JASPER US0096 (6477-58-001)

Items: 18

County: JASPER
Length: 0.0100 MILES
Highway: US0096
District: BEAUMONT
Control Number: 6477-58-001
DBE Goal: N/A
Project: BPM - A00213069
Guaranty: $23,000.00
Time: 30 WORKING DAYS
Engineer's Estimate: $1,140,338.53
Date: 07/01/2025 (11 months ago)
Contract Number: 7254017
Type: BRIDGE PREVENTATIVE MAINTENANCE
Project ID: A00213069
Project Description: MISCELLANEOUS BRIDGE REPAIRS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
BRYCE BROUSSARD
JIM GRISSOM
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (11)
E
Engineer's Estimate
$1,140,338.53
$594,805.82
Over/Under Est: -47.84% -$545,532.71
Over/Under Est: -46.93% -$535,107.13
Amt Left: 1.75% $10,425.58
Over/Under Est: -41.48% -$473,006.01
Amt Left: 12.19% $72,526.70
Delta: -10.26% -$62,101.12
$696,702.75
Over/Under Est: -38.9% -$443,635.78
Amt Left: 17.13% $101,896.93
Delta: -4.40% -$29,370.23
Over/Under Est: -38.73% -$441,640.53
Amt Left: 17.47% $103,892.18
Delta: -0.29% -$1,995.25
Over/Under Est: -37.37% -$426,185.03
Amt Left: 20.06% $119,347.68
Delta: -2.21% -$15,455.50
Over/Under Est: -26.04% -$296,974.53
Amt Left: 41.79% $248,558.18
Delta: -18.09% -$129,210.50
Over/Under Est: -13.77% -$157,064.53
Amt Left: 65.31% $388,468.18
Delta: -16.59% -$139,910.00
Over/Under Est: 6.95% $79,222.47
Amt Left: 105.04% $624,755.18
Delta: -24.03% -$236,287.00
$1,264,312.00
Over/Under Est: 10.87% $123,973.47
Amt Left: 112.56% $669,506.18
Delta: -3.67% -$44,751.00
Over/Under Est: 15.63% $178,258.47
Amt Left: 121.69% $723,791.18
Delta: -4.29% -$54,285.00
Subcontractor Percentage Amount
NELSON INDUSTRIAL SERVICES, INC. 1.03% $20,995.09
TRP CONSTRUCTION GROUP, LLC 0.70% $14,268.51
NORTEX CONCRETE LIFT & STABILIZATION, INC. 0.51% $10,395.63
TRAFFIC SIGNS & LINES, LLC 0.51% $10,395.63
AWP SAFETY 0.31% $6,318.91
Total: 3.06% $62,373.77

Bid Items & Bid Tabulations

18 Total 0 of 18
JASPER  |  US0096  |  BEAUMONT  |  6477-58-001  |  07/01/2025  |  $1,140,338.53  |  BPM - A00213069  |  BRIDGE PREVENT MAINT  |  30 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GIBSON & ASSOCIATES, INC.
STRUCTURAL INTEGRITY GROUP LLC
EMC CONSTRUCTION SERVICES INC.
PBX BRIDGE COMPANY
THE TRUESDELL CORPORATION
RAGLE CONSTRUCTION, INC.
BLACKSMITH VENTURES LLC
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
SOUTHERN ROAD & BRIDGE, LLC
ICOS MANAGEMENT, LLC
GARRET SHIELDS INFRASTRUCTURE
REMOV CONC (RIPRAP)
CY 3.000 $70.000 $1,000.000 $655.000 $1,312.000 $200.000 $1,050.000 $534.000 $250.000 $150.000 $6,850.000 $500.000 $500.000
FLOWABLE BACKFILL
CY 2.000 $500.000 $1,500.000 $1,100.000 $3,751.500 $1,000.000 $1,550.000 $826.000 $1,000.000 $750.000 $2,250.000 $2,500.000 $600.000
CONC STR REPAIR(DECK REP(PART DEPTH))
SF 4.000 $200.000 $1,000.000 $825.000 $2,253.110 $175.000 $1,050.000 $243.000 $1,000.000 $350.000 $1,450.000 $2,000.000 $200.000
CONC STR REPAIR(DECK REP (FULL DEPTH))
SF 8.000 $800.000 $735.000 $285.000 $3,448.610 $153.000 $3,400.000 $1,055.000 $1,000.000 $400.000 $1,850.000 $2,000.000 $200.000
CONC STR REPAIR (STANDARD)
SF 2.000 $400.000 $50.000 $1,155.000 $1,722.000 $340.000 $950.000 $422.000 $1,000.000 $350.000 $950.000 $1,000.000 $200.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 10.000 $300.000 $1,100.000 $335.000 $1,168.500 $400.000 $520.000 $787.000 $250.000 $500.000 $787.000 $1,500.000 $300.000
MULTI-LAYER POLYMER OVERLAY
SY 10,640.000 $50.000 $36.000 $36.500 $35.650 $43.250 $32.000 $43.600 $46.000 $62.000 $68.000 $80.000 $100.000
SHOT BLASTING
SY 10,640.000 $12.000 $2.250 $6.000 $2.000 $5.000 $3.000 $4.000 $10.000 $10.000 $15.000 $7.000 $8.000
MOBILIZATION
LS 1.000 $146,738.030 $97,000.000 $66,000.000 $138,725.000 $101,680.250 $211,576.200 $72,500.000 $75,000.000 $90,000.000 $115,000.000 $125,000.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $4,000.000 $12,850.000 $14,250.000 $9,500.000 $9,500.000 $7,200.000 $36,250.000 $25,000.000 $6,500.000 $44,500.000 $10,000.000 $5,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 22.000 $320.000 $110.000 $75.000 $89.000 $175.000 $220.000 $67.000 $500.000 $200.000 $150.000 $1.000 $1.000
TMA (STATIONARY)
DAY 30.000 $450.000 $100.000 $250.000 $286.000 $775.000 $450.000 $346.000 $500.000 $300.000 $250.000 $1.000 $300.000
REFL PAV MRK TY I (W)6"(BRK)(090MIL)
LF 630.000 $1.650 $1.650 $1.500 $2.000 $1.950 $2.100 $1.950 $3.000 $3.000 $4.000 $20.000 $2.500
REFL PAV MRK TY I (W)6"(SLD)(090MIL)
LF 2,520.000 $3.000 $1.380 $1.250 $2.000 $1.450 $2.100 $1.450 $3.000 $3.000 $4.000 $10.000 $2.500
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
LF 2,520.000 $3.000 $1.490 $1.350 $2.000 $1.450 $2.100 $1.450 $3.000 $3.000 $4.000 $10.000 $2.500
REFL PAV MRKR TY II-C-R
EA 32.000 $18.000 $13.200 $12.000 $10.000 $10.000 $11.000 $10.000 $10.000 $12.000 $15.000 $100.000 $10.000
REPAIR (T101)
LF 25.000 $75.000 $500.000 $305.000 $526.440 $250.000 $320.000 $175.000 $1,000.000 $350.000 $125.000 $200.000 $100.000
SOIL DENS & RAISING CONC SLABS (HDPF)
LB 2,496.000 $110.000 $4.620 $7.400 $4.200 $4.500 $6.800 $6.500 $14.000 $25.000 $16.000 $30.000 $10.000
Totals: $1,140,338.530 $594,805.820 $605,231.400 $667,332.520 $696,702.750 $698,698.000 $714,153.500 $843,364.000 $983,274.000 $1,219,561.000 $1,264,312.000 $1,318,597.000