JACKSON SL 522 (0089-12-004)

Items: 49

County: JACKSON
Length: N/A
Highway: SL 522
District: YOAKUM
Control Number: 0089-12-004
DBE Goal: N/A
Project: STP 2018(355)HES
Guaranty: N/A
Time: 90 WORKING DAYS
Engineer's Estimate: $680,230.20
Date: 12/05/2017 (8 years ago)
Contract Number: N/A
Type: SAFETY TREAT FIXED OBJECTS & WIDEN ROADWAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$680,230.20
$679,501.16
Over/Under Est: -0.11% -$729.04
Over/Under Est: 10.86% $73,901.60
Amt Left: 10.98% $74,630.64
$798,397.18
Over/Under Est: 17.37% $118,166.98
Amt Left: 17.5% $118,896.02
Delta: -5.87% -$44,265.38
Over/Under Est: 46.65% $317,300.82
Amt Left: 46.8% $318,029.86
Delta: -24.94% -$199,133.84
Over/Under Est: 110.17% $749,393.20
Amt Left: 110.39% $750,122.24
Delta: -43.32% -$432,092.38

Bid Items & Bid Tabulations

49 Total 0 of 49
JACKSON  |  SL 522  |  YOAKUM  |  0089-12-004  |  12/05/2017  |  $680,230.20  |  STP 2018(355)HES  |  SAFETY TREAT FIXED OBJECTS & WIDEN R...  |  90 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ISI CONTRACTING, INC.
HILL COUNTRY BRIDGE, INC.
SB CONTRACTORS LLC
CHAMPION INFRASTRUCTURE, LLC
REXCO CONSTRUCTION SERVICES, INC.
PREPARING ROW
STA 2.000 $2,500.000 $4,500.000 $4,800.000 $4,000.000 $3,500.000 $3,500.000
REMOVING CONC (SIDEWALKS)
SY 2.000 $20.000 $42.000 $200.000 $110.000 $300.000 $350.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 890.000 $15.000 $16.000 $19.000 $30.000 $52.000 $44.000
BLADING
HR 40.000 $100.000 $100.000 $160.000 $55.000 $160.000 $95.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 6,200.000 $0.500 $0.400 $0.500 $0.360 $2.000 $0.640
VEGETATIVE WATERING
MG 52.200 $50.000 $20.000 $100.000 $35.000 $200.000 $50.000
CEM STABIL BKFL
CY 96.000 $150.000 $75.000 $140.000 $155.000 $240.000 $130.200
CUT & RESTORING PAV
SY 27.000 $80.000 $100.000 $143.000 $100.000 $260.000 $230.000
CUT AND RESTORE PAV (FLEX BASE)
SY 24.000 $75.000 $100.000 $96.000 $110.000 $140.000 $90.000
TRENCH EXCAVATION PROTECTION
LF 200.000 $10.000 $1.000 $10.000 $8.000 $40.000 $15.000
TEMPORARY SPL SHORING
SF 700.000 $20.000 $5.000 $24.000 $32.500 $25.000 $10.000
RIPRAP (CONC)(5 IN)
CY 64.000 $425.000 $485.000 $600.000 $575.000 $790.000 $371.400
RIPRAP (STONE COMMON)(DRY)(18 IN)
CY 20.000 $200.000 $120.000 $150.000 $200.000 $320.000 $177.600
RIPRAP (MOW STRIP)(5 IN)
CY 43.000 $450.000 $550.000 $560.000 $525.000 $760.000 $391.400
CMP (GAL STL 24 IN)
LF 8.000 $100.000 $68.000 $90.000 $110.000 $150.000 $109.760
CONC BOX CULV (5 FT X 3 FT)
LF 54.000 $500.000 $470.000 $545.000 $400.000 $310.000 $488.200
CONC BOX CULV (5 FT X 5 FT)
LF 183.000 $350.000 $400.000 $320.000 $375.000 $290.000 $3,792.130
CONC BOX CULV (7 FT X 5 FT)
LF 111.000 $600.000 $700.000 $745.000 $550.000 $380.000 $885.600
CONC BOX CULV (6 FT X 2 FT)
LF 8.000 $800.000 $550.000 $775.000 $600.000 $420.000 $1,293.000
RC PIPE (CL III)(18 IN)
LF 76.000 $65.000 $90.000 $50.000 $105.000 $50.000 $49.250
RC PIPE (CL III)(24 IN)
LF 148.000 $80.000 $118.000 $77.000 $115.000 $70.000 $77.330
RC PIPE (CL III)(30 IN)
LF 24.000 $100.000 $170.000 $92.000 $135.000 $160.000 $127.950
RC PIPE (CL III)(42 IN)
LF 48.000 $175.000 $175.000 $155.000 $195.000 $210.000 $203.820
WINGWALL (FW - 0) (HW=11 FT)
EA 1.000 $20,000.000 $9,000.000 $6,320.000 $7,500.000 $21,000.000 $13,380.000
SET (TY I)(S= 5 FT)(HW= 6 FT)(3:1) (C)
EA 4.000 $6,000.000 $5,700.000 $5,300.000 $8,000.000 $9,000.000 $6,862.080
SET (TY I)(S= 5 FT)(HW= 6 FT)(6:1) (P)
EA 1.000 $12,000.000 $6,000.000 $7,900.000 $13,000.000 $11,000.000 $9,459.920
SET (TY I)(S= 6 FT)(HW= 3 FT)(3:1) (C)
EA 2.000 $5,000.000 $5,000.000 $4,800.000 $7,500.000 $10,000.000 $6,964.240
SET (TY I)(S= 6 FT)(HW= 4 FT)(6:1) (P)
EA 2.000 $8,000.000 $6,400.000 $6,600.000 $11,000.000 $12,000.000 $8,820.240
SET (TY I)(S= 7 FT)(HW= 4 FT)(6:1) (P)
EA 2.000 $9,000.000 $6,700.000 $7,700.000 $10,500.000 $14,000.000 $10,150.640
SET (TY I)(S= 7 FT)(HW= 5 FT)(6:1) (P)
EA 2.000 $9,500.000 $6,700.000 $10,800.000 $10,500.000 $16,000.000 $11,467.360
SET (TY I)(S= 7 FT)(HW= 6 FT)(3:1) (C)
EA 8.000 $7,000.000 $7,300.000 $3,000.000 $8,000.000 $12,000.000 $9,969.440
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 4.000 $900.000 $1,000.000 $1,265.000 $1,400.000 $1,800.000 $1,017.240
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 22.000 $1,000.000 $1,000.000 $1,500.000 $1,200.000 $2,100.000 $1,005.480
SET (TY II) (24 IN) (CMP) (6: 1) (P)
EA 2.000 $1,200.000 $1,200.000 $1,800.000 $1,300.000 $2,100.000 $1,041.080
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 23.000 $1,200.000 $1,000.000 $1,935.000 $1,400.000 $2,400.000 $1,419.640
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 6.000 $2,000.000 $1,500.000 $3,200.000 $1,700.000 $2,800.000 $2,108.200
SET (TY II) (42 IN) (RCP) (6: 1) (P)
EA 12.000 $2,500.000 $3,000.000 $5,300.000 $2,500.000 $7,000.000 $4,502.240
REMOV STR (SMALL)
EA 6.000 $800.000 $100.000 $1,100.000 $1,500.000 $1,500.000 $1,250.000
MOBILIZATION
LS 1.000 $50,000.000 $67,000.000 $57,000.000 $78,000.000 $40,000.000 $52,400.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $2,500.000 $2,000.000 $3,000.000 $5,000.000 $5,000.000 $728.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 200.000 $30.000 $30.000 $33.000 $30.900 $80.000 $41.550
ROCK FILTER DAMS (REMOVE)
LF 200.000 $10.000 $9.000 $12.000 $11.940 $40.000 $25.480
TEMP SEDMT CONT FENCE (INSTALL)
LF 900.000 $4.000 $2.500 $2.700 $3.600 $8.000 $4.940
TEMP SEDMT CONT FENCE (REMOVE)
LF 900.000 $1.000 $2.000 $1.500 $1.400 $4.000 $2.080
MTL W-BEAM GD FEN (TIM POST)
LF 359.660 $20.000 $20.000 $27.000 $25.250 $29.000 $26.260
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 65.340 $50.000 $94.000 $47.000 $44.350 $32.000 $46.120
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,200.000 $2,500.000 $2,600.000 $2,446.000 $2,900.000 $2,543.840
INSTL OM ASSM (OM-2Z)(FLX)GND(BI)
EA 4.000 $60.000 $45.000 $50.000 $45.550 $100.000 $47.370
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 13.000 $30.000 $30.000 $17.000 $15.750 $100.000 $16.380
Totals: $680,230.200 $679,501.160 $754,131.800 $798,397.194 $997,531.020 $1,429,623.402