JASPER US 190 (0213-08-094)
Items: 18
County: JASPER
Length: 3.1500 MILES
Highway: US 190
District: BEAUMONT
Control Number: 0213-08-094
DBE Goal: 0.0%
Project: STP 2025(593)HES
Guaranty: $5,000.00
Time: 38 WORKING DAYS
Engineer's Estimate: $251,865.02
Date: 03/05/2025 (1 year ago)
Contract Number: 3253233
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00184051
Contract Type: Federal
Project Description: BMT_US0190_1 (2021 HSIP) INSTALL ADVANCED WARNING SIGNALS AND SIGNS (INTERSECTION)
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
BRYCE BROUSSARD
JIM GRISSOM
JASPER US 190 (0213-08-094)
Project Name: N/A
Project: STP 2025(593)HES
Length: 0.2000 MILES
Project Type: CONSTRUCTION
Limits From: 0.1 MI W OF FM 777, EAST
Limits To: 0.1 MI E OF FM 777
Project Description: BMT_US0190_1 (2021 HSIP) INSTALL ADVANCED WARNING SIGNALS AND SIGNS (INTERSECTION)
NEWTON SH 87 (0304-06-081)
Project Name: BMT_SH0087_3(2021 HSIP)ADV WARNING SIGNS
Project: STP 2025(593)HES
Length: 0.2000 MILES
Project Type: SAFETY IMPROVEMENT PROJECTS
Limits From: 0.1 MI N OF FM 2626, SOUTH
Limits To: 0.1 MI S OF FM 2626
Project Description: BMT_SH0087_3 (2021 HSIP) INSTALL ADVANCED WARNING SIGNALS AND SIGNS (INTERSECTION)
LIBERTY SH 105 (0951-01-076)
Project Name: BMT_SH0105_1(2021 HSIP)SAFETY LIGHTING
Project: STP 2025(593)HES
Length: 2.7500 MILES
Project Type: SAFETY IMPROVEMENT PROJECTS
Limits From: SH 321, EAST
Limits To: CR 2800
Project Description: BMT_SH0105_1 (2021 HSIP) SAFETY LIGHTING
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$251,865.02 | |||
| $241,007.90 |
-4.31%
-$10,857.12
|
|||
| $256,688.60 |
1.92%
$4,823.58
|
6.51%
$15,680.70
|
||
| $278,751.00 |
10.67%
$26,885.98
|
15.66%
$37,743.10
|
-8.60%
-$22,062.40
|
|
| $318,980.00 |
26.65%
$67,114.98
|
32.35%
$77,972.10
|
-14.43%
-$40,229.00
|
|
| $464,070.00 |
84.25%
$212,204.98
|
92.55%
$223,062.10
|
-45.49%
-$145,090.00
|
E
Engineer's Estimate
$251,865.02
1
Awarded
$241,007.90
Over/Under Est:
-4.31%
-$10,857.12
$256,688.60
Over/Under Est:
1.92%
$4,823.58
Amt Left:
6.51%
$15,680.70
$278,751.00
Over/Under Est:
10.67%
$26,885.98
Amt Left:
15.66%
$37,743.10
Delta:
-8.60%
-$22,062.40
$318,980.00
Over/Under Est:
26.65%
$67,114.98
Amt Left:
32.35%
$77,972.10
Delta:
-14.43%
-$40,229.00
$464,070.00
Over/Under Est:
84.25%
$212,204.98
Amt Left:
92.55%
$223,062.10
Delta:
-45.49%
-$145,090.00
| Subcontractor | Percentage | Amount |
|---|---|---|
| SEMPER STRIPING LLC | 1.35% | $3,253.61 |
| Total: | 1.35% | $3,253.61 |
Bid Items & Bid Tabulations
18
Total
0 of 18
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $4,509.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| Total: | $5,509.00 |