PREPARING ROW
|
AC
|
11.000
|
$7,500.000
|
$4,050.000
|
$3,900.000
|
$5,000.000
|
|
|
PREPARING ROW
|
STA
|
703.000
|
$200.000
|
$32.870
|
$8.150
|
$14.650
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
65.000
|
$50.000
|
$32.400
|
$18.500
|
$46.600
|
|
|
REMOVING CONC (CURB AND GUTTER)
|
LF
|
16.000
|
$50.000
|
$32.400
|
$20.500
|
$43.500
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
308.000
|
$40.000
|
$49.260
|
$28.500
|
$28.250
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY B)
|
CY
|
1,036.000
|
$40.000
|
$48.680
|
$49.000
|
$40.000
|
|
|
BACKFILL (TY A)
|
STA
|
711.000
|
$220.000
|
$227.150
|
$240.000
|
$290.000
|
|
|
BLADING
|
STA
|
27.000
|
$190.000
|
$167.010
|
$215.000
|
$315.000
|
|
|
BROADCAST SEED (PERM) (RURAL) (SANDY)
|
AC
|
26.000
|
$700.000
|
$588.600
|
$525.000
|
$575.000
|
|
|
DRILL SEEDING (PERM) (RURAL) (SANDY)
|
AC
|
33.000
|
$700.000
|
$588.600
|
$510.000
|
$575.000
|
|
|
DRILL SEEDING (TEMP)(WARM OR COOL)
|
AC
|
33.000
|
$420.000
|
$432.000
|
$500.000
|
$420.000
|
|
|
BROADCAST SEED (TEMP)(WARM OR COOL)
|
SY
|
32.000
|
$700.000
|
$16.870
|
$500.000
|
$16.500
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY C)
|
SY
|
9,000.000
|
$2.500
|
$2.160
|
$4.100
|
$2.150
|
|
|
EMULS ASPH (EROSN CONT)(MULTI)
|
GAL
|
15,972.000
|
$4.000
|
$3.940
|
$4.600
|
$3.850
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(2")
|
SY
|
9,919.000
|
$20.000
|
$19.310
|
$26.000
|
$27.250
|
|
|
PLANE ASPH CONC PAV(0" TO 2")
|
SY
|
11,098.000
|
$3.000
|
$4.830
|
$4.900
|
$4.150
|
|
|
PLANE ASPH CONC PAV (2")
|
SY
|
12,533.000
|
$3.000
|
$4.670
|
$3.750
|
$3.250
|
|
|
CUT & RESTORE ASPH PAVING
|
SY
|
18.000
|
$300.000
|
$162.000
|
$100.000
|
$575.000
|
|
|
CL A CONC (COLLAR)
|
EA
|
20.000
|
$1,100.000
|
$1,296.000
|
$2,000.000
|
$2,110.000
|
|
|
CONC STR REPAIR(DECK REP(PART DEPTH))
|
SF
|
146.000
|
$210.000
|
$97.200
|
$92.000
|
$95.000
|
|
|
CONC STR REPAIR(DECK REP (FULL DEPTH))
|
SF
|
228.000
|
$230.000
|
$129.600
|
$120.000
|
$126.550
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
72.000
|
$750.000
|
$756.000
|
$840.000
|
$870.150
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
261.000
|
$750.000
|
$756.000
|
$895.000
|
$738.280
|
|
|
CLEANING EXISTING JOINTS
|
LF
|
120.000
|
$25.000
|
$21.600
|
$20.500
|
$21.100
|
|
|
MULTI-LAYER POLYMER OVERLAY
|
SY
|
989.000
|
$70.000
|
$61.560
|
$58.000
|
$60.150
|
|
|
HEADER TYPE EXPANSION JOINT
|
CF
|
40.000
|
$460.000
|
$1,317.600
|
$1,200.000
|
$1,285.000
|
|
|
JOINT SEALANT
|
LF
|
160.000
|
$45.000
|
$187.920
|
$180.000
|
$185.000
|
|
|
JOINT SEALANT (SPL)
|
LF
|
160.000
|
$50.000
|
$166.320
|
$155.000
|
$165.000
|
|
|
CMP (GAL STL 24 IN)
|
LF
|
10.000
|
$150.000
|
$232.200
|
$155.000
|
$160.000
|
|
|
CMP (GAL STL 48 IN)
|
LF
|
16.000
|
$300.000
|
$594.000
|
$255.000
|
$265.000
|
|
|
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
|
LF
|
14.000
|
$750.000
|
$1,080.000
|
$920.000
|
$950.000
|
|
|
CONC BOX CULV (3 FT X 3 FT)(EXTEND)
|
LF
|
4.000
|
$750.000
|
$1,296.000
|
$1,000.000
|
$1,055.000
|
|
|
CONC BOX CULV (4 FT X 3 FT)(EXTEND)
|
LF
|
4.000
|
$1,000.000
|
$1,620.000
|
$1,200.000
|
$1,265.000
|
|
|
CONC BOX CULV (5 FT X 5 FT)(EXTEND)
|
LF
|
4.000
|
$1,500.000
|
$1,944.000
|
$1,400.000
|
$1,475.000
|
|
|
CONC BOX CULV (4 FT X 2.5 FT) (EXTEND)
|
LF
|
10.000
|
$1,500.000
|
$1,512.000
|
$1,200.000
|
$1,265.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
4.000
|
$200.000
|
$108.000
|
$205.000
|
$210.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
52.000
|
$210.000
|
$135.000
|
$225.000
|
$235.000
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
10.000
|
$300.000
|
$162.000
|
$275.000
|
$285.000
|
|
|
INLET (COMPL)(PSL)(FG)(4FTX4FT-4FTX4FT)
|
EA
|
1.000
|
$9,500.000
|
$9,180.000
|
$11,500.000
|
$12,130.000
|
|
|
SET (TY I) (30 IN) (3: 1) (C)
|
EA
|
1.000
|
$4,000.000
|
$5,400.000
|
$14,500.000
|
$14,765.000
|
|
|
SET (TY I) (42 IN) (4: 1) (C)
|
EA
|
1.000
|
$7,500.000
|
$8,100.000
|
$24,500.000
|
$25,300.000
|
|
|
SET (TY I) (48 IN) (4: 1) (C)
|
EA
|
4.000
|
$8,500.000
|
$9,180.000
|
$23,000.000
|
$23,750.000
|
|
|
SET (TY I)(S=3 FT)(HW=3FT)(4:1)(C)
|
EA
|
2.000
|
$10,000.000
|
$7,020.000
|
$14,500.000
|
$14,765.000
|
|
|
SET (TY I)(S=3 FT)(HW= 4 FT)(4:1)(C)
|
EA
|
3.000
|
$11,000.000
|
$7,560.000
|
$13,500.000
|
$13,700.000
|
|
|
SET (TY I)(S=3 FT)(HW= 5 FT)(4:1)(C)
|
EA
|
2.000
|
$12,000.000
|
$8,100.000
|
$20,000.000
|
$20,565.000
|
|
|
SET (TY I)(S=3 FT)(HW= 5 FT)(6:1)(C)
|
EA
|
1.000
|
$14,000.000
|
$9,180.000
|
$18,000.000
|
$18,450.000
|
|
|
SET (TY I)(S= 4 FT)(HW= 4 FT)(4:1) (C)
|
EA
|
2.000
|
$14,000.000
|
$8,100.000
|
$14,500.000
|
$14,765.000
|
|
|
SET (TY I)(S= 4 FT)(HW= 4 FT)(6:1) (C)
|
EA
|
1.000
|
$16,000.000
|
$12,960.000
|
$28,000.000
|
$29,000.000
|
|
|
SET (TY I)(S= 4 FT)(HW= 5 FT)(3:1) (C)
|
EA
|
1.000
|
$14,000.000
|
$8,640.000
|
$10,000.000
|
$10,550.000
|
|
|
SET (TY I)(S= 4 FT)(HW= 5 FT)(4:1) (C)
|
EA
|
1.000
|
$15,000.000
|
$10,800.000
|
$13,000.000
|
$13,200.000
|
|
|
SET (TY I)(S= 5 FT)(HW= 7 FT)(4:1) (C)
|
EA
|
2.000
|
$16,000.000
|
$16,200.000
|
$26,000.000
|
$26,900.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$2,250.000
|
$1,296.000
|
$2,300.000
|
$2,375.000
|
|
|
SET (TY II) (24 IN) (CMP) (4: 1) (C)
|
EA
|
1.000
|
$2,250.000
|
$1,944.000
|
$2,600.000
|
$2,640.000
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
4.000
|
$2,250.000
|
$1,944.000
|
$2,600.000
|
$2,640.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (C)
|
EA
|
1.000
|
$2,750.000
|
$2,160.000
|
$3,100.000
|
$3,165.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
6.000
|
$2,750.000
|
$2,160.000
|
$3,100.000
|
$3,165.000
|
|
|
SHOT BLASTING
|
SY
|
989.000
|
$14.000
|
$12.420
|
$11.500
|
$12.150
|
|
|
REMOV STR (HEADWALL)
|
EA
|
24.000
|
$1,100.000
|
$1,512.000
|
$2,000.000
|
$2,110.000
|
|
|
REMOV STR (PIPE)
|
LF
|
37.000
|
$30.000
|
$32.400
|
$20.500
|
$21.000
|
|
|
REMOV STR (BOX CULVERT)
|
LF
|
33.000
|
$90.000
|
$162.000
|
$155.000
|
$160.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$660,000.000
|
$314,074.870
|
$740,000.000
|
$860,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
7.000
|
$18,000.000
|
$26,487.390
|
$14,500.000
|
$36,000.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
725.000
|
$3.500
|
$4.480
|
$7.650
|
$7.700
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
725.000
|
$1.250
|
$1.080
|
$2.050
|
$5.450
|
|
|
CONC CURB & GUTTER (TY I)
|
LF
|
16.000
|
$75.000
|
$108.000
|
$92.000
|
$95.000
|
|
|
RUMBLE STRIPS (SHOULDER) ASPHALT
|
LF
|
105,475.000
|
$0.200
|
$0.120
|
$0.120
|
$0.200
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
9,070.000
|
$34.000
|
$31.320
|
$29.500
|
$34.300
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
8.000
|
$2,500.000
|
$2,916.380
|
$2,400.000
|
$3,240.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
18.000
|
$1,150.000
|
$1,647.000
|
$1,600.000
|
$1,530.000
|
|
|
MTL BM GD FEN (LONG SPAN SYSTEM)
|
LF
|
100.000
|
$38.000
|
$36.720
|
$34.500
|
$30.000
|
|
|
MTL BM GD FEN TRANS (NON - SYM)
|
EA
|
2.000
|
$1,050.000
|
$1,069.200
|
$1,000.000
|
$1,265.000
|
|
|
CONNECTOR PLATE FOR THRIE BEAM
|
EA
|
6.000
|
$1,050.000
|
$1,053.000
|
$995.000
|
$685.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
1,875.000
|
$2.500
|
$3.240
|
$3.050
|
$2.100
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
6.000
|
$225.000
|
$324.000
|
$305.000
|
$210.000
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
2.000
|
$300.000
|
$324.000
|
$305.000
|
$210.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
24.000
|
$3,600.000
|
$3,213.000
|
$3,000.000
|
$3,500.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
6.000
|
$285.000
|
$324.000
|
$305.000
|
$210.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
15.000
|
$950.000
|
$772.200
|
$730.000
|
$885.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
|
EA
|
3.000
|
$1,200.000
|
$874.800
|
$825.000
|
$950.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
18.000
|
$1,000.000
|
$933.120
|
$880.000
|
$1,030.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P-BM)
|
EA
|
21.000
|
$1,350.000
|
$1,297.080
|
$1,200.000
|
$1,345.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
2.000
|
$1,520.000
|
$1,293.840
|
$1,200.000
|
$1,370.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
|
EA
|
17.000
|
$30.000
|
$25.870
|
$25.500
|
$20.000
|
|
|
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
|
EA
|
17.000
|
$30.000
|
$25.870
|
$25.500
|
$20.000
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
431.000
|
$20.000
|
$5.400
|
$30.500
|
$10.550
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
|
EA
|
190.000
|
$30.000
|
$53.950
|
$51.000
|
$44.300
|
|
|
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
|
EA
|
15.000
|
$30.000
|
$53.950
|
$51.000
|
$44.300
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND
|
EA
|
41.000
|
$120.000
|
$131.760
|
$125.000
|
$155.000
|
|
|
INSTL DEL ASSM (D-SY)SZ 1(YFLX)GND
|
EA
|
44.000
|
$120.000
|
$131.760
|
$125.000
|
$155.000
|
|
|
INSTL DEL ASSM (D-DW)SZ 1(WFLX)GND
|
EA
|
13.000
|
$120.000
|
$131.760
|
$125.000
|
$155.000
|
|
|
INSTL DEL ASSM (D-DY)SZ 1(YFLX)GND
|
EA
|
9.000
|
$125.000
|
$131.760
|
$125.000
|
$155.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND
|
EA
|
85.000
|
$130.000
|
$131.760
|
$125.000
|
$155.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
5,566.000
|
$1.000
|
$1.980
|
$1.350
|
$1.500
|
|
PREFAB PAV MRK TY C (W) (24") (SLD)
|
LF
|
31.000
|
$20.000
|
$54.000
|
$15.500
|
$52.750
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
8.000
|
$275.000
|
$432.000
|
$305.000
|
$420.000
|
|
PREFAB PAV MRK TY C (W) (18")(YLD TRI)
|
EA
|
135.000
|
$42.000
|
$64.800
|
$41.000
|
$63.250
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
1,070.000
|
$10.000
|
$5.400
|
$3.950
|
$5.250
|
|
|
SP MIXES SP-D SAC-A PG70-28
|
TON
|
35,883.000
|
$138.000
|
$132.460
|
$122.150
|
$124.750
|
|
|
TACK COAT
|
GAL
|
42,496.000
|
$5.750
|
$4.790
|
$8.750
|
$6.250
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$10,000.000
|
$9,276.700
|
$8,700.000
|
$8,470.000
|
|
|
HPPM W/RET REQ TY I(W)6"(BRK)(090MIL)
|
LF
|
17,982.000
|
$0.700
|
$0.750
|
$0.620
|
$0.750
|
|
|
HPPM W/RET REQ TY I(W)6"(SLD)(090MIL)
|
LF
|
71,616.000
|
$0.650
|
$0.750
|
$0.600
|
$0.750
|
|
|
HPPM W/RET REQ TY I(Y)6"(SLD)(090MIL)
|
LF
|
71,616.000
|
$0.650
|
$0.750
|
$0.600
|
$0.750
|
|
|
TMA (STATIONARY)
|
DAY
|
110.000
|
$255.000
|
$383.940
|
$205.000
|
$380.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
80.000
|
$100.000
|
$82.920
|
$97.000
|
$87.000
|
|
|
CLEANING STRUCTURE (BENT)
|
EA
|
11.000
|
$1,000.000
|
$1,620.000
|
$1,500.000
|
$1,580.000
|
|
|
CLEANING STRUCTURE (ABUTMENT)
|
EA
|
8.000
|
$800.000
|
$1,620.000
|
$1,500.000
|
$1,580.000
|
|
Totals: |
$8,506,438.450
|
$7,851,871.780
|
$8,248,997.440
|
$8,630,396.880
|