JASPER US0096 (6481-29-001)

Items: 6

County: JASPER
Length: 0.0100 MILES
Highway: US0096
District: BEAUMONT
Control Number: 6481-29-001
DBE Goal: N/A
Project: RMC - A00214364
Guaranty: $3,000.00
Time: 26 WORKING DAYS
Engineer's Estimate: $167,915.00
Date: 06/17/2025 (11 months ago)
Contract Number: 6252001
Type: FULL DEPTH CONCRETE REPAIR
Project ID: A00214364
Project Description: REPAIR CONCRETE PAVEMENT AND TRAFFIC RAIL
Mail/Deliver Bids To: N/A
JIM GRISSOM
BRYCE BROUSSARD
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$167,915.00
$150,459.00
Over/Under Est: -10.4% -$17,456.00
Over/Under Est: 13.51% $22,687.00
Amt Left: 26.68% $40,143.00
Over/Under Est: 57.94% $97,285.00
Amt Left: 76.26% $114,741.00
Delta: -39.14% -$74,598.00
Over/Under Est: 63.71% $106,985.00
Amt Left: 82.71% $124,441.00
Delta: -3.66% -$9,700.00
Over/Under Est: 115.32% $193,643.00
Amt Left: 140.3% $211,099.00
Delta: -31.52% -$86,658.00
Over/Under Est: 154.86% $260,035.00
Amt Left: 184.43% $277,491.00
Delta: -18.36% -$66,392.00

Bid Items & Bid Tabulations

6 Total 0 of 6
JASPER  |  US0096  |  BEAUMONT  |  6481-29-001  |  06/17/2025  |  $167,915.00  |  RMC - A00214364  |  FULL DEPTH CONC REPAIR  |  26 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CROSS PLUS CONSTRUCTION, LLC
AUSTIN BARRICADE COMPANY, L.L.C.
GARRET SHIELDS INFRASTRUCTURE
WINDING ROAD CONSTRUCTION, INC.
ISI CONTRACTING, INC.
O. TREVINO CONSTRUCTION, LLC
FULL - DEPTH REPAIR CRCP (12")
CY 83.000 $750.000 $699.000 $750.000 $1,200.000 $1,300.000 $850.000 $1,800.000
FULL - DEPTH REPAIR CRCP (15")
CY 58.000 $800.000 $802.000 $750.000 $1,400.000 $1,300.000 $900.000 $2,300.000
MOBILIZATION
LS 1.000 $15,265.000 $15,000.000 $18,000.000 $10,000.000 $20,000.000 $30,000.000 $42,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $7,500.000 $6,000.000 $1.000 $5,000.000 $15,000.000 $5,500.000 $12,000.000
TMA (STATIONARY)
DAY 26.000 $700.000 $1.000 $2,000.000 $400.000 $250.000 $7,500.000 $500.000
CONCRETE RAIL REPAIR (IN-KIND)
LF 54.000 $200.000 $350.000 $275.000 $1,000.000 $650.000 $52.000 $1,225.000
Totals: $167,915.000 $150,459.000 $190,602.000 $265,200.000 $274,900.000 $361,558.000 $427,950.000