HUNT CS (0901-22-122)

Items: 37

County: HUNT
Length: N/A
Highway: CS
District: PARIS
Control Number: 0901-22-122
DBE Goal: N/A
Project: BR 2023(660)
Guaranty: N/A
Time: 207 WORKING DAYS
Engineer's Estimate: $1,036,646.77
Date: 06/28/2023 (2 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
JESSE HERRERA
DUSTIN LYDAY
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$1,036,646.77
$1,080,968.31
Over/Under Est: 4.28% $44,321.54
Over/Under Est: 5.85% $60,607.18
Amt Left: 1.51% $16,285.64
Over/Under Est: 10.03% $104,021.73
Amt Left: 5.52% $59,700.19
Delta: -3.96% -$43,414.55
Over/Under Est: 28.07% $291,006.43
Amt Left: 22.82% $246,684.89
Delta: -16.39% -$186,984.70
Subcontractor Percentage Amount
TRAFFIC HIGHWAY MAINTENANCE, LLC 0.50% $5,645.84
Total: 0.50% $5,645.84

Bid Items & Bid Tabulations

37 Total 0 of 37
HUNT  |  CS  |  PARIS  |  0901-22-122  |  06/28/2023  |  $1,036,646.77  |  BR 2023(660)  |  BRIDGE REPL  |  207 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HIGHWAY 19 CONSTRUCTION LLC
RAYFORD'S TRUCK & TRACTOR
HODGES AND SON CONSTRUCTION COMPANY, INC.
EAST TEXAS BRIDGE, INC.
PREPARING ROW
STA 7.100 $3,000.000 $3,000.000 $5,000.000 $5,600.000 $10,000.000
EXCAVATION (ROADWAY)
CY 336.000 $15.000 $25.000 $22.500 $25.000 $30.000
EXCAVATION (CHANNEL)
CY 532.000 $25.000 $25.000 $20.000 $20.000 $30.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 316.000 $49.000 $30.000 $30.000 $30.000 $45.000
BROADCAST SEED (TEMP) (WARM)
SY 1,856.000 $0.100 $0.800 $1.150 $1.000 $0.950
BROADCAST SEED (TEMP) (COOL)
SY 1,856.000 $0.100 $0.800 $1.150 $1.000 $0.950
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 3,712.000 $1.000 $1.180 $1.300 $1.000 $1.250
VEGETATIVE WATERING
MG 12.000 $28.000 $10.000 $1.000 $1.000 $100.000
FL BS (CMP IN PLC)(TY A GR 4) (6")
SY 433.000 $32.000 $54.000 $65.000 $60.000 $40.000
REWORK BS MTL (TY B) (8") (ORD COMP)
SY 662.000 $2.500 $10.000 $15.000 $35.000 $20.000
CEM STABIL BKFL
CY 98.000 $223.000 $250.000 $275.000 $250.000 $325.000
DRILL SHAFT (24 IN)
LF 294.000 $177.000 $133.000 $225.000 $155.000 $175.000
DRILL SHAFT (30 IN)
LF 216.000 $300.000 $196.000 $275.000 $210.000 $230.000
CL C CONC (ABUT)
CY 54.000 $1,435.000 $1,357.000 $1,100.000 $2,000.000 $1,550.000
REINF CONC SLAB
SF 1,040.000 $28.000 $37.000 $35.000 $30.000 $30.000
REINF CONC SLAB (BOX BEAM)
SF 2,486.000 $21.000 $37.000 $25.000 $26.000 $30.000
SHEAR KEY
CY 25.400 $250.000 $400.000 $700.000 $800.000 $700.000
PRESTR CONC BOX BEAM (4B34)
LF 378.000 $375.000 $308.000 $350.000 $380.000 $400.000
PRESTR CONC BOX BEAM (5B34)
LF 189.000 $325.000 $308.000 $350.000 $380.000 $400.000
PRESTR CONC SLAB BEAM (5SB12)
LF 197.500 $250.000 $308.000 $425.000 $335.000 $400.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 597.000 $182.000 $250.000 $140.000 $210.000 $200.000
RAIL (TY T631LS)
LF 338.000 $73.000 $78.000 $100.000 $75.000 $85.000
TYPE A JOINT
LF 53.000 $350.000 $35.000 $150.000 $100.000 $100.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $13,000.000 $15,000.000 $18,000.000 $20,000.000 $20,000.000
MOBILIZATION
LS 1.000 $89,906.070 $100,000.000 $100,000.000 $95,000.000 $130,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $4,000.000 $973.000 $2,000.000 $2,600.000 $7,500.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 108.000 $40.000 $80.000 $40.000 $1.000 $70.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 54.000 $40.000 $45.000 $40.000 $1.000 $80.000
ROCK FILTER DAMS (REMOVE)
LF 162.000 $11.000 $10.000 $10.000 $1.000 $25.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 312.000 $40.000 $55.900 $10.000 $1.000 $35.000
CONSTRUCTION EXITS (REMOVE)
SY 312.000 $7.000 $20.000 $1.000 $1.000 $11.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,013.000 $4.500 $3.750 $3.850 $1.000 $4.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,013.000 $2.000 $1.000 $1.000 $1.000 $1.100
MTL W-BEAM GD FEN (STEEL POST)
LF 200.000 $30.000 $37.000 $35.000 $30.000 $32.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $2,920.000 $3,725.000 $3,500.000 $3,000.000 $3,300.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 10.000 $25.000 $42.000 $100.000 $30.000 $30.000
D-GR HMA TY-C PG64-22
TON 146.000 $180.000 $252.000 $250.000 $250.000 $277.000
Totals: $1,036,646.770 $1,080,968.310 $1,097,253.950 $1,140,668.500 $1,327,653.200