JACK SH 59 (0134-05-034)

Items: 81

County: JACK
Length: N/A
Highway: SH 59
District: FORT WORTH
Control Number: 0134-05-034
DBE Goal: N/A
Project: C 134-5-34
Guaranty: N/A
Time: 234 WORKING DAYS
Engineer's Estimate: $3,295,665.62
Date: 01/07/2022 (4 years ago)
Contract Number: N/A
Type: INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFT T
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (3)
E
Engineer's Estimate
$3,295,665.62
$3,685,479.68
Over/Under Est: 11.83% $389,814.06
$4,610,119.64
Over/Under Est: 39.88% $1,314,454.02
Amt Left: 25.09% $924,639.96
Over/Under Est: 43.18% $1,422,933.91
Amt Left: 28.03% $1,033,119.85
Delta: -2.35% -$108,479.89
Subcontractor Percentage Amount
RAMBO CONTRACTING, INC. 8.70% $320,636.73
FARR FOUNDATION, INC. 2.83% $104,299.07
J. H. ODEN CONTRACTING COMPANY 2.50% $92,136.99
STRIPING TECHNOLOGY, L.P. 2.47% $91,031.35
SOUTHERN CROSS CONTRACTORS, LLC 2.28% $84,028.94
XROADS, L.P. 1.41% $51,965.26
DUSTROL, INC. 1.25% $46,068.50
WEST TEXAS ROCK RESOURCES, LLC 0.15% $5,528.22
Total: 21.59% $795,695.06

Bid Items & Bid Tabulations

81 Total 0 of 81
JACK  |  SH 59  |  FORT WORTH  |  0134-05-034  |  01/07/2022  |  $3,295,665.62  |  C 134-5-34  |  INTERS IMPRVS WITH RIGHT AND/OR LEFT...  |  234 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JAGOE-PUBLIC COMPANY
DIGG COMMERCIAL, LLC
EUROVIA ATLANTIC COAST LLC
PREPARING ROW
STA 58.150 $3,200.000 $750.000 $1,667.000 $135.000
REMOVING CONC (DRIVEWAYS)
SY 191.000 $16.000 $46.000 $83.000 $35.000
REMOVING STAB BASE AND ASPH PAV(0"-16")
SY 7,891.000 $17.000 $6.900 $9.000 $12.000
REMOV STAB BASE AND ASPH PAV (3"-9")
SY 563.000 $7.750 $6.900 $11.000 $15.000
EXCAVATION (ROADWAY)
CY 4,679.390 $5.000 $13.000 $37.000 $23.500
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 4,886.310 $25.000 $11.000 $44.000 $23.500
COMPOST MANUF TOPSOIL (4")
SY 12,052.000 $0.900 $4.900 $5.000 $5.500
BROADCAST SEED (TEMP) (WARM)
SY 12,052.000 $1.950 $0.300 $1.160 $0.250
BROADCAST SEED (TEMP) (COOL)
SY 12,052.000 $2.400 $0.300 $1.160 $0.250
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 12,052.000 $1.000 $0.400 $1.450 $0.330
VEGETATIVE WATERING
MG 421.820 $21.000 $80.000 $58.000 $55.000
FL BS (CMP IN PLACE)(TY A GR 1-2)(12")
SY 20,873.000 $22.800 $25.000 $20.000 $28.000
LIME (HYDRATED LIME (SLURRY))
TON 324.600 $161.000 $230.000 $222.000 $215.000
LIME TRT (SUBGRADE)(8")
SY 19,473.000 $5.500 $7.500 $14.000 $12.500
CEMENT
TON 434.900 $175.000 $310.000 $248.000 $265.000
CEMENT TREAT (NEW BASE)(12")
SY 20,873.000 $3.030 $3.500 $10.000 $10.600
PRIME COAT (MC-30 OR EC-30)
GAL 4,174.600 $3.250 $4.500 $7.400 $5.000
TEMPORARY SPL SHORING
SF 3,120.000 $14.000 $42.000 $39.000 $45.000
RIPRAP (STONE TYPE R)(DRY)(24")
CY 45.000 $250.000 $250.000 $220.000 $375.000
RIPRAP (MOW STRIP)(4 IN)
CY 79.000 $510.000 $600.000 $754.000 $815.000
CONC BOX CULV (4 FT X 4 FT)(EXTEND)
LF 84.000 $540.850 $360.000 $1,088.000 $900.000
CONC BOX CULV (6 FT X 5 FT)(EXTEND)
LF 32.000 $1,326.150 $670.000 $1,400.000 $1,175.000
RC PIPE (CL III)(24 IN)
LF 484.000 $67.000 $160.000 $130.000 $90.000
JCT BOX (CIP)(SPL)(COMPL)(27FTX14FT)
EA 1.000 $96,000.000 $69,000.000 $69,500.000 $90,000.000
WINGWALL (FW - 0) (HW=6 FT)
EA 1.000 $12,000.000 $13,000.000 $11,050.000 $27,000.000
WINGWALL (PW - 1) (HW=10 FT)
EA 1.000 $41,908.000 $59,000.000 $31,500.000 $54,000.000
WINGWALL (PW - 1) (HW=12 FT)
EA 1.000 $100,000.000 $108,000.000 $53,000.000 $85,500.000
WINGWALL (PW - 1) (HW=5 FT)
EA 1.000 $13,700.000 $25,000.000 $25,100.000 $18,000.000
WINGWALL (PW - 1) (HW=8 FT)
EA 1.000 $26,500.000 $44,000.000 $33,150.000 $41,000.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 20.000 $1,750.000 $1,700.000 $2,575.000 $1,700.000
CLEAN EXIST CULVERTS
EA 5.000 $1,680.000 $910.000 $3,962.000 $2,500.000
REMOV STR (WINGWALL)
EA 4.000 $2,450.000 $3,300.000 $4,728.000 $1,500.000
REMOV STR (PIPE)
LF 64.000 $16.500 $6.800 $67.000 $20.000
MOBILIZATION
LS 1.000 $291,442.330 $355,000.000 $369,000.000 $300,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 11.000 $8,000.000 $20,000.000 $6,620.000 $56,000.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 222.000 $19.000 $32.000 $21.000 $25.000
CONSTRUCTION EXITS (REMOVE)
SY 222.000 $8.150 $13.000 $6.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 12,542.000 $1.890 $3.600 $4.000 $2.850
TEMP SEDMT CONT FENCE (REMOVE)
LF 12,542.000 $0.280 $0.500 $1.000 $0.400
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 132.000 $5.850 $7.600 $10.000 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 132.000 $1.200 $1.300 $2.000 $1.000
DRIVEWAYS (CONC)
SY 163.000 $82.500 $90.000 $138.000 $190.000
DRIVEWAYS (ACP)
SY 1,129.000 $45.000 $35.000 $56.000 $70.000
TURNOUTS (ACP)
SY 6.000 $55.000 $30.000 $200.000 $375.000
RUMBLE STRIPS (SHOULDER)
LF 11,218.000 $0.200 $0.550 $1.000 $0.760
RUMBLE STRIPS (CENTERLINE)
LF 1,515.000 $0.170 $0.550 $2.000 $1.020
MTL W-BEAM GD FEN (TIM POST)
LF 1,900.000 $24.000 $35.000 $46.000 $27.850
REMOVE METAL BEAM GUARD FENCE
LF 436.000 $2.800 $5.100 $7.000 $4.000
GUARDRAIL END TREATMENT (INSTALL)
EA 10.000 $2,750.000 $3,800.000 $3,549.000 $3,000.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $250.000 $320.000 $750.000 $250.000
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 1.000 $380.000 $570.000 $1,260.000 $545.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 29.000 $640.000 $910.000 $890.000 $800.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 4.000 $800.000 $1,200.000 $892.000 $900.000
IN SM RD SN SUP&AM TYS80(1)SA(T-2EXT)
EA 1.000 $1,100.000 $1,400.000 $1,200.000 $950.000
REMOVE SM RD SN SUP&AM
EA 15.000 $160.000 $120.000 $450.000 $100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 44.000 $30.000 $60.000 $132.000 $50.000
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 24.000 $190.000 $250.000 $144.000 $80.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 32,402.000 $0.850 $1.100 $1.080 $0.900
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 28,699.000 $0.900 $1.100 $1.080 $0.900
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,092.000 $0.800 $0.950 $5.000 $2.500
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 2,240.000 $1.000 $1.100 $1.400 $0.850
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 11,085.000 $0.400 $0.650 $0.800 $0.500
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 1,540.000 $0.450 $1.300 $1.200 $1.000
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 12,000.000 $0.390 $0.650 $0.800 $0.500
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 84.000 $15.000 $19.000 $26.000 $15.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 6.000 $198.000 $250.000 $280.000 $200.000
PREFAB PAV MRK TY C (W) (WORD)
EA 6.000 $249.000 $320.000 $320.000 $250.000
REFL PAV MRKR TY I-C
EA 160.000 $3.950 $5.100 $8.000 $4.000
REFL PAV MRKR TY II-A-A
EA 360.000 $5.000 $5.100 $8.000 $4.000
ELIM EXT PAV MRK & MRKS (4")
LF 60,216.000 $0.550 $0.300 $0.500 $0.250
STRIP MOWING
CYC 1.000 $3,000.000 $1,800.000 $4,000.000 $7,500.000
LITTER REMOVAL
CYC 12.000 $1,750.000 $910.000 $1,100.000 $1,600.000
D-GR HMA TY-B PG64-22
TON 2,782.700 $78.000 $85.000 $134.000 $110.000
D-GR HMA TY-B PG64-22 (LEVEL-UP)
TON 19.200 $83.000 $200.000 $240.000 $250.000
SP MIXES SP-C SAC-A PG70-28
TON 2,948.000 $115.000 $115.000 $154.000 $130.000
TACK COAT
GAL 6,835.200 $0.210 $2.500 $3.000 $3.250
INTRLCK ART CONC BLKS (4" MIN)
SF 335.000 $12.000 $36.000 $95.000 $52.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,000.000 $13,000.000 $15,000.000 $22,000.000
TMA (STATIONARY)
DAY 200.000 $100.000 $75.000 $400.000 $325.000
TMA (MOBILE OPERATION)
HR 1,600.000 $35.000 $25.000 $80.000 $48.000
CASING STEEL (30IN)
LF 90.000 $203.000 $350.000 $240.000 $300.000
Totals: $3,295,665.622 $3,685,479.680 $4,610,119.640 $4,718,599.540