JACKSON SH 172 (0420-02-047)

Items: 65

County: JACKSON
Length: N/A
Highway: SH 172
District: YOAKUM
Control Number: 0420-02-047
DBE Goal: N/A
Project: STP 2020(630)HES
Guaranty: N/A
Time: 210 WORKING DAYS
Engineer's Estimate: $1,247,429.00
Date: 03/05/2020 (6 years ago)
Contract Number: N/A
Type: SAEFTY TREAT FIXED OBJECTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$1,247,429.00
$1,200,898.00
Over/Under Est: -3.73% -$46,531.00
$1,660,867.00
Over/Under Est: 33.14% $413,438.00
Amt Left: 38.3% $459,969.00
$1,976,180.00
Over/Under Est: 58.42% $728,751.00
Amt Left: 64.56% $775,282.00
Delta: -18.98% -$315,313.00
Over/Under Est: 76.31% $951,943.00
Amt Left: 83.14% $998,474.00
Delta: -11.29% -$223,192.00

Bid Items & Bid Tabulations

65 Total 0 of 65
JACKSON  |  SH 172  |  YOAKUM  |  0420-02-047  |  03/05/2020  |  $1,247,429.00  |  STP 2020(630)HES  |  SAEFTY TREAT FIXED OBJECTS  |  210 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SJ&J CONSTRUCTION, LLC
3LW CIVIL LLC
FNH CONSTRUCTION, LLC
TIERRA LEASE SERVICE, LLC
PREPARING ROW(TREE)(12" TO 24" DIA)
EA 10.000 $1,500.000 $300.000 $1,000.000 $5,000.000 $3,000.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 2,834.000 $50.000 $18.000 $42.000 $40.000 $58.000
BLADING
HR 226.000 $100.000 $50.000 $155.000 $150.000 $150.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 8,440.000 $1.000 $0.500 $0.900 $1.000 $2.000
VEGETATIVE WATERING
MG 71.000 $100.000 $20.000 $50.000 $100.000 $65.000
HMCL ACP TY-D AC-0.6
TON 197.000 $250.000 $85.000 $300.000 $185.000 $350.000
CEM STABIL BKFL
CY 110.000 $120.000 $160.000 $200.000 $350.000 $280.000
CUT & RESTORING PAV
SY 70.000 $85.000 $90.000 $117.000 $200.000 $200.000
CUT AND RESTORE PAV (FLEX BASE)
SY 71.000 $100.000 $60.000 $88.000 $100.000 $175.000
TRENCH EXCAVATION PROTECTION
LF 32.000 $15.000 $30.000 $20.000 $20.000 $100.000
TEMPORARY SPL SHORING
SF 133.000 $13.000 $20.000 $40.000 $85.000 $200.000
TEMPORARY SPL SHORING (COFFERDAM)
SF 100.000 $30.000 $40.000 $50.000 $150.000 $125.000
RIPRAP (CONC)(5 IN)
CY 7.300 $400.000 $500.000 $1,000.000 $650.000 $1,100.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 17.000 $200.000 $180.000 $300.000 $185.000 $350.000
CMP (GAL STL 18 IN)
LF 228.000 $100.000 $45.000 $85.000 $85.000 $85.000
CMP (GAL STL 24 IN)
LF 8.000 $125.000 $90.000 $110.000 $105.000 $125.000
CMP (GAL STL 36 IN)
LF 16.000 $150.000 $160.000 $190.000 $150.000 $150.000
CMP AR (GAL STL DES 2)
LF 8.000 $110.000 $160.000 $95.000 $85.000 $125.000
CMP AR (GAL STL DES 3)
LF 36.000 $150.000 $180.000 $200.000 $95.000 $150.000
CONC BOX CULV (4 FT X 2 FT)
LF 71.000 $600.000 $600.000 $375.000 $1,020.000 $675.000
CONC BOX CULV (9 FT X 5 FT)
LF 34.000 $1,000.000 $850.000 $1,000.000 $2,000.000 $1,700.000
CONC BOX CULV (4 FT X 2 FT)(EXTEND)
LF 20.000 $600.000 $700.000 $750.000 $1,000.000 $1,575.000
CONC BOX CULV (5 FT X 2 FT)(EXTEND)
LF 60.000 $650.000 $850.000 $700.000 $1,250.000 $500.000
CONC BOX CULV (6 FT X 3 FT)(EXTEND)
LF 4.000 $700.000 $900.000 $800.000 $1,500.000 $1,300.000
CONC BOX CULV (6 FT X 2 FT) (EXTEND)
LF 5.000 $700.000 $1,000.000 $900.000 $1,400.000 $1,200.000
RC PIPE (CL III)(15 IN)
LF 64.000 $90.000 $65.000 $110.000 $85.000 $200.000
RC PIPE (CL III)(18 IN)
LF 503.000 $85.000 $77.000 $100.000 $85.000 $160.000
RC PIPE (CL III)(24 IN)
LF 230.000 $100.000 $110.000 $110.000 $105.000 $180.000
RC PIPE (CL III)(36 IN)
LF 8.000 $150.000 $250.000 $160.000 $150.000 $250.000
WINGWALL (PW - 1) (HW=3 FT)
EA 2.000 $7,000.000 $4,000.000 $10,000.000 $6,500.000 $15,000.000
SET (TY I)(S= 4 FT)(HW= 3 FT)(3:1) (C)
EA 2.000 $6,000.000 $6,500.000 $10,000.000 $8,500.000 $10,000.000
SET (TY I)(S= 4 FT)(HW= 3 FT)(4:1) (C)
EA 2.000 $6,100.000 $6,500.000 $11,000.000 $8,500.000 $12,000.000
SET (TY I)(S= 4 FT)(HW= 3 FT)(6:1) (P)
EA 8.000 $6,200.000 $7,000.000 $11,000.000 $8,500.000 $12,000.000
SET (TY I)(S= 6 FT)(HW= 3 FT)(4:1) (C)
EA 1.000 $5,000.000 $8,500.000 $11,000.000 $10,000.000 $12,000.000
SET (TY I)(S= 6 FT)(HW= 4 FT)(3:1) (C)
EA 1.000 $6,200.000 $8,500.000 $13,500.000 $15,000.000 $13,000.000
SET (TY I)(S= 9 FT)(HW= 6 FT)(3:1) (C)
EA 2.000 $9,000.000 $10,000.000 $15,000.000 $40,000.000 $30,000.000
SET (TY II) (15 IN) (RCP) (6: 1) (P)
EA 28.000 $900.000 $700.000 $1,000.000 $1,850.000 $2,000.000
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 73.000 $900.000 $900.000 $1,500.000 $1,250.000 $1,750.000
SET (TY II) (18 IN) (HDPE) (6: 1) (P)
EA 6.000 $1,000.000 $900.000 $1,500.000 $1,850.000 $1,750.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 106.000 $950.000 $900.000 $1,500.000 $1,100.000 $2,000.000
SET (TY II) (24 IN) (CMP) (6: 1) (P)
EA 20.000 $1,200.000 $1,050.000 $2,000.000 $2,000.000 $2,250.000
SET (TY II) (24 IN) (HDPE) (6: 1) (P)
EA 6.000 $1,200.000 $1,050.000 $1,500.000 $2,100.000 $2,000.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 46.000 $1,250.000 $1,100.000 $1,600.000 $2,000.000 $2,500.000
SET (TY II) (27 IN) (RCP) (6: 1) (P)
EA 4.000 $1,375.000 $1,200.000 $4,000.000 $2,850.000 $2,750.000
SET (TY II) (36 IN) (CMP) (6: 1) (P)
EA 2.000 $3,500.000 $2,800.000 $3,750.000 $4,000.000 $2,500.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 2.000 $2,500.000 $3,200.000 $5,000.000 $4,000.000 $3,500.000
SET (TY II) (DES 2) (CMP) (6: 1) (P)
EA 2.000 $1,000.000 $3,200.000 $1,500.000 $4,000.000 $2,500.000
SET (TY II) (DES 3) (CMP) (6: 1) (P)
EA 10.000 $1,250.000 $3,200.000 $2,000.000 $4,000.000 $3,000.000
REMOV STR (SMALL)
EA 15.000 $500.000 $500.000 $3,500.000 $2,500.000 $2,500.000
MOBILIZATION
LS 1.000 $90,000.000 $150,000.000 $85,000.000 $180,000.000 $225,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $2,500.000 $4,000.000 $12,000.000 $8,500.000 $5,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 25.000 $30.000 $20.000 $30.000 $30.000 $50.000
ROCK FILTER DAMS (REMOVE)
LF 25.000 $8.000 $8.000 $15.000 $15.000 $25.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,565.000 $2.500 $4.000 $3.000 $4.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,565.000 $1.000 $1.000 $1.500 $2.000 $2.000
MTL W-BEAM GD FEN (TIM POST)
LF 2,700.000 $22.000 $31.000 $20.000 $25.000 $28.000
MTL BEAM GD FEN TRANS (T6)
EA 4.000 $625.000 $200.000 $700.000 $1,850.000 $1,000.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 125.000 $65.000 $60.000 $60.000 $50.000 $75.000
REMOVE METAL BEAM GUARD FENCE
LF 3,225.000 $2.500 $3.000 $1.500 $4.000 $3.000
GUARDRAIL END TREATMENT (INSTALL)
EA 20.000 $2,400.000 $2,500.000 $2,500.000 $3,000.000 $3,000.000
GUARDRAIL END TREATMENT (REMOVE)
EA 24.000 $300.000 $300.000 $330.000 $1,500.000 $400.000
WIRE FENCE (WATER GAP) (SPECIAL)
LF 57.000 $150.000 $100.000 $35.000 $500.000 $55.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 10.000 $75.000 $60.000 $50.000 $100.000 $200.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 38.000 $25.000 $40.000 $30.000 $100.000 $50.000
TMA (STATIONARY)
DAY 32.000 $350.000 $100.000 $150.000 $350.000 $500.000
Totals: $1,247,429.000 $1,200,898.000 $1,660,867.000 $1,976,180.000 $2,199,372.000