MRKS (8")
LF 3,540.000 $0.600 $1.600 $0.800 $1.000 $0.820
ELIM EXT PAV MRK & MRKS (24")
LF 357.000 $4.500 $5.000 $200.000 $3.000 $2.050
CONC CRCK REPR(DISCRETE)(ROUT AND SEAL)
LF 1,110.000 $26.000 $24.000 $25.820 $25.000 $19.750
BRIDGE JOINT REPLACEMENT (SEJ)
LF 152.000 $430.000 $560.000 $203.080 $700.000 $540.000
CARBON FIBER REINF POLYMER PROTECTION
SF 1,119.100 $47.000 $68.000 $48.380 $0.400 $57.000
REPLACE ELASTOMERIC BEARING PADS
EA 20.000 $5,000.000 $11,500.000 $2,365.600 $0.400 $5,840.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $11,000.000 $9,300.000 $10,807.920 $20,000.000 $13,000.000
CCTV FIELD EQUIPMENT (DIGITAL)
EA 2.000 $10,000.000 $13,500.000 $8,935.000 $12,000.000 $18,000.000
ITS POLE (40 FT)(90 MPH)
EA 2.000 $8,300.000 $13,000.000 $10,175.000 $15,000.000 $10,800.000
ITS POLE MNT CAB (TY 1)(CONF 1)
EA 2.000 $39,500.000 $6,300.000 $4,910.000 $7,500.000 $9,600.000
TMA (STATIONARY)
EA 4.000 $12,465.000 $10,500.000 $10,807.920 $20,000.000 $20,900.000
TMA (MOBILE OPERATION)
DAY 72.000 $500.000 $190.000 $728.650 $500.000 $205.000
ITS GND BOX(PCAST) TY 1 (243660)W/APRN
EA 4.000 $4,000.000 $5,700.000 $4,435.000 $5,500.000 $4,800.000
Totals: $21,091,620.910 $21,735,071.850 $23,501,495.609 $24,894,592.340 $25,994,667.190