Show Job Controls
Bid Cobra

JEFFERSON US 90 (0028-06-078)

Items: 47

County: JEFFERSON
Length: N/A
Highway: US 90
District: BEAUMONT
Control Number: 0028-06-078
DBE Goal: N/A
Project: STP 1702(502)HES
Guaranty: N/A
Time: 60 WORKING DAYS
Engineer's Estimate: $1,337,568.50
Date: 07/12/2017 (8 years ago)
Contract Number: N/A
Type: GR, BS,STR,PVMT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$1,337,568.50
$1,139,171.29
Over/Under Est: -14.83% -$198,397.21
$1,282,735.51
Over/Under Est: -4.1% -$54,832.99
Amt Left: 12.6% $143,564.22
Over/Under Est: 28.79% $385,066.80
Amt Left: 51.22% $583,464.01
Delta: -34.29% -$439,899.79
$1,954,217.00
Over/Under Est: 46.1% $616,648.50
Amt Left: 71.55% $815,045.71
Delta: -13.44% -$231,581.70

Bid Items & Bid Tabulations

47 Total 0 of 47
JEFFERSON  |  US 90  |  BEAUMONT  |  0028-06-078  |  07/12/2017  |  $1,337,568.50  |  STP 1702(502)HES  |  GR, BS,STR,PVMT  |  60 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
OLDCASTLE MATERIALS TEXAS, INC.
A. L. HELMCAMP, INC.
ANGEL BROTHERS HOLDINGS CORP.
FNH CONSTRUCTION, LLC
REMOVING CONC (RIPRAP)
SY 301.000 $7.000 $17.500 $18.000 $50.000 $20.000
SUBGRADE WIDENING (ORD COMP)
STA 208.230 $500.000 $405.000 $220.000 $400.000 $450.000
BACKFILL (TY A OR B)
STA 208.230 $150.000 $60.000 $180.000 $200.000 $350.000
BROADCAST SEED (TEMP) (WARM)
SY 10,952.000 $0.250 $0.120 $0.180 $0.250 $0.500
BROADCAST SEED (TEMP) (COOL)
SY 10,952.000 $0.250 $0.120 $0.180 $0.250 $0.500
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 21,904.000 $0.500 $0.260 $0.300 $0.500 $0.500
VEGETATIVE WATERING
MG 185.000 $20.000 $20.000 $20.000 $35.000 $50.000
FL BS (CMP IN PLACE) (TY D GR 1-2)(10")
SY 18,252.000 $20.000 $19.000 $24.000 $43.000 $27.500
PRIME COAT (RC-250)
GAL 3,651.000 $3.000 $4.200 $5.000 $4.000 $8.000
AGGR (TY-PD GR-4 OR TY-PL GR-4)(SAC-B)
CY 685.000 $150.000 $145.000 $120.000 $125.000 $285.000
ASPH (AC-20-5TR OR AC-20XP)
GAL 27,113.000 $4.000 $2.900 $3.500 $3.200 $6.000
AGGR (TY-PD GR-5 OR TY-PL GR-5)
CY 141.000 $4.000 $240.000 $180.000 $200.000 $30.000
D-GR HMA(SQ) TY-D SAC-B PG64-22
TON 1,219.000 $120.000 $80.000 $120.000 $120.000 $120.000
RIPRAP (MOW STRIP)(4 IN)
CY 33.000 $400.000 $460.000 $850.000 $500.000 $550.000
RETROFIT RAIL (TY T131RC)
LF 237.000 $200.000 $130.000 $150.000 $170.000 $185.000
MOBILIZATION
LS 1.000 $120,000.000 $35,000.000 $104,000.000 $145,000.000 $180,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $4,000.000 $1,500.000 $8,000.000 $5,000.000 $8,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 340.000 $30.000 $30.000 $40.000 $45.000 $30.000
ROCK FILTER DAMS (REMOVE)
LF 340.000 $10.000 $8.200 $7.000 $16.000 $15.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 290.000 $5.000 $5.100 $7.000 $10.000 $16.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 290.000 $1.000 $1.000 $1.000 $2.250 $8.000
TURNOUTS (SURF TREAT)
SY 5,590.000 $20.000 $25.000 $4.000 $6.000 $35.000
RUMBLE STRIPS (SHOULDER)
LF 31,253.000 $0.200 $0.300 $0.220 $0.400 $0.500
MTL W-BEAM GD FEN (TIM POST)
LF 450.000 $20.000 $18.500 $19.000 $22.000 $25.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 2.000 $2,000.000 $1,360.000 $1,500.000 $1,650.000 $1,850.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,000.000 $980.000 $1,000.000 $1,200.000 $1,850.000
MTL BM GD FEN TRANS (NON - SYM)
EA 2.000 $800.000 $660.000 $700.000 $850.000 $1,850.000
REMOVE METAL BEAM GUARD FENCE
LF 550.000 $4.000 $4.100 $5.000 $3.200 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $400.000 $350.000 $350.000 $160.000 $500.000
RM MTL BM GD FEN TRANS (T101)
EA 2.000 $150.000 $400.000 $270.000 $8.000 $2,500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $2,000.000 $2,100.000 $2,200.000 $2,500.000 $2,850.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $600.000 $350.000 $600.000 $320.000 $1,500.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 2.000 $50.000 $48.000 $50.000 $55.000 $100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 8.000 $25.000 $15.200 $18.000 $33.000 $100.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 570.000 $1.500 $1.050 $0.600 $1.000 $5.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 2,125.000 $0.800 $0.680 $0.700 $0.700 $2.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 5,700.000 $0.400 $0.350 $0.360 $0.350 $2.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 21,047.000 $0.400 $0.320 $0.330 $0.300 $0.500
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 20,244.000 $0.400 $0.320 $0.330 $0.350 $0.500
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 90.000 $60.000 $4.100 $4.500 $5.000 $20.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 21.000 $200.000 $205.000 $210.000 $250.000 $150.000
REFL PAV MRKR TY I-C
EA 303.000 $3.000 $3.300 $3.500 $4.000 $15.000
REFL PAV MRKR TY II-C-R
EA 224.000 $4.000 $3.300 $3.500 $4.000 $15.000
ELIM EXT PV MRK & MRKS (RUMBLE STRIP)
LF 160.000 $2.000 $2.050 $2.200 $2.000 $5.000
RELOCT RDSD FLSH BCN AM (SOLAR PWRD)
EA 1.000 $5,000.000 $2,000.000 $5,000.000 $3,500.000 $10,000.000
JT / CRCK ROUT / SEAL(RUBBER - ASPHALT)
LF 32,852.000 $1.500 $1.600 $2.200 $2.000 $3.000
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
LF 160.000 $20.000 $6.200 $6.500 $7.000 $2.000
Totals: $1,337,568.500 $1,139,171.290 $1,282,735.510 $1,722,635.300 $1,954,217.000