JASPER US 96 (0065-02-058)
Items: 12
County: JASPER
Length: 6.7800 MILES
Highway: US 96
District: BEAUMONT
Control Number: 0065-02-058
DBE Goal: 0.0%
Project: STP 2026(034)HES
Guaranty: $44,000.00
Time: 56 WORKING DAYS
Engineer's Estimate: $2,175,291.20
Date: 10/08/2025 (8 months ago)
Contract Number: 10253021
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00192942
Contract Type: Federal
Project Description: BMT_US0096_4 (2022 HSIP) INSTALL MEDIAN BARRIERS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
BRYCE BROUSSARD
JIM GRISSOM
JASPER US 96 (0065-02-058)
Project Name: N/A
Project: STP 2026(034)HES
Length: 6.7800 MILES
Project Type: CONSTRUCTION
Limits From: 0.2 MI S FM 1005
Limits To: 0.4MI S OF CR 441
Project Description: BMT_US0096_4 (2022 HSIP) INSTALL MEDIAN BARRIERS
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,175,291.20 | |||
| $989,115.00 |
-54.53%
-$1,186,176.20
|
|||
| $1,148,045.60 |
-47.22%
-$1,027,245.60
|
16.07%
$158,930.60
|
||
| $1,194,027.74 |
-45.11%
-$981,263.46
|
20.72%
$204,912.74
|
-4.01%
-$45,982.14
|
|
| $1,383,151.00 |
-36.42%
-$792,140.20
|
39.84%
$394,036.00
|
-15.84%
-$189,123.26
|
|
| $1,472,968.90 |
-32.29%
-$702,322.30
|
48.92%
$483,853.90
|
-6.49%
-$89,817.90
|
|
| $1,617,441.38 |
-25.64%
-$557,849.82
|
63.52%
$628,326.38
|
-9.81%
-$144,472.48
|
|
| $1,751,409.98 |
-19.49%
-$423,881.22
|
77.07%
$762,294.98
|
-8.28%
-$133,968.60
|
|
| $2,158,491.00 |
-0.77%
-$16,800.20
|
118.22%
$1,169,376.00
|
-23.24%
-$407,081.02
|
E
Engineer's Estimate
$2,175,291.20
1
Awarded
$989,115.00
Over/Under Est:
-54.53%
-$1,186,176.20
$1,148,045.60
Over/Under Est:
-47.22%
-$1,027,245.60
Amt Left:
16.07%
$158,930.60
$1,194,027.74
Over/Under Est:
-45.11%
-$981,263.46
Amt Left:
20.72%
$204,912.74
Delta:
-4.01%
-$45,982.14
$1,383,151.00
Over/Under Est:
-36.42%
-$792,140.20
Amt Left:
39.84%
$394,036.00
Delta:
-15.84%
-$189,123.26
$1,472,968.90
Over/Under Est:
-32.29%
-$702,322.30
Amt Left:
48.92%
$483,853.90
Delta:
-6.49%
-$89,817.90
$1,617,441.38
Over/Under Est:
-25.64%
-$557,849.82
Amt Left:
63.52%
$628,326.38
Delta:
-9.81%
-$144,472.48
$1,751,409.98
Over/Under Est:
-19.49%
-$423,881.22
Amt Left:
77.07%
$762,294.98
Delta:
-8.28%
-$133,968.60
$2,158,491.00
Over/Under Est:
-0.77%
-$16,800.20
Amt Left:
118.22%
$1,169,376.00
Delta:
-23.24%
-$407,081.02
| Subcontractor | Percentage | Amount |
|---|---|---|
| J. H. ODEN CONTRACTING COMPANY | 2.97% | $29,376.72 |
| LONESTAR TRAFFIC SAFETY, LLC | 0.62% | $6,132.51 |
| Total: | 3.59% | $35,509.23 |
Bid Items & Bid Tabulations
12
Total
0 of 12
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $8,000.00 |
| Total: | $13,000.00 |