Show Job Controls
Bid Cobra

JASPER FM 1408 (1419-01-009)

Items: 53

County: JASPER
Length: N/A
Highway: FM 1408
District: BEAUMONT
Control Number: 1419-01-009
DBE Goal: N/A
Project: BR 1702(118)
Guaranty: N/A
Time: 174 WORKING DAYS
Engineer's Estimate: $1,938,477.60
Date: 05/02/2017 (9 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$1,938,477.60
1
Awarded
$1,409,475.08
Over/Under Est: -27.29% -$529,002.52
Over/Under Est: -24.78% -$480,322.37
Amt Left: 3.45% $48,680.15
Over/Under Est: -9.61% -$186,211.70
Amt Left: 24.32% $342,790.82
Delta: -20.17% -$294,110.67
Over/Under Est: -8.74% -$169,413.81
Amt Left: 25.51% $359,588.71
Delta: -0.96% -$16,797.89
Over/Under Est: -3.12% -$60,391.80
Amt Left: 33.25% $468,610.72
Delta: -6.16% -$109,022.01
Over/Under Est: 0.84% $16,337.80
Amt Left: 38.69% $545,340.32
Delta: -4.09% -$76,729.60

Bid Items & Bid Tabulations

53 Total 0 of 53
JASPER  |  FM 1408  |  BEAUMONT  |  1419-01-009  |  05/02/2017  |  $1,938,477.60  |  BR 1702(118)  |  REPLACE BRIDGE AND APPROACHES  |  174 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ALLCO, LLC
DREWERY CONSTRUCTION COMPANY, INCORPORATED
HODGES AND SON CONSTRUCTION COMPANY, INC.
OLDCASTLE MATERIALS TEXAS, INC.
RAGLE CONSTRUCTION, INC.
LONGVIEW BRIDGE AND ROAD, LTD.
EXCAVATION (ROADWAY)
CY 200.000 $100.000 $25.000 $15.000 $16.000 $108.000 $125.000 $20.000
EXCAVATION (CHANNEL)
CY 1,065.000 $100.000 $27.500 $15.000 $16.000 $23.000 $15.000 $20.000
EMBANKMENT (FINAL)(ORD COMP)(TY A)
CY 136.000 $100.000 $36.000 $55.000 $22.000 $82.000 $125.000 $25.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 383.000 $100.000 $31.000 $32.000 $22.000 $48.000 $50.000 $25.000
BLADING
HR 40.000 $100.000 $80.000 $160.000 $60.000 $120.000 $135.000 $75.000
FURNISHING AND PLACING TOPSOIL (4")
SY 2,984.000 $1.000 $10.000 $4.000 $6.000 $7.500 $1.200 $5.000
BROADCAST SEED (TEMP) (WARM)
SY 2,028.000 $0.150 $0.380 $0.260 $0.600 $0.260 $0.750 $0.350
BROADCAST SEED (TEMP) (COOL)
SY 2,028.000 $0.150 $0.380 $0.260 $0.600 $0.260 $0.750 $0.350
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
SY 4,054.000 $0.300 $0.420 $0.330 $1.600 $0.320 $0.750 $0.500
VEGETATIVE WATERING
MG 38.900 $40.000 $69.940 $15.000 $1.000 $18.000 $100.000 $50.000
SOIL RETENTION BLANKETS (CL 2) (TY F)
SY 1,070.000 $1.500 $3.750 $1.520 $3.000 $1.470 $2.000 $2.000
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 567.000 $60.000 $108.000 $105.000 $95.000 $135.000 $105.000 $100.000
REWORK BS MTL (TY A) (6") (ORD COMP)
SY 2,960.000 $2.500 $4.000 $2.000 $12.000 $3.000 $3.500 $4.000
CEMENT
TON 70.000 $200.000 $152.000 $179.200 $200.000 $140.000 $170.000 $215.000
CEMENT TREAT (MX EXST MTL & NW BS)(9")
SY 3,858.000 $2.500 $4.000 $7.250 $8.000 $10.000 $6.000 $5.000
PRIME COAT (AE-P)
GAL 774.000 $5.000 $8.000 $7.500 $14.000 $8.000 $6.500 $16.000
AGGR (TY-PD GR-4 OR TY-PL GR-4)(SAC-B)
CY 72.000 $150.000 $454.000 $450.000 $600.000 $400.000 $175.000 $350.000
ASPH(AC-15P,AC-20XP,AC10-2TR,AC-12-5TR)
GAL 2,784.000 $4.000 $6.000 $5.000 $10.000 $4.100 $5.500 $7.000
CEM STABIL BKFL
CY 82.000 $180.000 $217.180 $180.000 $320.000 $280.000 $200.000 $215.000
DRILL SHAFT (24 IN)
LF 1,077.000 $150.000 $150.000 $124.000 $130.000 $144.000 $125.000 $170.000
CL C CONC (ABUT)
CY 41.600 $1,300.000 $1,300.000 $1,200.000 $1,200.000 $1,700.000 $1,800.000 $1,500.000
CL C CONC (BENT)
CY 39.900 $1,200.000 $1,425.000 $1,150.000 $1,200.000 $2,000.000 $3,000.000 $1,500.000
REINF CONC SLAB (SLAB BEAM)
SF 7,710.000 $20.000 $20.000 $18.000 $18.000 $15.750 $28.000 $25.000
APPROACH SLAB
CY 96.000 $430.000 $750.000 $570.000 $700.000 $567.000 $475.000 $700.000
PRESTR CONC SLAB BEAM (4SB12)
LF 1,896.000 $180.000 $117.000 $125.000 $180.000 $121.100 $195.000 $175.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 659.000 $200.000 $113.000 $165.000 $150.000 $123.000 $150.000 $240.000
RIPRAP (MOW STRIP)(4 IN)
CY 35.000 $500.000 $255.000 $515.000 $500.000 $1,350.000 $475.000 $750.000
RAIL (TY T223)
LF 528.000 $140.000 $100.000 $140.000 $110.000 $260.000 $95.000 $115.000
ARMOR JOINT (SEALED)
LF 112.000 $100.000 $98.000 $87.000 $120.000 $85.000 $80.000 $85.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $100,000.000 $40,000.000 $25,000.000 $60,000.000 $60,000.000 $65,000.000 $90,000.000
MOBILIZATION
LS 1.000 $250,000.000 $70,000.000 $140,000.000 $150,000.000 $168,000.000 $185,000.000 $190,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $3,000.000 $750.000 $2,000.000 $3,000.000 $3,670.000 $3,850.000 $1,200.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 414.000 $30.000 $20.000 $31.000 $40.000 $30.000 $25.000 $35.000
ROCK FILTER DAMS (REMOVE)
LF 414.000 $10.000 $4.000 $8.400 $20.000 $8.100 $10.000 $8.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 40.000 $50.000 $69.000 $215.000 $60.000 $238.000 $125.000 $100.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 3,510.000 $6.000 $2.300 $5.250 $10.000 $5.100 $4.250 $7.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 3,510.000 $1.000 $0.500 $1.050 $1.000 $1.000 $0.700 $1.000
DRIVEWAYS AND TURNOUTS (SURF TREAT)
SY 84.000 $50.000 $60.000 $45.000 $30.000 $60.000 $50.000 $100.000
MTL W-BEAM GD FEN (TIM POST)
LF 175.000 $25.000 $44.000 $19.000 $32.000 $18.250 $22.000 $25.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 7.000 $2,000.000 $1,425.000 $2,400.000 $2,000.000 $1,285.000 $1,600.000 $1,800.000
GUARDRAIL END TREATMENT (INSTALL)
EA 7.000 $2,500.000 $2,600.000 $2,050.000 $2,500.000 $1,975.000 $2,200.000 $2,000.000
CRASH CUSH ATTEN (INSTL)(R)(N)(TL3)
EA 1.000 $15,000.000 $14,000.000 $17,300.000 $15,000.000 $14,510.000 $15,000.000 $25,000.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 1.000 $250.000 $700.000 $235.000 $200.000 $234.000 $275.000 $315.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 6.000 $500.000 $560.000 $390.000 $400.000 $301.000 $550.000 $415.000
REMOVE SM RD SN SUP&AM
EA 9.000 $100.000 $55.000 $80.000 $200.000 $76.000 $120.000 $105.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND
EA 3.000 $50.000 $54.000 $47.250 $80.000 $46.000 $50.000 $63.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 8.000 $30.000 $20.000 $15.750 $60.000 $15.250 $15.000 $21.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 6.000 $30.000 $48.000 $28.350 $60.000 $28.000 $45.000 $37.800
PAVEMENT SEALER 4"
LF 1,280.000 $0.250 $0.140 $0.110 $2.000 $0.110 $0.100 $0.200
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 3,060.000 $0.350 $1.250 $1.260 $1.000 $1.220 $1.200 $2.000
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 3,060.000 $0.350 $1.250 $1.260 $1.000 $1.220 $1.200 $2.000
REFL PAV MRKR TY II-A-A
EA 40.000 $10.000 $6.000 $5.250 $5.000 $5.100 $5.000 $7.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,000.000 $12,750.000 $12,500.000 $16,000.000 $18,500.000 $15,000.000 $23,000.000
Totals: $1,938,477.600 $1,409,475.086 $1,458,155.230 $1,752,265.900 $1,769,063.790 $1,878,085.800 $1,954,815.400