HUTCHINSON SH 136 (0379-01-050)
Items: 90
County: HUTCHINSON
Length: 0.0000 MILES
Highway: SH 136
District: AMARILLO
Control Number: 0379-01-050
DBE Goal: 6.0%
Project: F 2025(753)
Guaranty: $73,000.00
Time: 152 WORKING DAYS
Engineer's Estimate: $3,654,451.25
Date: 05/02/2025 (1 year ago)
Contract Number: 5253217
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Project ID: A00201205
Contract Type: Federal
Project Description: PEDESTRIAN IMPROVEMENTS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ZACHARY MAYER
HUTCHINSON SH 136 (0379-01-050)
Project Name: N/A
Project: F 2025(753)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: 340' WEST OF HOYNE AVE
Limits To: 230' EAST OF CANADIAN DR
Project Description: PEDESTRIAN IMPROVEMENTS
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,654,451.25 | |||
| $3,406,939.22 |
-6.77%
-$247,512.03
|
|||
| $3,458,256.25 |
-5.37%
-$196,195.00
|
1.51%
$51,317.03
|
||
| $3,544,271.53 |
-3.01%
-$110,179.72
|
4.03%
$137,332.31
|
-2.49%
-$86,015.28
|
|
| $3,794,048.81 |
3.82%
$139,597.56
|
11.36%
$387,109.59
|
-7.05%
-$249,777.28
|
|
| $4,434,333.00 |
21.34%
$779,881.75
|
30.16%
$1,027,393.78
|
-16.88%
-$640,284.19
|
|
| $5,444,048.83 |
48.97%
$1,789,597.58
|
59.79%
$2,037,109.61
|
-22.77%
-$1,009,715.83
|
E
Engineer's Estimate
$3,654,451.25
1
Awarded
$3,406,939.22
Over/Under Est:
-6.77%
-$247,512.03
$3,458,256.25
Over/Under Est:
-5.37%
-$196,195.00
Amt Left:
1.51%
$51,317.03
$3,544,271.53
Over/Under Est:
-3.01%
-$110,179.72
Amt Left:
4.03%
$137,332.31
Delta:
-2.49%
-$86,015.28
$3,794,048.81
Over/Under Est:
3.82%
$139,597.56
Amt Left:
11.36%
$387,109.59
Delta:
-7.05%
-$249,777.28
$4,434,333.00
Over/Under Est:
21.34%
$779,881.75
Amt Left:
30.16%
$1,027,393.78
Delta:
-16.88%
-$640,284.19
$5,444,048.83
Over/Under Est:
48.97%
$1,789,597.58
Amt Left:
59.79%
$2,037,109.61
Delta:
-22.77%
-$1,009,715.83
| Subcontractor | Percentage | Amount |
|---|---|---|
| WG ENGINEERING & CONSTRUCTION, LLC | 6.67% | $227,242.85 |
| TRP CONSTRUCTION GROUP, LLC | 3.71% | $126,397.45 |
| DK CONTRACTING, LLC | 2.46% | $83,810.70 |
| BLUE BIRD CONSTRUCTION, LLC | 0.11% | $3,747.63 |
| Total: | 12.95% | $441,198.63 |
Bid Items & Bid Tabulations
90
Total
0 of 90
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $3,000.00 |
| Total: | $4,000.00 |